Академический Документы
Профессиональный Документы
Культура Документы
Work
Breakdown
Gantt Risk
Chart Management
Schedule
In-Country Component Level
Calculating Recapitulation
Budget Sheaf Item and Service TKDN
Job List
KDN KLN TOTAL Item/Service Total
(1) (2) (3) (4) (5) (6)
Item
I. Basic Material 653.042.478,94 0 653.042.478,94 20,45% -
II. Tools 1.188.750.000,00 0 1.188.750.000,00 37,22% -
A. Sub Total of Item 1.841.792.478,94 0 1.841.792.478,94 57,67% -
Service
III. Project Management and Engineer 203.720.000,00 0 203.720.000,00 6,38% -
IV. Work Facility 129.379.618,29 0 129.379.618,29 4,05% -
V. Construction and Fabrication 318.090.519,24 0 318.090.519,24 9,96% -
VI. General Service 700.837.383,54 0 700.837.383,54 21,94% -
B. Sub Total of Service 1.352.027.521,06 0 1.352.027.521,06 42,33% -
C. Total Cost 3.193.820.000,00 0 3.193.820.000,00 100,00% 100,00%
Quantity List
UNIT TOTAL
NO JOB LIST UNIT VOL. COST COST
(Rp) (Rp)
I II III IV V VI
I. General Item
1), Mobilisasi dan Demobilisasi Ls 1,00 117.645.000,00 117.645.000,00
2), Pengukuran Trace Jaringan Pipa KM 12,50 4.950.000,00 61.875.000,00
3), Shop Drawing dan As Built Drawing (ABD) Ls 1,00 24.200.000,00 24.200.000,00
Sub-Total I 203.720.000,00
V. Plumbing Job
1), Pengadaan Pipa GI Φ 150 mm, SNI m1 120,00 350.000,00 42.000.000,00
2), Pengadaan Pipa GI Φ 100 mm, SNI m1 180,00 300.000,00 54.000.000,00
3), Pengadaan Pipa GI Φ 75 mm, SNI m1 80,00 250.000,00 20.000.000,00
4), Pengadaan Pipa PVC Φ 150 mm, SNI m1 1.600,00 125.000,00 200.000.000,00
5), Pengadaan Pipa PVC Φ 100 mm, SNI m1 8.000,00 100.000,00 800.000.000,00
6), Pengadaan Pipa PVC Φ 75 mm, SNI m1 2.520,00 75.000,00 189.000.000,00
7), Pemasangan Pipa GI Φ 150 mm m1 120,00 22.311,67 2.677.400,00
8), Pemasangan Pipa GI Φ 100 mm m1 180,00 22.311,67 4.016.100,00
9), Pemasangan Pipa GI Φ 75 mm m1 80,00 22.311,67 1.784.933,33
10), Pemasangan Pipa PVC Φ 150 mm m1 1.600,00 16.839,17 26.942.666,67
11), Pemasangan Pipa PVC Φ 100 mm m1 8.000,00 16.839,17 134.713.333,33
12), Pemasangan Pipa PVC Φ 75 mm m1 2.520,00 16.839,17 42.434.700,00
Sub-Total V 1.517.569.133,33
VI. Supplying and Ins talling Plumbing Acce s s ory Job
1), Bend all Flange Φ 150 mm, CI bh 6,00 1.000.000,00 6.000.000,00
2), Bend all Flange Φ 100 mm, CI bh 6,00 700.000,00 4.200.000,00
3), Bend all Flange Φ 75 mm, CI bh 12,00 450.000,00 5.400.000,00
4), Flange Φ 150 mm, CI bh 18,00 1.000.000,00 18.000.000,00
5), Flange Φ 100 mm, CI bh 20,00 700.000,00 14.000.000,00
6), Flange Φ 75 mm, CI bh 20,00 450.000,00 9.000.000,00
7), Bend Socket RR Joint Φ 150 mm, PVC bh 2,00 900.000,00 1.800.000,00
8), Bend Socket RR Joint Φ 100 mm, PVC bh 4,00 700.000,00 2.800.000,00
9), Bend Socket RR Joint Φ 75 mm, PVC bh 3,00 250.000,00 750.000,00
10), Flange Socket RR Joint Φ 150 mm, PVC bh 8,00 1.350.000,00 10.800.000,00
11), Flange Socket RR Joint Φ 100 mm, PVC bh 8,00 900.000,00 7.200.000,00
12), Flange Socket RR Joint Φ 75 mm, PVC bh 6,00 700.000,00 4.200.000,00
13), Tee All Socket RR Joint Φ 150 x 150 mm, PVC bh 2,00 1.850.000,00 3.700.000,00
14), Tee All Socket RR Joint Φ 150 x 100 mm, PVC bh 4,00 1.350.000,00 5.400.000,00
15), Tee All Socket RR Joint Φ 100 x 100 mm, PVC bh 4,00 900.000,00 3.600.000,00
16), Tee All Socket RR Joint Φ 100 x 75 mm, PVC bh 8,00 500.000,00 4.000.000,00
17), Reducer All Socket RR Joint Φ 150 x 100 mm, PVC
bh 2,00 400.000,00 800.000,00
18), Reducer All Socket RR Joint Φ 100 x 75 mm, PVCbh 4,00 250.000,00 1.000.000,00
19), Gate Valve All Flange Φ 150 mm bh 2,00 100.000,00 200.000,00
20), Gate Valve All Flange Φ 100 mm bh 6,00 100.000,00 600.000,00
21), Gate Valve All Flange Φ 75 mm bh 4,00 100.000,00 400.000,00
22), Clam Sadle Φ 150 mm x 1" bh 3,00 900.000,00 2.700.000,00
23), Clam Sadle Φ 100 mm x 1" bh 5,00 750.000,00 3.750.000,00
24), Air Valve Φ 1" bh 8,00 900.000,00 7.200.000,00
Sub-Total VI 117.500.000,00
Read :
THREE BILLIONS ONE HUNDRED NINETY THREEMILLION
MILLION EIGHT HUNDRED
TWENTY THOUSAND RUPIAHS
Risk Management
OPERATIONAL
RISK
MANAGEMENT
Measure Risk
How to consider the risks that will occur before starting a job or making a
decision
Monitor Risk
Monitor all possible failures that occur during the job for taking a corrective
action
Report Risk
Make a list of risks or failures that iccur during the job
Identify Risk
Analyze the causes of risks and failures
Evaluate Risk
Find solutions of the failures that occurred and innovate a new thing to
minimize the failure possibilities
Control Risk
Periodically check the status of the risk and how the impact of the decision
3. Performance and Control
EFFORT COST
TRACKING TRACKING
Cost Tracking
TOTAL COST
NO. JOB LIST
(Rp.)
Rp1,800,000,000
Rp1,600,000,000
Rp1,400,000,000
Rp1,200,000,000
Rp1,000,000,000
Rp800,000,000
Rp600,000,000
Rp400,000,000
Rp200,000,000
Rp0
GENERAL ITEM PREPARATION BRICK PAIR AND CONCRETE JOB PLUMBING SUPPLYING AND FINISHING JOB
JOB PLASTER JOB NETWORK JOB INSTALLING
PLUMBING
ACCESSORY JOB
25,000 hrs
20,000 hrs
WORK (HRS)
15,000 hrs
10,000 hrs
5,000 hrs
0 hrs
GENERAL ITEM PREPARATION JOB BRICK PAIR AND CONCRETE JOB PLUMBING SUPPLYING AND FINISHING JOB
PLASTER JOB NETWORK JOB INSTALLING
PLUMBING
ACCESSORY JOB
Rp2,456,045,465