Академический Документы
Профессиональный Документы
Культура Документы
Built IN Economical
Safety as Repetitive use
Speed
Quality Technology like reshoring /reproping
can be applied
Standard Schemes for optimum
Utilization of material
Less Skilled labour required at job site
L&T - FORMWORK SYSTEM
H-BEAMS
CLIMBING WALL
FLEX
COLUMN
&
ACCESS BFS
STAIR HDT
FLEX
HDT – Heavy Duty Tower
ADVANTAGES
1) Movement of large Wall System in single unit with
crane.
2) Walls of height 7-8 m can be cast in a single pour.
COLUMN
PROP
Table formwork
Floor forms used for Footings & Rafts
LIFTSHAFT FORMWORK
Tunnel formwork system
Application
Tunnel formwork system
Lifting of porticoes
with the help of
crane
MOCK UP ASSEMBLY OF ALUMINIUM FORMWORK FOR
DDA PRIOR TO DESPATCH -
Aluminium formwork system
Water tank
RAIL COLUMNS – HEW, HAZIRA
PROJECT APPLICATIONS
Moving
Formwork
Arrangement
APPLICATION
SYSTEM
L&T- HEAVY DUTY TOWER SYSTEM
STRUCTURE
4 CELL TUNNEL
PROJECT
METRO CORRIDOR MC 1A - DMRC
CASE STUDY 1
PROBLEM
Failure of H – Beams near the compression strut while lifting the
panels.
WallPW-20-95e
Formwork with safe working platform and compression strut
40mm thick
Timber plank
as
compression
strut
Angle should
not be less
than 60º
Normal Lifting
Position
Recommended nail
location for fixing
compression strut
with H-Beam
PROBLEM
Failure of Props in Slab Formwork.
PROBABLE REASONS
Overloading.
Design failure
Quality of the components.
Proper Connection between the components.
Proper lapping of H – Beams at the junctions.
ACTUAL REASONS
PROBABLE REASONS
Overloading
Wrong usage of C Frame as per the scheme drawing issued.
Mis-alignment CG of the Flex table, C frame and the crane sling.
Proper Connection between the components.
ACTUAL REASONS
PROBLEM
Failure of Heavy Duty Tower System.
PROBABLE REASONS
Heavy Loading.
Verticality of the tower.
Missing components at its appropriate location.
Connection between Tower to Tower and permanent structure.
Deviation from scheme drawing.
ACTUAL REASONS
BROKEN PROPS
INTERMEDIATE PROPS
W/O NAILING
.
A PROJECT SITE AFTER ACCIDENT
Accident
happened due to
caving in of slab
connecting these
two pillars when
the scaffolding
below gave way.
Contd………..A PROJECT SITE AFTER ACCIDENT
Contd……….. A PROJECT SITE AFTER ACCIDENT
Contd……….. A PROJECT SITE AFTER ACCIDENT
Ledgers
Swivel Clamps
Twisted swivel
clamp