Академический Документы
Профессиональный Документы
Культура Документы
75TPD of Ethanol
By Molasses
Final Year Project (Group-10)
Amir Nauman But 13073123-052
Farrukh Javaid 13073123-053
Supervisor: Dr. Ghulam Abbas
Contents
Pakistan 4 million
Ethanol Production by Molasses in Pakistan
• Use of ethanol in place of tetraethyl lead which acts as anti-knocking agents will
prevent dangerous and poisonous emissions containing lead from petrol.
• Engines of cars do not need any change to use petrol with up to 24 % ethanol in
it.
• Gasoline with ethanol as anti-knocking agent will not cause any damage to the
engine.
Ethanol as Fuel
• Operational Factors
• Supply Chain Factors
• External Factors
Production of Ethanol
• Major processes utilized when ethanol is being produced from corn are
following:
• Wet Milling Process
• Dry Milling Process
• Corn’s components are Starch (61%), Corn oil (4 %), Protein (8%) and Fiber (11%)
and approximately 16% of the corn kernel’s weight is moisture.
Production of Ethanol
• Diethyl ether is the principal by-product of ethyl alcohol with diethyl sulfate. The
diethyl sulfate not only causes an increase in ether formation but is also more
difficult to hydrolyze to alcohol than is ethyl hydrogen sulfate.
• Costly equipment must by used to concentrate the sulfuric acid and over come
the corrosion problems. Such as mild steel lined with brick or lead, pipe lines are
generally of lead; and for concentration absorption column are used.
Direct Hydration Process
• Developed in 1970
• Designed to eliminate the use of Sulfuric Acid
• There are two main processes for the direct hydration of
ethylene to ethanol.
• Vapor-phase contacts a solid a liquid catalyst with
gaseous reactants.
• Mixed - phase processes contact a solid or liquid catalyst
with liquid and gaseous reactants.
Limitations Of Process
• Corrosion problem take place. Copper is widely used for lining the reactors. Some
heat exchangers are made of phosphor bronze.
PFD EQUIPMENTS
• T-108 (Yeast)
• Y-102 (pre-fermenter)
• F-201 (fermenter)
• A-201 (absorber)
• T-201 (storage tank)
• H-302 (Preheater)
• H-301 (Heat exchanger)
• D-301 (Distillation column-I)
PFD EQUIPMENTS
Basis: 75 TPD
Quality of alcohol: 95.4%
• 75000 kg/day
• 93388.12 L/day
• 24670.61 gallons/day
• Molasses usage: 2.5 gallons/gallon of alcohol
• Sulphuric Acid required: 0.17 lb/gallon of alcohol
• Ammonium Sulphate Required: 0.015 lb/gallon of alcohol
Material Balance
• Storage Drum
• Distillation Column-III
• Separator
• Surge drum
• Distillation column-II
• Distillation column-I
• Mash Storage Tank
• Scrubber
• Fermenter
Material Balance Equipments
• Storage tank
M33
M27
M29
M32
Material Balance
• Inlet= Outlet
• M27+M29= M33+M32
• Distillation Column-III
• M27= Product from Distillation Column-II=99.615 TPD
• M29= Alcohol Water mixture from separator= 61.822 TPD
• M32= Bottom product from rectifying column= 86.437 TPD
• M33= Product Stream = 75 TPD
Material Balance
• Separator
M34
M28
M 29
M30
Material Balance
• Inlet=Outlet
• M28+M34=M29+M30
• M28= Bottom Product from Column-II= 32.322 TPD
• M29= Alcohol water mixture = 61.822 TPD
• M30= Fusel Oil from separator= 0.5 TPD
• M34= Water added to separator= 30 TPD
Material Balance
• Surge Drum
M25
M26
M31
Material Balance
• Inlet=outlet
• M25=M26+M31
• M25=Top Product from column-II= 0.5 TPD
• M26= recycle stream= 0.25 TPD
• M31= Aldehyde to storage = 0.25 TPD
Material Balance
M26
M27
M23
M28
M24
Material Balance
• Inlet=outlet
• M23+M26=M24+M25+M27+M28
• M26= recycled stream= 0.25 TPD
• M23= product from column-I= 242.68 TPD
• M24= Bottom Product from Rectification column=110.492 TPD
• M25=Top Product from Rectification column=0.5 TPD
• M27= Middle Product from Rectification Column=99.615 TPD
• M28=Product from Rectification Column to Separator=32.322 TPD
Material Balance
• Distillation Column-I
M23
M21
M22
Material Balance
• inlet=outlet
• M21=M22+M23
• M21= from mash storage tank= 1213.4 TPD
• M22= bottom stream od column= 960.72 TPD
• M23= Top product of the column= 242.68 TPD
Material Balance
M20 M21
Material Balance
• Inlet=outlet
• M20=M21
• M20= From fermenter= 1213.4 TPD
• M21= M20= 1213.4 TPD
Material Balance
M19
• Scrubber
M18
M17
M16
Material balance
• Inlet=outlet
• M18=M16+M17+M19
• M16= Carbon dioxide from fermenter= 61.28 TPD
• M17= water from scrubber to diluter= 27.192 TPD
• M18= Water added to scrubber= 18 TPD
• M19= Carbon dioxide from scrubber= 52.0896 TPD
Material Balance
M11
M10 M12
Material Balance
• Inlet=Outlet
• M10+M11=M12
• M10= molasses from mixer= 65.8338 TPD
• M11= yeast added to vessel = 0.6662 TPD
• M12= feed to pre-fementer = 66.5 TPD
Material Balance
• Yeast Propagator
M12
M14
M13
Material Balance
• Inlet=outlet
• M12+M13=M14
• M12= feed to prefementer= 66.5 TPD
• Fermenter
M16
M14
M20
M15
Material Balance
• Inlet=outlet
• M14+M15=M16+M20
• M14= yeast culture from prefementer= 216.5 TPD
• M15= molasses from mixer-settler = 1048.9896 TPD
• M16= Carbon dioxide produced in fermenter= 52.0896 TPD
• M20= From fermenter to mash storage tank = 1213.4 TPD
Material Balance
• Mixer
M7
M8
M10
M9
Material Balance
• Inlet=Outlet
• M7+M8+M9=M10
• M7 = Sulphuric acid added= 4.619 TPD
• M8 = Molasses from sterilizer= 60.3998 TPD
• M9 = Nutrients added= 0.815 TPD
• M10 = molasses from mixer to yeast= 65.8338 TPD
Material Balance
• Sterilizer
M5 M8
Material Balance
• Inlet=Outlet
• M5=M8
• M5 = from mixer settler to sterilizer= 60.3998 TPD
• M8 = M5 = 60.3998 TPD
Material Balance
• Mixer- Settler
M4
M6
M3
Material Balance
• Inlet=outlet
• M3+M4=M6
• M3 = from diluter to mixer settler= 1254.7704 TPD
• M4 = sulphuric acid to mixer-settler= 4.619 TPD
• M6 = feed from mixer-settler= 1259.3894 TPD
Material Balance
• Diluter
M1
M2 M3
M17
Material Balance
• Inlet=outlet
• M1+M2+M17=M3
• M1 = Molasses to diluter= 325.56 TPD
• M2 = water added to diluter= 902.0184 TPD
• M3 = from diluter to mixer-settler= 1254.7704 TPD
• M17 = water from scrubber= 27.192
Material Balance
21(b)
21(a) Preheater
Energy Balance
• Basis: Room Temperature 25 0C
• Heat in the inlet stream Q 21(A) = m Cp ΔT
Cp for Ethanol=0.6211(Perry’s Chemical Engineering hand Book
m21=1213.4Tons/day
1213.4T 1000kg 1day
m21=
day1T 24 hour
m21=50558.33kg/hr
• Q21=mCpΔT
• Q21=50558.33kg 0.6211kcal 35k
hr kg-k
Energy Balance
Q21=10999062.32kcal/hr
And required Preheat is 98C so,
Q 21(A) = m Cp ΔT
=50558.33kg 0.6211kcal 73k
hr kg-k
Q 21(A) =2292329.85kcal/hr
Heat Required = 2292329.85-1099062.32
= 1193267.53kcal/hr
Energy Balance around Heat
exchanger
Cold fluid
21 21(a)
Hot Fluid
Energy Balance
Q 21(a) = m21 Cp ΔT
ΔT=32-25 =70C 0r 7k
Q21=50558.33kg 0.6211kcal 7k
hr kg-k
Q21=219812.45kcal/hr
Q22(a) =m22 Cp ΔT
M22 =970.72 tons/day
M22 =40446.67 kg/hr
Cp= 0.6211kcal/kg-k
Energy Balance
ΔT=100-25
ΔT=75
Q22(a) = 40446.67kg 0.6221kcal 75k
hr kg-k
Q22(a) = 1884106.85kcal/hr
Q21(a) = 1099062.32 kcal/hr (calculated in Preheater)
Heat gained by cold fluid= Q21(a) – Q21
= 1099062.32 – 219812.45
Q22(b) =879249.87kcal/hr
Energy Balance
Q22(b)= m22CpΔT
Q22(b) = m22CpΔT
T=650C
Energy Balance around Fermenter
16
14
20
15
Energy Balance
Inlet streams:
Q15=heat flow through M15= m15CpΔT
T=260C (T=ΔT)
Cp=3.198 kJ/Kg.0C
m15=1048.9896tons/day
= 43707.9 kg/ hr
Q15= 3634224.469KJ/hr
Heat flow through M14= m14CpΔT
T=270C
Energy Balance
Cp=2.6Jg-1k-1
(This is the Heat capacity of Saccharomyces Serevisiae) by Edwin
H.Battely, Robert L.Putnam Juliana Boerio-Goates
m14=216.5tons/day
=9020.833kg/hr
Cp = 2.6 KJ/Kg.0C
Q14= m14CpΔT
= 9020.833*2.6*27
Q14= 633262.5KJ/hr
Energy Balance
Q20 =m20CpΔT
Cp=0.34KJ/Kg.oC
T=400C
Q20=687593.33KJ/hr
Total output=756351.60KJ/hr
Heat to b removed = 3511135.364kJ/hr
Energy Balance around Sterilizer
5 8
Sterilizer
Energy Balance
Q5=m5CpΔT
m5=60.3998 Tons/day
= 2516.65833kg/hr
ΔT=32-25= 7k
Cp=0.472kcal/ Kg.k
Q5= 8315.039122kcal/hr
Q8=m8CpΔT
m8= 60.3998tons/day
=2516.658kg/hr
Cp=0.472kcal/hr
Energy Balance
ΔT= 75k
Q8=89089.705kcal/hr
27
26
23
28
24
Energy Balance
Q23=m23CpΔT
m23=10111.667kg/hr
Cp=0.8819kcal/kg.k
ΔT=92-25=67k
Q23=597471.1015kcal/hr
Q24=m24CpΔT
m24=110.492tons/day
4603.833kg/hr
Cp=1kcal/kg.k
ΔT=100-25= 75 k
Energy Balance
Q24=4603.833*1*75
= 345287.4975kcal/hr
Q25=m25CpΔT
m25=0.5tons/day
=20.83kg/hr
Cp=0.739kacl/kg.k
T1=25
T2=82
ΔT=57k
Energy Balance
ƛ=2.61*10-5kcal/kg
Q25=(20.83*.739*57) + (20.83*2.61*10 -5)
Q25=877.4226kcal/hr
Q28=m28CpΔT
= 1346.75*0.65028489*75
Q28=65682.83817kcal/hr
Q27=m27CpΔT+mƛ
Cp=0.739kcal/kg
m27=99.615tons/day
=4150.625kg/hr
Energy Balance
ΔT=82-25=57k
ƛ=2.61*10-5kcal/kg
By Putting values,
Q27=190173.4446kcal/hr
Q26=m26CpΔT
m26=0.25tons/day
ΔT=78-25=53k
Cp=0.739kcal/kg
Q26=407.9896kcal/hr
Energy Balance
Heat Out=Q24+Q25+Q27+Q28
= 345287.4975+877.4226+190173.446+65682.83817
= 602021.2029kcal/hr
Heat In= Q23+Q26
= 597471.1015+407.9896
= 597879.0911kcal/hr
Heat provided by steam to Reboiler = Qout – Qin
=602021.2029 – 597879.0911
= 4142.1118 kcal/hr
Energy Balance around Distillation Column
II
23
27
32
Energy Balance
Q27=190173.4446kcal/hr
Q33=m33CpΔT
M33=75tons/day
=3125kg/hr
Cp=0.6211kcal/kg.k
ΔT=78-25=53k
Q33=m33CpΔT
Q33=3125*0.6211*53
Q33=102869.6875kcal/hr
Energy Balance
Q32=m32CpΔT
m32=86.437tons/day
=3601.541667kg/hr
ΔT=100-25=75k
Cp = 1kcal/kg.k
Q32=3601.541667*1*75
=270115.625kcal/hr
Energy Balance
Q29 = m29CpΔT
m29= 61.822tons/day
=2575.916667kg/hr
Cp= 0.65028489kcal/kg.k
ΔT= 90-25=65k
Q29 =2527.916667*1*65
Q29 =108880.1796kcal/hr
Energy Balance
• Reactor Selection
• Process Design
• Mechanical Design
• Heat Calculation
• Specification Sheet
Fermenter Design
Where;
tF’ = Time needed for filling.
tR = Time taken for reaction.
tC’ = Time taken to cool.
tE’ = Time taken for emptying and cleaning.
tB = Time taken for the entire batch operation.
Fermenter Design
Conversion = 70%.
Reaction Time = 48 hrs.
Batch Time (tB) = 52 hrs.
No. of Fermenters used =4
Working Pressure of Vessel (P) = 180 kPa
Temperature of Reaction = 32 oC.
pH = 4.8
Mass flow rate in (ml’) = 6700 Kg/hr.
Density of Material in Fermenter (ρ’) = 1200 Kg/m3.
Volume of Fermenter
Now;
tB = 52 hrs.
Density of Feed (ρ’) = 1200kg/m3
Now;
ml’ =8788.12Kg/hr
Therefore;
Vr = 8788.12 x 52
1200
Vr = 380m3.
Volume of Fermenter
Now;
We allow 30% of volume of fluid as the free space in the
fermenter.
Hence;
With 30% allowance;
VT = 1.30 x Vr
= 1.30 x 380
= 495 m3.
Dimensions
L/D = 1.5
VT = Π x (D2/4) x L
= Π x (D2/4) x 1.5D
= (3/8)Π x (D3)
VT = 495 m3.
Hence, putting in above equation;
D = 7.5m.
L = 1.5*7.5= 11.24 m
Fermenter Design
Now;
Height of Dished Bottom =1m
( From Literature)
Therefore;
•Ellipsoidal Head.
•Torispherical Head.
•Hemispherical Head.
Ellipsoidal head is used for pressure greater than 150 psi and for
less than that pressure we use Torispherical head. That is why we
have selected a Torispherical head.
Torispherical Head
Now,
No. of baffles =6
Height of baffle = 10 m.
VISUAL DISPLAY OF AGITATOR WITH DIMENSIONS
regg
0.75
0.625
0.5m
2.25m
7.5m
VISUAL DISPLAY OF FERMENTER WITH DIMENSIONS
7.5m
FRONT VIEW
VISUAL DISPLAY OF FERMENTER WITH DIMENSIONS
0.68
0.75mm Width of Baffle
2.2 m
2.25m
6.80
7.5mm
TOP VIEW
Heat transfer Calculation
Cooling fluid used = Cooling Water.
Cooling Jacket area available (A) = 17 m2
This area is obtained from Table 7.3 in
“ Chemical Process Engineering Design and Economics by
Harry Silla”
CW inlet temp = 20 oC
CW outlet temp = 28 oC
Approaches;
• ΔT1= 32 – 20 = 12 0C
• ΔT2= 32 – 28 = 4 0C
LMTD = ΔT1 – ΔT2 = 12-4
ln (ΔT1 / ΔT2 ) ln (12/4)
LMTD = 7.28
Heat of Reaction;
Q = ∆Hr = 1.1 x 106 kJ/hr
Design Overall Coefficient=U D=(Ho* Hio)/(Hio+Ho)
=(0.67*60.54)/(0.67+60.54)
=0.662Btu/hr.ft2.0F=170W/m2.0K
Now; Heat Removable by Jacket;
Qj = UD x A x LMTD
= 27938 W
Heat transfer Calculation
Since the heat of reaction (1.1 x 106 kJ/hr) < heat removable
by jacket (2 x 106kJ/hr )
Our design for a cooling jacket is justified in comparison with
a cooling coil.
Now Cooling water Flow rate can be calculated as:
Heat to be removed from reactor = 1.1 x 106 kJ/hr
Identification
Item Fermenter
Item Name R-101
No. Required 4
Function Production of Industrial Alcohol by Fermentation
Operation Batch
Type Jacketed, Stirred Tank Reactor
Volume 495m3
Height 12.24 m
Diameter 7.5m
Temperature 32oC
Working Pressure 1.8 atm
Batch Time 52 hrs
Height to Diameter Ratio 1.5
Type of Head Torispherical
Depth of Dished Bottom 1m
Wall Thickness 0.0214 m
Head Thickness 0.021 m
No. of Baffles 6
Width of Baffle 0.75m
Height of Baffle 10 m
Material of Construction of Fermenter Carbon Steel
Identification
Item Agitator
Type Three 6-bladed Flat Turbine
Number of Blades 6
Impeller Diameter 2.25m
Length of Blade 0.625 m
Width of Blade 0.5 m
Impeller Above Vessel Floor 2.2 m
Speed of Impeller 38 RPM
Power Required 60 hp
Identification
Item Cooling Jacket
Fluid Handled Cooling Water
Inlet Temperature 20oC
Outlet Temperature 28oC
Heat Transfer Area 17 m2
UD 0.662Btu/hr.ft2.0F
Designing of Distillation
Column
Distillation Column Design
(1.16*0.29)/(1.16 - ɵ) + (0.69*1)/(1 - ɵ) =0
So ,
ɵ =1.1076
Distillation Column Design
(1.16*0.89)/(1.16-1.1076) + (1*.11)/(1-1.16) = R m +1
Rm = 18.015
Optimum Reflux Ratio :
From Book “Rules of Thumb for Chemical Engineers)
R = 1.2 – 1.5 of Rm
So we select multiple 1.2
R = 1.2 Rm
R = 21618
Distillation Column Design
Column Efficiency :
uavg = 0.58 Cp
ɑavg = 1.08
E0 = 51 – 32.5 [ log (0.58*1.08)]
Eo = 67.5 %
Actual number of plates = 24/0.675 = 36 plates
Distillation Column Design
ND/NB = [ (86.437/75)(0.69/0.29)(0.00164/0.11)2]0.200
ND/NB = 0.7
ND= 0.7 NB
ND +NB = 36
NB= 36/1.7 = 21
so feed is entering at 21st plate.
Distillation Column Design
Material Balance :
Calculations at Top
Ln = D*Rmin
Ln = 3125*18.015
Ln = 56296.875kg/hr
Vn = L n + D
Vn = 56296.875 + 3125
Vn = 59421.875 kg /hr
Dv = 1.57kg/m3
DL = 803 kg /m3
Distillation Column Design
Calculation on Bottom:
Lm = Ln + F
Lm= 56296.875 + 4150.625
Lm = 60447.5 kg /hr
Vm = Lm – B
Vm = 60447.5 – 3601.541667
Vm = 56845. 95833 kg/hr
Distillation Column Design
ɑ= surface tension
= 21.5
Vn,f = (0.078)[21.5/20]0.2[(803-1.57)/1.57]0.5
Vn,f = 1.79m/sec
For 75% flooding , Actual vapor velocity
Vn = (0.75) (0.79)
Vn = 1.34 m/sec
Distillation Column Design
An = mv/Vn = 10.06/1.34
An= 7.9m2
So for75% flooding, Actual area
Ac = An/ 0.75
Ac = 7.9/ 0.75
Ac = 10.75 m2
So Diameter = D =
D = [( 4* 10.5)/3.1416)]1/2
D= 3.66m
Distillation Column Design
Height of Column:
Hc= (Nact-1) Hs+ ∆H
Hc= (36-1) *(0.61) + 2m
Hc = 23.4
It should b less then 30 m.
Pressure Drop:
H=23.4m
ρL=803kg/m3 , g=9.81m/sec2
Pt = ρgH = 803 * 9.81 * 23.4
Pt = 184pa = 0.124 psi per tray
Designing of Heat
Exchanger
Heat Exchanger Design
For Cold stream:
m21 =50558.33kg/hr
Temperature in = 320C= 305 k
Temperature out = 600C = 333k
pressure = 44.1psi
Cp = 4.605 kJ/kg.k
For Hot stream:
m22 = 40446.67kg/hr
Temperature in = 1000C= 373 k
Temperature out = 680C = 341k
pressure = 120psi
Cp = 4.034 kJ/kg.k
Heat Exchanger Design
Heat load =Q = m21 Cp ΔT
Q = 50558.33*4.605*(60-32)
Q = 6518991.07 kJ/hr
LMTD
LMTD=(341-305) – (373-333)
ln[(341-305)/373-333]
LMTD=37.965K
Heat Exchanger Design
R = (Th, in - Th, out)/ ( Tc, out - Tc, in)
R= (373-341)/(333-305)
R= 1.143
P = (Tc, out - Tc,in)/ ( Th,in - Tc,in)
P = (333-305)/(373-341)
P =0.875
Ft=0.86
True temperature difference
ΔTo.m = LMTD * Ft
ΔTo.m =32.64990C
Heat Exchanger Design
Assumed that
Ud = 500 W/m2.k
Heat transfer Area = Q/(Ud * LMTD)
A = 6518991.07/(500*305.6499)
A= 42.657m2