1. eaves over required windows not < _____.

minimum over from the


side & rear property lines
A. 300 MM
B. 600 MM
C. 1000MM
D. 750MM
2. sum of areas of openings must not exceed _____ % of sum of areas
of walls
A. 50
B. 20
C. 40
D. 60
3. Distance of Exits – w/o sprinkler – ____m from exterior exit
door, w/sprinkler will be ____m
A. 45, 50
B. 30, 60
C. 45, 60
4. Width and Height of doors will be not < _____mm in width, not <
______m in height, opening will be 90 degrees and exit way clear width
not < 700mm
A. 900,2.1
B. 800, 2.0
C. 900, 2.0
5. If arcaded bldg, no chaflan reqtd notwithstanding the width of public
street, <________m
A. 12
B. 13
C. 14
D. 15
6. nonstructural facing brick, concrete, tile, metal, etc. attached at the
backing or structural components for the purpose of ornamentation.
A. Brick
B. Face
C. Stone
D. Veneer
7. spacing of rows of seats from back to back – not < ______mm
(standard seating)
A. 840
B. 850
C. 860
8. new construction w/c increases the height or area of an existing
bldg./structures.
A. Addition
B. Renovation
C. Revision
D. Alteration
9. inner courts shall be connected to a street or yard, or by a
passageway – at least how many meters
A. 1.0
B. 1.1
C. 1.2
D. 1.3
E. 2
10. if only 2 exits required, shall be placed distance apart not < ____ of
the perimeter area.
A. 1/3
B. 1/4
C. 1/5
11. Foundations – not < _______ mm below the grade, may encroach
______mm into public sidewalk areas
A. 600, 500
B. 600, 400
C. 500, 300
D. 600, 600
12. Footings must be at least _______ m below grade along national
roads, may project not >______mm beyond Property line.
A. 2.4, 400
B. 2.5, 300
C. 2.3, 400
D. 2.4, 300
13. a permanent roofed structure above a door attached to and
supported by the building and projecting over a wall or sidewalk
A. Balconies
B. Awnings
C. Canopies
14. Work done on any damaged/deteriorated portion of bldg.
A. Alteration
B. Renovation
C. Repair
15. Window openings for room must have at least _____% of the floor
area with a minimum area of _____ sq.m.
A. 20, 1
B. 10, 2
C. 10,1
D. 20,2
16. WHICH IS NOT INCLUDED IN THE EXCEPTION OF BUILDING PERMIT?
A. PRIVATE BUILDING
B. PUBLIC BUILDING
C. INSTITUTIONAL BUILDING
17. WHICH ARE NOT INCLUDED FOR THE REQUIREMENTS FOR
BUILDING PERMIT
A. The use or occupancy of proposed work
B. A description of work to be covered by the permit
C. Description and ownership of the lot- TCT
D. Tax documents
18. WHAT TYPE OF CONSTRUCTION IS FOR WOOD CONSTRUCTION
WITH FIRE RESISTANT MATERIALS 1 HR FIRE RESISTIVE RATING
A. Type II
B. Type III
C. Type IV
D. Type 1
19. WHAT TYPE OF CONSTRUCTION IS FOR WOOD CONSTRUCTION
A. TYPE II
B. TYPE III
C. TYPE I
D. TYPE IV
20. WHAT TYPE OF CONSTRUCTION IS FOR WOOD AND MASONRY
CONSTRUCTION WITH FIRE RESISTANT MATERIALS 1 HR FIRE RESISTIVE
RATING
A. TYPE II
B. TYPE IV
C. TYPE III
D. TYPE I
21. This is where all on site work done
A. Office
B. Construction
C. Plants
22. The width of a stair way if the occupant load of more than 50 shall
not be < ____ m
A. 1.2
B. 1.1
C. 1
D. 1.5
23. The size of room for kitchen must be at least
A. 1.5x2m
B. 1.5x3m
C. 2x3m
D. 1.5x2.1m
24. The size of bathrooms or toilets must be at least an area of _____
sq.m. and ______M minimum distance
A. 1.2, 1.0
B. 1.5,0.9
C. 1.2,0.9
25. The RATING IN which a material can withstand fire
A. Fire Respective Rating
B. Fire Resistive Rating
C. Fire Protective Rating
26. The maximum rise and run of the stairs will be
A. 200MMX200MM
B. 200MMX250MM
C. 200MMX300MM
D. 250MMX250MM
27. THE GENERAL PROVISION OF PD 1096 OR THE NATIONAL BUILDING
CODE OF THE PHILIPPINES ARE?
A. Safe Construction
B. Adequate Environmental Safeguards
C. Maintain building in Safe, sanitary and good working conditions
D. All of the above
29. THE ENFORCEMENT OF PD1096 ON THEIR
RESPECTIVE JURISDICTION IS THE
A. Mayor
B. Architect
C. Building Official
D. City Engineer
29. THE ENFORCEMENT OF PD1096 ON THEIR
RESPECTIVE JURISDICTION IS THE
A. Swing
B. Panel
C. Leaf
30. THE BUILDING PERMIT WILL BE NULL OR VOID IF THE
CONSTRUCTION DIDN'T COMMENCED THE WORK IN A PERIOD OF
A. 6 months
B. 12 months
C. 2 years
D. 3 months
31. THE BUILDING PERMIT WILL BE NULL OR VOID IF THE
CONSTRUCTION HAS BEEN ABANDONED FOR HOW MANY DAYS
A. 30
B. 60
C. 120
D. 80
32. Systematic dismantling of a bldg in whole or part.
A. Reinstallation
B. Demolition
C. Dismantle
33. Stair with a straight run, the landing will be a maximum of _______
m vertical distance
A. 1.5
B. 1.2
C. 1.4
34. Spacing of rows of seats from back to back : rows of 46 seats or
more (continental)
A. 450mm
B. 500mm
C. 520mm
D. 550mm
35. Spacing of rows of seats from back to back : rows of 45 seats or
less (continental)
A. 450mm
B. 500mm
C. 520mm
D. 550mm
36. Spacing of rows of seats from back to back : rows of 35 seats or
less (continental)
A. 450mm
B. 500mm
C. 520mm
D. 500mm
37. Spacing of rows of seats from back to back : rows of 18
seats (continental)
A. 500mm
B. 450mm
C. 520mm
D. 550mm
38. Side aisle width will be a minimum of
A. 1.0m
B. 1.1m
C. 1.2m
D. 1.3m
39. Reviewing Stands, Grandstands, and Bleachers the minimum row
spacing of seats without backrest in open air stand
A. 600
B. 650
C. 700
40. Public Street or alley <______m in width shall be truncated at the
corner “Chaflan”
A. 3.4
B. 3.6
C. 3.5
D. 3.7
41. Private stairways that serve <10 occupants will be a minimum of
_____m
A. 0.60
B. 0.80
C. 0.75
D. 0.70
42. PD 1096 WILL BE ENFORCED BY THE SECRETARY OF
A. UAP
B. PRC
C. MUNICIPALITY
D. PUBLIC WORKS
43. Minimum aisle width if serving only two side
A. 1m
B. 1.2m
C. 1.5m
D. 0.90m
44. Minimum aisle width if serving only one side
A. 800
B. 900
C. 700
45. Min height of mezzanine floor in meter
A. 1.80
B. 2.0
C. 1.75
D. 1.85
46. Means "installation of components of a building/structure"

A. Secure

B. Erection

C. Site work
47. canopy shall be removed ____days after protection no longer

required.

A. 30

B.15

C. 20
48. Located partly in one (1) fire zone and partly in another

A. HIGH RESTRICTIVE FIRE ZONES

B. MODERATE RESTRICTIVE FIRE ZONES

C. HIGH RESTRICTIVE FIRE HAZARDS

D. MODERATE RESTRICITVE FIRE HAZARDS


49. In winding stairsways, the narrower side of the tread will be
__________

A. 150-150mm
B. 200-300mm
C. 150-300mm
50. IN QUALIFICATION FOR BEING AN BUILDING OFFICIAL, YOU MUST
HAVE A DIVERSIFIED WORKING EXPERIENCE OF AN ARCHITECT OR
ENGINEER FOR HOW MANY YEARS?

A. 6
B. 4
C. 5
D. 7
51. IN QUALIFICATION FOR BEING AN BUILDING OFFICIAL, YOU MUST
BE A REGISTERED ?

A. Architect
B. Engineer
C. Urban Planner
D. Landscape Architect
E. A and B
52. IN QUALIFICATION FOR BEING AN BUILDING OFFICIAL, YOU MUST
BE A MEMBER OF A ACCREDITED ORGANIZATION OF NOT LESS THAN
HOW MANY YEARS

A. 2
B. 1.5
C. 3
D. 5
53. HOW MANY SETS OF PLANS AND SPECIFICATION ARE NEEDED FOR
THE REQUIREMENTS OF BUILDING PERMIT?

A. 5
B. 4
C. 6
D. 7
54. HOW MANY SETS OF PLANS AND SPECIFICATION ARE NEEDED FOR
THE REQUIREMENTS OF BUILDING PERMIT?

A. 12 days upon payment


B. 15 days upon payment
C. 14 days upon payment
D. 30 days upon payment
55. Handrails in stairs will be _________ MM

A. 800-900
B. 700-900
C. 900-1200
56. Groups H, I occupancies w/o seats, line of travel to exit door by an
aisle is not > ______ m

A. 45
B. 30
C. 60
57. For Protective Nets/Screen the G.I wire gauge must be
________mm mesh _____ net; canvas

16. 38 mm/ nylon


16.37 mm / steel
16.39 mm/ nylon
16.38 mm/steel
58. for Protection of Pedestrians during Construction or
Demolition Fences must be not < _____mabove grade

A. 2.3
B. 2.2
C. 2.4
D. 2.5
59. For Protection of Pedestrians during Construction or
Demolition Canopies must _______m above the railway, live load 600
kg per sq.m.

A. 2.5
B. 2.6
C. 2.4
D. 2.3
60. for Protection of Pedestrians during Construction or Demolition
the Temporary walkway will be at least _____m wide (during
construction)

A. 1.2
B. 1.3
C. 1.4
D. 1.5