Key Milestones Risks to required outcome Mitigating actions


(if applicable)
SCR:3295-Implementation of Negative Interest rates • Delays in completion of EOD jobs in UAT • Continuous monitoring with support and Data
for FCY Current accounts in Finacle. Environments may cause delay in Testing center team to complete EOD on time and
execution. coordinating with testing teams to initiate the
• UAT Parameter Setup Completion Date: 5-Aug-19. testing as on time daily with out delay.
• UAT Completion Date:15-Sep-19.
• BAT Completion Date : 10-Oct-19. • Delay in completion of UAT /BAT due to • Continuous monitoring of defects raised and
• InfoSec RA Completion Date:24-Oct-19. defects raised during Testing. coordinating with vendor to resolve the issues
14-Nov • SRF Approvals Completion Date: 4-Nov-19. on priority basis, so that the UAT/ BAT
Treasury • Parameter setup Completion Date: 13-Nov-19 completes as planned.
• Go-Live Date :14-Nov-19.
• Expecting Issues during creation of • Coordinating with Finance and Parameter setup
negative scheme codes and Dummy team to identify the issues and fix them
accounts for FCY Current accounts in BAU. immediately.

Sensitivity: Internal & Restricted 1


[Risk, Compliance, Operations, GBE, Islamic Banking, PB, WBG & Treasury]

Key Milestones Risks to required outcome Mitigating actions


(if applicable)
SCR-3144: Automation of Loan again trust • Existing Finacle Lien Marking API is not working • Coordinating with Infosys and Finacle
Receipts /Short Term Loans /Loan Against as expected and needs to be fixed by 06-Aug. Support to fix the issue by 06-Aug. else
Invoices /Local Cheque Discounting needs to escalate Vendor management.
settlements in Eximbills.
• UAT and BAT is done by Business team. Delay in • Continuous monitoring of Testing
• UAT Completion Date : 29-Aug-19 UAT/BAT Testing closure by Business team. progress and timely escalations to
• BAT Completion Date : 30-Sep-19. Business Managers to avoid the delay in
• InfoSec RA Completion Date : 6-Oct-19. Testing.
Operations 17-Oct • SRF Approvals Completion Date 15-Oct-19.
• Go-Live Date :17-Oct-19. • Issues can be raised during InfoSec during Risk • Assigning of Issues raised by InfoSec to
Assessment. vendors ( Infosys, China Systems) and
coordinating with them to fix the issues
on priority basis, so that the Go-Live is
not impacted

Sensitivity: Internal & Restricted 2


[Risk, Compliance, Operations, GBE, Islamic Banking, PB, WBG & Treasury]

Key Milestones Risks to required outcome Mitigating actions


(if applicable)
SCR-3284: Inward Non STP Transactions – • Outward FTS transactions are not processing in • Escalations done to the FTS Support
Corporate FTS Environment and this issue needs to be manager and to IT Manager
• UAT Completion Date : 15-Aug-19 fixed by 06-Aug to complete the UAT.
• InfoSec RA Completion Date : 09-Aug-19
• SRF Approvals Completion Date :20-Aug-19.
• Parameter Setup Completion Date:21-Aug- • Any issues raised during RA will be
19 • Issues raised by InfoSec during Risk Assessment reported to vendors and Internal
22-Aug • Go-Live Date :22-Aug-19. initiating from 05-Aug to 09-Aug-2019 development team and coordinated to
Operations
fix the issues on priority basis, so that
the SCR will be implemented as
planned .

Sensitivity: Internal & Restricted 3


[Risk, Compliance, Operations, GBE, Islamic Banking, PB, WBG & Treasury]

Key Milestones Risks to required outcome Mitigating actions


(if applicable)

Enable AMEX card payments from Digital • For implementing Temporary solution Amex • Requested FTS team to get the Amex card
Banking, Mobile banking, Finacle, and FTS card BINs setup needs to done and RAK bank BINs from Central bank as they only have
FTS team don’t have Amex card BINs access to CB FTP Portal by 04-Aug-2019.
• CB Notification Date: 25-Mar-19
• SCR Initiation Date: 08-Jul-2019 • Amex card Details needs to added in Digital • Coordinating with business team to
and Mobile banking screens in Pay cards implement the change to bypass adding
Temporary Solution: menu. Amex card Details in Digital and Mobile
Adding prefix ‘0’ to the 15-digit Amex card Banking screens.
TBD number while adding Amex card in Pay bills
and process the transaction.
This change needs to be implemented with • Business team is requesting for a popup • This message can be added in permanent
PCR message “add ‘0’ as prefix to 15-digit card solution only as changes needs to be done
PCR Implementation Date: TBD number”. in both Digital and Mobile banking
Applications. Discussing with Business to
Operations
implementing temporary solution without
pop up message.

Permanent solution:
Requires changes in Digital banking ,Mobile • Modification in validation for 16-digit card • BRD circulated to business stakeholders
TBD Banking, Finacle and FTS systems. number needs to be done in Mobile banking and received concurrence from
by Infosys as Internal development team is Operations, Remittance, Digital banking
BRD for Completion Date: 30-Jul-19 not having bandwidth to take new changes teams and waiting for approval from
BRD Approvals Date: 08-Aug-19 and Infosys requested for Approved BRD to Architecture team.
provide estimated efforts.