ELECTRICAL CABLING

&
UPS INSTALLATION

Presented by :
Muhammad Shahbaz
Senior Transmission Supervisor
VIDEO/ERD
• After attending this training, the participants would be
able to learn

Technical Ethics for working


Importance of Electrical Cabling
UPS Installation Guide
Use of Multi-Meter
Technical Ethics for working

• Use right tool for right job.


• Before using your tool, inspect it .
• Keep it sharp.
• Always maintain a neat and dry power tool
storage space.
Use right tool for right job
Use right tool for right job
Use right tool for right job
Use right tool for right job
Use right tool for right job
Use right tool for right job
Use right tool for right job
Use right tool for right job
Technical Ethics for working
• Use right tool for right job.
• Before using your tools, inspect it .
• Keep it sharp.
• Always maintain a neat and dry power tool
storage space.
Tools Inspection
Technical Ethics for working
• Use right tool for right job.
• Before using your tools, inspect it .
• Keep tools sharp.
• Always maintain a neat and dry power tool
storage space.
Keep tools sharp
Technical Ethics for working
• Use right tool for right job.
• Before using your tools, inspect it .
• Keep tools sharp.
• Always maintain a neat and dry power tool
storage space.
Use right tool for right job
Multimeter
Use Of Multimeter
A multi-meter is used to make various electrical measurements,
such as
• AC and DC voltages
• DC current
• Resistance

It is called a multi-meter because it combines


the functions of a voltmeter, ammeter
and ohmmeter.
Use Of Multimeter
Voltage Measurement Using Multi-meter
Use Of Multimeter
Current Measurement Using Multi-meter
Use Of Multimeter
• Resistance Measurement
Use Of Multimeter
Multi-meters may also have other functions, such
as
• Diode Testing
• Continuity tests
ELECTRICAL CABLING
Loose plugs and sockets, low quality power
extensions, multi plugs and improper cabling are
a major source of customer downtime.

Properly done power cabling can save many


future downtimes and field visits.
ELECTRICAL CABLING
• Multi Shoe Plug is not permitted.
• No loose connections in sockets and with plugs.
• Extension Boards should be avoided.
• Choose suitable/proper sockets for plugs.
• Separation between Power and Data Cables
ELECTRICAL CABLING
Never install a multi plug to connect plugs of routers, ONT and
adapters.

Cheap multi plugs have loose contacts and cause sparks resulting
in damage to equipment and service interruptions.
ELECTRICAL CABLING
• Multi Shoe Plug is not permitted.
• No loose connections in sockets and with
plugs.
• Extension Boards should be avoided.
• Choose suitable/proper sockets for plugs.
• Separation between Power and Data Cables
ELECTRICAL CABLING

No loose connections in sockets and with plugs


ELECTRICAL CABLING
• Multi Shoe Plug is not permitted.
• No loose connections in sockets and with plugs.
• Extension Boards should be avoided.
• Choose suitable/proper sockets for plugs.
• Separation between Power and Data Cables
ELECTRICAL CABLING
• If an extension wire is to be installed, make sure that it is of good quality and
all contacts are strong enough. Insert a plug in the socket and pull it back. If
this comes out easily, then contacts and grips are not good. Such an
extension should not be used.
ELECTRICAL CABLING
• Multi Shoe Plug is not permitted.
• No loose connections in sockets and with plugs.
• Extension Boards should be avoided.
• Choose suitable/proper sockets for plugs.
• Separation between Power and Data Cables
ELECTRICAL CABLING
ELECTRICAL CABLING
ELECTRICAL CABLING
• Multi Shoe Plug is not permitted.
• No loose connections in sockets and with plugs.
• Extension Boards should be avoided.
• Choose suitable/proper sockets for plugs.
• Separation between Power and Data Cables
ELECTRICAL CABLING
Types Of Nayatel UPS
Nayatel Ups

Cyber Power
Nayatel UPS

APC
Nayatel UPS

Plastic Body UPS


Nayatel UPS

Metal Body 70 watt UPS


Nayatel UPS

Metal Body 50 watt UPS


Nayatel UPS

Huawei UPS
Installation Of 70w Ntl Ups
Installation Of 70w Ntl Ups

Electrical Specifications:

Unit Name: 70W-NTL UPS


Nominal Input Voltage: 220V AC
Input Frequency: 50Hz
Output DC Voltage: 12.5V DC (inline mode)
Low cut 10.5 V
High cut 14.5 V
Total Wattage of Unit: 70W
Load Current: 3 Amp
Battery Charging Current: 200 TO 800 mAh Max
Charging Method PWM (pulse width modulation)
Battery Capacity: 12V 12AH
Installation Of 70w Ntl Ups
Mechanical:

Weight:
Unit Weight: 4.75 Kg
Battery Weight: 3.6 Kg
Net Weight: 8.35 Kg

Dimensions of UPS:
Width: 293mm
Height: 257mm
Depth: 105mm
Installation Of 70w Ntl Ups
Installation Procedure
• Material Required
1. Marking Dye
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 03)
6. Rawal Plugs (Qty 03)
7. Hammer Medium
8. Drill Machine
9. Drill bit 4mm
10. Screw Driver
Installation Of 70w Ntl Ups
Installation Procedure
• Material Required
1. Marking Dye
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 03)
6. Rawal Plugs (Qty 03)
7. Hammer Medium
8. Drill Machine
9. Drill bit 4mm
10. Screw Driver
Installation Of 70w Ntl Ups
Installation Procedure
• Material Required
1. Marking Dye
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 03)
6. Rawal Plugs (Qty 03)
7. Hammer Medium
8. Drill Machine
9. Drill bit 4mm
10. Screw Driver
Installation Of 70w Ntl Ups
Installation Procedure
• Material Required
1. Marking Dye
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 03)
6. Rawal Plugs (Qty 03)
7. Hammer Medium
8. Drill Machine
9. Drill bit 4mm
10. Screw Driver
Installation Of 70w Ntl Ups
Installation Procedure
• Material Required
1. Marking Dye
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 03)
6. Rawal Plugs (Qty 03)
7. Hammer Medium
8. Drill Machine
9. Drill bit 4mm
10. Screw Driver
Installation Of 70w Ntl Ups
Installation Procedure
• Material Required
1. Marking Dye
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 03)
6. Rawal Plugs (Qty 03)
7. Hammer Medium
8. Drill Machine
9. Drill bit 4mm
10. Screw Driver
Installation Of 70w Ntl Ups
Installation Procedure
• Material Required
1. Marking Dye
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 03)
6. Rawal Plugs (Qty 03)
7. Hammer Medium
8. Drill Machine
9. Drill bit 4mm
10. Screw Driver
Installation Of 70w Ntl Ups
Installation Procedure
• Material Required
1. Marking Dye
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 03)
6. Rawal Plugs (Qty 03)
7. Hammer Medium
8. Drill Machine
9. Drill bit 4mm
10. Screw Driver
Installation Of 70w Ntl Ups
Installation Procedure
• Material Required
1. Marking Dye
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 03)
6. Rawal Plugs (Qty 03)
7. Hammer Medium
8. Drill Machine
9. Drill bit 4 mm
10. Screw Driver
Installation Of 70w Ntl Ups
Installation Procedure
• Material Required
1. Marking Dye
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 03)
6. Rawal Plugs (Qty 03)
7. Hammer Medium
8. Drill Machine
9. Drill bit 4mm
10.Screw Driver
Installation Of 70w Ntl Ups
INSTALLATION INSTRUCTIONS

 70W NTL UPS is wall mounted UPS.

To install the unit on wall follow instructions below:


a) Mark a suitable place on wall free from direct
sunlight, heater, water seepage, dust etc.
b) Place the dye on the wall. Please ensure that dye is placed
horizontal properly.
c) Mark the holes on wall using lead pencil.
Installation Of 70w Ntl Ups
INSTALLATION INSTRUCTIONS
a) Mark a suitable place on wall free from direct sunlight,
heater, water seepage, dust etc.
b) Place the dye on the wall. Please ensure that
dye is placed horizontal properly.
c) Mark the holes on wall using lead pencil.
d) Remove dye and drill holes at marked places.
e) Hammer rawal plugs in each hole.
f) Tighten one wooden screw at top hole till its head remains
off about 0.25 inches from surface of wall.
g) Open the lid of UPS.
Installation Of 70w Ntl Ups
INSTALLATION INSTRUCTIONS
a) Mark a suitable place on wall free from direct sunlight,
heater, water seepage, dust etc.
b) Place the dye on the wall. Please ensure that dye is
placed horizontal properly.
c) Mark the holes on wall using lead pencil.
d) Remove dye and drill holes at marked places.
e) Hammer rawal plugs in each hole.
f) Tighten one wooden screw at top hole till its head
remains off about 0.25 inches from surface of wall.
g) Open the lid of UPS.
Installation Of 70w Ntl Ups
INSTALLATION INSTRUCTIONS
a) Mark a suitable place on wall free from direct sunlight,
heater, water seepage, dust etc.
b) Place the dye on the wall. Please ensure that dye is
placed horizontal properly.
c) Mark the holes on wall using lead pencil.
d) Remove dye and drill holes at marked
places.
e) Hammer rawal plugs in each hole.
f) Tighten one wooden screw at top hole till its head
remains off about 0.25 inches from surface of wall.
g) Open the lid of UPS.
Use a Polythene bag
Installation Of 70w Ntl Ups
INSTALLATION INSTRUCTIONS
a) Mark a suitable place on wall free from direct sunlight,
heater, water seepage, dust etc.
b) Place the dye on the wall. Please ensure that dye is
placed horizontal properly.
c) Mark the holes on wall using lead pencil.
d) Remove dye and drill holes at marked places.
e) Hammer Rawal plugs in each hole.
f) Tighten one wooden screw at top hole till its head
remains off about 0.25 inches from surface of wall.
g) Open the lid of UPS.
Installation Of 70w Ntl Ups
INSTALLATION INSTRUCTIONS
a) Mark a suitable place on wall free from direct sunlight,
heater, water seepage, dust etc.
b) Place the dye on the wall. Please ensure that dye is
placed horizontal properly.
c) Mark the holes on wall using lead pencil.
d) Remove dye and drill holes at marked places.
e) Hammer Rawal plugs in each hole.
f) Tighten one wooden screw at top hole till
its head remains off about 0.25 inches
from surface of wall.
g) Open the lid of UPS.
Installation Of 70w Ntl Ups
INSTALLATION INSTRUCTIONS
a) Mark a suitable place on wall free from direct sunlight,
heater, water seepage, dust etc.
b) Place the dye on the wall. Please ensure that dye is
placed horizontal properly.
c) Mark the holes on wall using lead pencil.
d) Remove dye and drill holes at marked places.
e) Hammer Rawal plugs in each hole.
f) Tighten one wooden screw at top hole till its head
remains off about 0.25 inches from surface of wall.
g) Open the lid of UPS.
Installation Of 70w Ntl Ups

INSTALLATION INSTRUCTIONS
d) Remove dye and drill holes at marked places.
e) Hammer Rawal plugs in each hole.
f) Tighten one wooden screw at top hole till its head remains
off about 0.25 inches from surface of wall.
g) Open the lid of UPS.
h) Place the device on screw aligning its bottom
holes to that in wall.
i) Tight the wooden screws in bottom holes of device firmly.
j) Please check that device is fixed properly and not loose on
wall.
Installation Of 70w Ntl Ups
INSTALLATION INSTRUCTIONS
d) Remove dye and drill holes at marked places.
e) Hammer Rawal plugs in each hole.
f) Tighten one wooden screw at top hole till its head
remains off about 0.25 inches from surface of wall.
g) Open the lid of UPS.
h) Place the device on screw aligning its bottom holes
to that in wall.
i) Tight the wooden screws in bottom holes
of device firmly.
j) Please check that device is fixed properly and not
loose on wall.
Installation Of 70w Ntl Ups
INSTALLATION INSTRUCTIONS
d) Remove dye and drill holes at marked places.
e) Hammer Rawal plugs in each hole.
f) Tighten one wooden screw at top hole till its head
remains off about 0.25 inches from surface of wall.
g) Open the lid of UPS.
h) Place the device on screw aligning its bottom holes
to that in wall.
i) Tight the wooden screws in bottom holes of device
firmly.
j) Please check that device is fixed
properly and not loose on wall.
Commissioning
After installation check the following parameters of UPS:
1. Plug the mains 220V AC cord to the unit and
connect it to electrical outlet having proper
earth.
2. Observe the output voltage at both terminals with a multi-meter. It
should be 12.5V.
3. Switch off the mains supply and observe for availability of output.
It should range from 12V to 13.4V and BO LED should glow.
4. If device is not providing DC output then open the UPS Front
cover.
5. Check that all terminals are connected properly and power the
device. In case of any problem, replace the unit and submit faulty
unit to Electronic Repair Department.
Installation Of 70w Ntl Ups

Verify UPS input source voltages

WAPDA GENERATOR OR CUSTOMER UPS


Installation Of 70w Ntl Ups

CHECK AC VOLT WITH VOLT METER


Commissioning

CAUTION
YOU HAVE TO CHECK THESE VOLTAGES ON MAINS LINE
SO BE CAREFUL FOR ELECTRIC SHOCK
Commissioning

After installation check the following parameters of UPS:

1. Plug the mains 220V AC cord to the unit and connect it to


electrical outlet having proper earth.
2. Observe the output voltage at both terminals
with a multi-meter. It should 12.5V
3. Switch off the mains supply and observe for availability of output. It
should range from 12V to 13.4V and BO LED should glow.
4. If device is not providing DC output then open the UPS Front
cover.
5. Check that all terminals are connected properly and power the
device. In case of any problem, replace the unit and submit faulty
unit to Electronic Repair Department.
Commissioning
After installation check the following parameters of UPS:

1. Plug the mains 220V AC cord to the unit and connect it to electrical
outlet having proper earth.
2. Observe the output voltage at both terminals with a multi-meter. It
should be 12.5v
3. Switch off the mains supply and observe for
availability of output. It should range from 12V to
13.4V and BO LED should glow.
4. If device is not providing DC output then open the UPS Front cover.
5. Check that all terminals are connected Properly and power the
device. In case of any problem, replace the unit and submit faulty
unit to Electronic Repair Department.
Commissioning

After installation check the following parameters of UPS:

1. Plug the mains 220V AC cord to the unit and connect it to


electrical outlet having proper earth.
2. Observe the output voltage at both terminals with a multi-meter.
It should be 12.5V
3. Switch off the mains supply and observe for availability of output.
It should range from 12V to 13.4V and BO LED should glow.
4. If device is not providing DC output then open
the UPS Front cover.
5. Check that all terminals are connected Properly and power the
device. In case of any problem, replace the unit and submit
faulty unit to Electronic Repair Department.
Commissioning
After installation check the following parameters of UPS:

1. Plug the mains 220V AC cord to the unit and connect it to


electrical outlet having proper earth.
2. Observe the output voltage at both terminals with a multi-meter. It
should be 12.5V
3. Switch off the mains supply and observe for availability of output.
It should range from 12V to 13.4V and BO LED should glow.
4. If device is not providing DC output then open the UPS Front
cover.
5. Check that all terminals are connected Properly
and power the device. In case of any problem,
replace the unit and submit faulty unit to
Electronic Repair Department
Installation Of 70w Ntl Ups
INSTALLATION INSTRUCTIONS
Connect the output cables to the load (ONT or router)
and please ensure that pin is well settle in DC
receptacle. Route the cables properly.
Installation Of 70w Ntl Ups

Please ensure that unit is placed as near to load as


possible. No heat source or wet source should
be closer to the unit.
Installation Of 70w Ntl Ups

IMPORTANT
TOTAL LOAD TO UNIT SHOULD NOT EXCEED MORE THAN 3 AMP IN
ANY CONDITIONS. EXCESSIVE LOAD WILL DAMAGE THE UNIT.
Light Status Of 70/50 W LED
LED Description
indicator
PSU-FAIL (Power fail) : there is some problem in unit board

PO (Power up) : shows that unit is properly power up

ST (Status) shows normal behavior of unit .It should blink

BO (Backup Operation) Its blink on battery back up mode

) Battery is being charged. It should blink

BF (Battery Fault) Battery faulty or battery is not connected


Reasons Of Burning Fuse
Reasons Of Burning Fuse

Charging Fuse SCR


1 light fluctuating
2 Diode faulty
3 SCR faulty
Diode

Battery Fuse
Battery getting
high Amp above
1 Amp it should
be 200 to 800
mAh
Trouble Shooting Low Backup Of 70 W

Remove ac
Check plug and
Check battery connect 12volt Change
Check fuse volt 4amp bulb at
Above if Voltage drop battery or
battery near ok increas Yes battery
11v below 12 send to
heat e during terminal check
volt ERD
chargin volt direct on
sink
g battery
terminals

Below No No
burn
11 v drop

Continue
Send to ERD charging
Installation Of Huawei Ups

ONT UPS
UMC
INSTALATION OF Huawei UPS

Electrical Specifications:

Unit Name: Huawei HW-Li4Ah


Nominal Input Voltage: 13.8 v DC
Output DC Voltage: 11.1V DC
Low cut off 10.5 V
High cut off 12.2 V
Total Wattage of Unit: 45W
Load Current: 2 Amp
Battery Charging Current: 200 TO 800 mAh Max
Battery Capacity: 11.1V 4AH
Installation Of Huawei Ups

Mechanical:

Weight:
Unit Weight: 0.45Kg

Dimensions of UPS:
Width: 105mm
Height: 50mm
Depth: 35mm
Installation Of Huawei Ups
Installation Procedure
• Material Required
1. Marking Dye
90mm
2. Measuring Tape
3. Level Meter
4. Lead Pencil
5. Wooden Screw 1.5 Inches (Qty 02)
6. Rawal Plugs (Qty 02)
7. Hammer Medium
8. Drill Machine
9. Drill bit 1/4mm
10. Screw Driver
INSTALATION OF Huawei UPS
INSTALLATION INSTRUCTIONS

a) Mark a suitable place on wall free from direct sunlight, heater,


water seepage, dust etc.
b) Place the dye on the wall. Please ensure that dye is placed
vertical properly.
c) Mark the holes on wall using lead pencil.
d) Remove dye and drill holes at marked places.
e) Hammer rawal plugs in each hole.
f) Tighten one wooden screw at top hole till its head remains off
about 0.25 inches from surface of wall.
INSTALATION OF Huawei UPS

ups Mounted on wall


Installation Of Huawei Ups
UPS monitoring port

Out put 11.1 volt Input 13.8volt

UPS Connector And Port


Installation Of Huawei Ups

Use of UPS Monitoring Port


Installation Of Huawei Ups

Inside Huawei Ups


Troubleshooting Of Huawei UPS

RED ALARM LIGHT ON


*UPS IS ABNORMAL BEEP BUZZER

*THE BATTERY IS OVER CHARGED

*BATTERY TEMPERATURE EXCEEDS

*BATTERY FAULTY

RED LIGHT OFF

UPS IS NORMAL
Troubleshooting Of Huawei UPS
DISCHARGE LIGHT ON

THE BATTERY IS DISCHRGING ON


BACKUP MODE WITH LOAD

DISCHARGE LIGHT OFF

THE UPS IS ONLINE MODE


Troubleshooting of Huawei UPS

Red light ON UPS Monitoring Cable Discharging light ON


when ups on
backup mode
Installation Of Huawei Ups

Adaptor for Huawei ups

Always use same rating for ups


Troubleshooting of Huawei UPS
IF CHARGING LIGHT ON

THE BATTERY BEING CHARGED


IF CHARGING LIGHT BLINK
ADOPTORE IS NOT 13.8VOLT RATING
IF CHARGING LIGHT OFF

NOW BATTERY IS FULLY CHARGED


OR
CHECK AC PLUG PROPERLY INSERTED

IF AC PLUG NOT FIT PRORERLY


DISCHAGING LIGHT GOES ON
Troubleshooting of Huawei UPS
NO LIGHTS ON

WHEN UPS FULLY CHARGED ALL LIGHTS GOES OFF


AND UPS RUNNING IN INLINE MODE

TESTING
PULL OUT AC PLUG OR SWITCH OFF MAIN AC
DISCHARGING LIGHT WILL GO ON
Troubleshooting of Huawei UPS

Services running smooth NO LIGHTS ON