Академический Документы
Профессиональный Документы
Культура Документы
INTRODUCTION
MUMBAI METRO LINE 03, PACKAGE -05.
GROUP 4
KENIL BHIMANI, UC0315
AASHIR KHAN, UC1615
M AYA N K J A I N , U C 2 5 1 5
OVERVIEW
Property
Stakeholder ASIDE 1810m
developm
contribution… funding /
ent and
MMRDA BKC
impact fee
grant
Sub4%
debt
3%
by Centre 1241m
5%
Sub debt Dharavi
by State JICA loan
7% 57%
Equity by
MMRC Expected Cost- 23,136 crore
and StateEquity by Expected Daily Ridership- 17 Lakh
10% Centre
11% Cost Break-down of the Project Rolling Stock- Alstom
MAPLE
CONSULTANT
L&T STEC HCC- OJOC DOGUS- CEC-ITD- J.Kumar- J.Kumar- L&T STEC
(JV) (JV) SOMA TATA CRTG (JV) CRTG (JV) (JV)
CBS_UGC_01 CBS_UGC_02 CBS_UGC_03 CBS_UGC_04 CBS_UGC_05 CBS_UGC_06 CBS_UGC_07
Scope of Work
The UGC-05 package of Mumbai Metro Rail Corporation Ltd. Consists of Design and Construction of Underground
Stations at Dharavi, BKC, Vidyanagri, Santacruz and associated tunnels. This package starts from Station Dharavi, Mumbai
and ends at Mid-ventilation shaft at Agreepada.
Contract Period: 18th July 2016 to 21st Jan 2021 (1638 Days)
Tunnel Length: 3724 x 2= 7448 meters Qualified CEC-ITD- Dogus- J.Kumar- L&T- STEC HCC-OJSC
Contract value: ₹ 28,177,299,998 /- Bidder TATA SOMA China Rail Moscow
Group
UCG_01 3712.12 3350.26 3606.06
UCG_02 2919.78 3418.89 3088.23 2713.90
UCG_03 3194.29 2720.14 3531.19
UCG_04 3000.89 3057.04 3375.22 3213.01
UCG_05 3088.23 2988.41 3425.13 3418.89
UCG_06 2302.14 2489.30 2245.99 2639.03 2420.67
UCG_07 2757.57 2552.94
MID-
VENTILLATI
ON SHAFT
BANDRA-KURLA
COMPLEX
STATION
13.1 RIGHT TO VARY 13.1.1 Variations may be initiated by the Engineer at any time prior to issuing the
Taking-Over Certificate for the Works, either by an instruction or by a request for the
Contractor to submit a proposal. A Variation shall not comprise the omission of any
work which is to be carried out by others.
13.1.2 The lump sum items included in the Pricing Document shall not be eligible for
revision.
13.1.3 In case the Engineer introduces an item for which the Contract does not
contain any rates or prices applicable to the varied Works, the rate of such items shall
be derived, wherever possible, from the rate for similar items as submitted by the
Contractor under Sub-Clause 13.3.
13.1.4 In the event of the Contractor’s disagreement in respect of any new or revised
rates, the Engineer shall fix such rates or prices as appropriate and shall notify the
Contractor accordingly, with a copy to the Employer.
13.1.5 Until such time as such rate(s) are agreed or fixed, the Engineer, after
consultation with the Employer, shall determine the provisional rate(s) to enable
Interim Payment Certificates to be issued by the Engineer.
13.1.6 The Contractor shall execute and be bound by each Variation, unless the
Contractor promptly gives notice to the Engineer stating (with supporting particulars)
that: (i) the Contractor cannot readily obtain the Goods required for the Variation, (ii)
it will reduce the safety or suitability of the Works, or (iii) it will have an adverse
impact on the achievement of the Schedule of Guarantees.
Conditions of
PROCEDURE following provisions:
(a) within 14 days (or such other period as the Engineer may allow) of the Engineer informing
contract - the Contractor in writing of the intention to request a Variation, the Contractor shall notify
the Engineer in writing whether in his opinion the Variation would, if ordered:
fidic (Y) + PCC (i) give rise to any entitlement to an extension of time; or (ii) affect the achievement of any
Items of Payment; or (iii) give rise to any entitlement to additional payment; or (iv) affect the
guarantees of the Contractor set out in Sub-Clause 4.2 of the Particular Conditions of
Contract, and shall submit his proposals for the Engineer’s evaluation.
If the Engineer requests a proposal, prior to instructing a Variation, the Contractor shall
respond in writing as soon as practicable, either by giving reasons why he cannot comply (if
this is the case) or by submitting:
(a) a description of the proposed design and/or work to be performed and a programme for
its execution,
(b) the Contractor’s proposal for any necessary modifications to the programme according to
Sub-Clause 8.3 [Programme] and to the Time for Completion, and
(c) the Contractor’s proposal for adjustment to the Contract Price.
The Engineer shall, as soon as practicable after receiving such proposal (under Sub-Clause
13.2 [Value Engineering] or otherwise), respond with approval, disapproval or comments.
The Contractor shall not delay any work whilst awaiting a response.
Each instruction to execute a Variation, with any requirements for the recording of Costs,
shall be issued by the Engineer to the Contractor, who shall acknowledge receipt.
CLAUSE
NO. CLAUSE DESCRIPTION
13.9 PRICE CENTRES 13.9.1 It has to be ensured that the whole of the Works (except items included in
Schedule of Provisional Sums) have been covered by the Price Centres and the Items
of Payment included in each Price Centre. In order to meet the Employer’s
Requirements, and if it becomes necessary during the course of execution, to add
another Price Centre or to add more Items of Payment in the Price Centre, the Lump
Sum Contract Price of the whole of Works, shall remain unaltered, shall be
redistributed amongst the affected Price Centres and further redistributed under the
Items of Payment in each Price Centre.
13.9.2 Other than for Sub-Clause 13.8 [Adjustments for Changes in Cost], the liability
of the Employer will be limited to the fixed Lump Sum Contract Price already
accepted and the Contractor will have no right to claim anything over and above the
Lump Sum price for any such addition of Price Centre or Items of Payment in any
Price Centre.
According to the calculated price as per the approved price by both the parties at the time of tendering. (Price center E- 2.11 & 2.13) the implicating
amount is Rs 37,14,73,516.29/- after reducing the cost of tunneling through TBM.
The scope of the Design Report was to examine the effect of coefficient of lateral earth
pressure in the amount of reinforcement. The analysis to be taken into Santacruz Station
and Vidyanagri Station. Thus, 2 scenarios have been developed.
• Scenario (n.1) the geotechnical parameter of competent rock is estimated as K0=0.50.
• Scenario (n.1) the geotechnical parameter of competent rock is estimated as K0=0.33.
All other factors (geotechnical parameters, safety factors, loads, combinations) assumed
are equal.
REINFORCEMENT FOR
EXTERNAL WALLS
(K0=0.50)
CONTRACT PROVISIONS
11 May 2015 The rate of royalty was revised by Revenue and Forests Department vide their notification dated 11th May’15.
On 05th August’16, the Government of Maharashtra, notified for additional payment of 10% to be paid to ‘District
5 August 2016 Mineral Foundation Mumbai Suburban District’ for Development of Land in Mumbai Suburban region under
‘PradhanMantri Kshetra Kalyan Yojna’
The Contractor vide their letter no. JKC-GCC-AAO-P05-LET-170013-A00 dated 14th January’17, intimated the
14 January 2017 Engineer regarding the change in rate of royalties for excavated material, and requested for reimbursement of
additional cost incurred by the Contractor pursuant to clause 13.7 of GCC- Change in Legislature.
The Engineer vide their letter no. GCC-UGC05-LET-000818-A00 dated 16th July’18, rejected the Contractors claim
under clause 13.7 of GCC and stated that the change in Rate of Royalties for Excavated Earth comes under PCC
16 July 2018 clause 13.8.1 and suggested that as this rise in rate is not covered by the price adjustment formula, the rates shall
be deemed to include the amount to cover the contingency of such rise in costs. The Engineer also stated that
being an experienced contractor, it is deemed that contractor had considered such risk in their bid.
The Engineer vide their letter no. GCC-UGC05-LET-000818-A00 dated 16th July’18, rejected the Contractors claim
16 July 2018 under clause 13.7 of GCC and stated that the change in Rate of Royalties for Excavated Earth comes under PCC
clause 13.8.1 and suggested that as this rise in rate is not covered by the price adjustment formula, the rates shall
be deemed to include the amount to cover the contingency of such rise in costs. The Engineer also stated that
being an experienced contractor, it is deemed that contractor had considered such risk in their bid.
The Engineer through their letter no. GCC-UGC05-LET-000818-A01 dated 10th September’18, denied Contractor’s
interpretation of the notification and asked the Contractor to substantiate with evidence, that there has been any
10 September change in the official Government interpretation of the said Law subsequent to Contractor’s submission of Price
2018 Bid. Engineer also stated that the directive was issued only in pursuance of the provision in the existing Law on
Royalty and thus clause 13.7 of GCC is not applicable.
The Contractor in their letter no. GCC-UGC05-LET-000818-A01 dated 20th November’18, substantiated that
20 November changes in rates of royalty as per directive dated 11th May’15 is modification of existing Law on Royalty. Also
2018 Contractor submitted their financial entitlement up to 31st October’18
The Client provided the contractor with a lumpsum amount of 5 Cr. And the further settlement will be done
15 October 2018 afterwards.
VALUATION
The Contractor has submitted its additional amount incurred. The amount payable to the Claimant is works out to Rs. 6,74,89,003/-
based on the additional amount paid by Contractor towards royalty up to 25th September’19.
Cost
Operational
and IDC components
Maintenance
of Project
Replacement Additional
Cost Capital Cost
1. INITIAL
CAPITAL COST 9%
60000
2. IDC 50000
20000
10000
0
2012-13 2013-14 2014-15 2015-16 2016-17 2017-18
3. Additional
Capital Cost
The additional cost in the year 2031
includes the cost of providing stabling
facilities that would be required for
additional rolling stock. These costs have
been brought to the current price level by
using a factor of 5% p.a.
5. Operational
&
Maintenance (ii) Maintenance cost which
include expenditure towards
upkeep and maintenance of
The total O&M cost in the year
2016-17 is estimated at the system and
Rs.4,407 Million. The total O&M
cost in the year 2024-25 is
estimated at Rs 12,390 Million
As per CTS carried out by MMRDA for Mumbai Metropolitan Region,In the year 2017, the
ridership on the proposed Colaba- Bandra- Seepz metro system has been estimated at 10.38
lakh passenger trips per day.
1. Fare box The trip length distribution has been taken on the basis of the available details on land use,
collection corridor composition and existing traffic characteristics in the catchment areas of various
sections of the corridor. Average trip length on the corridor is 12 km.
C. Fare structure:
MMRDA has proposed a fare structure for all mass transit systems in Mumbai for the year 2015
with the increase by 11% every fourth year
Delhi metro rail Corporation (DMRC) has been in metro operation for last 10 years and has
revised metro fares on regular intervals. Recently DMRC also proposed a fare structure for the
year 2016 for Phase 3 of Delhi metro with the increase of 7.5 % at the end of every two years.
Fare 0-3 3-8 8-12 12-15 15-20 20-25 25-30 30-35 >30
MMRDA
2021 12 14 18 22 27 30 33 37 41
Fare 0-2 2-4 4-6 6-9 9-12 12-15 15-18 18-21 21-24 24-27 27-31 31-35
DMRC
2021 12 14 17 22 23 25 28 30 31 34 36 39
0 -13245
0 21297 2130
0 -13955
0 22032 2203
04-Nov-19
0 -14915
0 24501 2450 Additional Capital
Fare Box Revenue
0 -15744
0 25347 2535
Project Completion Cost
0 -17806
0 29160 2916
0 -19063
0 32428 3243
0 -20196
0 33547 3355
0 -21645
0 37307 3731
Land Cost
0 -22971
0 38594 3859
0 -24638
0 42920 4292
/
0 -26191
0 43778 4378
0 -28119
0 48003 4800
0 -32172
0 53688 5369
0 -36752
0 60046 6005
Total Taxes
0 -39281
0 61247 6125
0 -41984
0 67157 6716
0 -44874
0 68500 6850
0 -47962
0 75110 7511
58
0 -51262
0 76613 7661
0 -54790
0 84006 8401
0 -58560
0 856868569
Revenue
from
Project
Fare Box Advt. and Additional Operation
CASHFLOW YEAR Completio Land Cost Total Taxes
n Cost
Revenue Property
Developm
O&M Cost
Capital al Surplus
CASHFLOW 2031-2032
2032-2033
19151
21297
1915
2130
-12407
-13245
0
0
8659
10182
STATEMENT 2033-2034
2034-2035
2035-2036
22032
24501
25347
2203
2450
2535
-13955
-14915
-15744
0
0
0
10280
12037
12137
2036-2037 28188 2819 -16837 -3734 10435
2037-2038 29160 2916 -17806 0 14270
2038-2039 32428 3243 -19063 0 16608
2039-2040 33547 3355 -20196 0 16706
2040-2041 37307 3731 -21645 0 19393
2041-2042 38594 3859 -22971 0 19482
2042-2043 42920 4292 -24638 0 22574
2043-2044 43778 4378 -26191 0 21965
2044-2045 48003 4800 -28119 0 24684
2045-2046 48963 4896 -29941 -30929 -7011
2046-2047 53688 5369 -32172 0 26884
2047-2048 54761 5476 -34386 0 25851
2048-2049 60046 6005 -36752 0 29298
2049-2050 61247 6125 -39281 0 28090
2050-2051 67157 6716 -41984 0 31889
2051-2052 68500 6850 -44874 0 30476
2052-2053 75110 7511 -47962 0 34659
2053-2054 76613 7661 -51262 0 33012
2054-2055 84006 8401 -54790 0 37616
2055-2056 85686 8569 -58560 0 35694
Total -174412 -9250 0 0 369998
R = 3.7 %
Sub Debt by
Equity by Central
Centre Govt.
11% 5%
Equity by
State
EXISTING 10%
FUNDING OF
PROJECT Sub Debt by
State Govt.
JICA loan
57% 7%
Property
ASIDE Developmen
t + Impact
Funding / Stakeholder
MMRDA Contribution Fee
Grant (MIAL)4%
3% 3%