Min: 4.5 m
to 4m minimum above
the roofline.
A A
‘Anchor spring
A A
SECTION A-A
January 18, 2020 16
Telltales installed at intersections should be at the centre of the span and
should be installed before the junction geometry is formed
X
X X X
X
X
Road excavated just past junction. Three way geometry formed Four way geometry formed
Tell tale installed at the junction
centre following support . This sequence illustrates the ideal timing of tell tale installation in
relation to geometry formation to maximise the effectiveness of the tell tale.
Tell Tale
0.6m
0.6m
Tell Tale
PLAN PLAN
January 18, 2020 18
BOLTS SHOWN ARE IN ADDITION TO NORMAL SUPPORT AND MUST BE AT LEAST 0.5m
LONGER THAN HEIGHT OF BROW
NORMAL PATTERN
RESUMED
HIGH SIDE
NORMAL PATTERN
RESUMED
NORMAL PATTERN
BROW
NORMAL PATTERN
RESUMED
TELL TALE
3 ROWS AT
0.3m
HIGHER BOLT DENSITY
max
SECTION
January 18, 2020 20
Reference Codes for Telltales Installed in a
Section SECTION/ROAD/SPLIT
M22 / 1L-2L / S23
M22 / 1L / S23
2L 1L
SPLIT 23
M22 / 1L / S22-S23
SPLIT 22
It should be the responsibility of the MINER each shift to record the tell
tales by colour for all active areas in the section.
A book should be kept at the section WAITING PLACE in which each
shifts tell tale readings are recorded.
Where a Auto Warning Telltale is triggered (Flashing) the workforce
should be withdrawn immediately, fenced off and the Shift Boss
informed.
This is then logged in the Shift Boss’s statutory shift report, together with
comment on any remedial actions taken.
Only after the affected area has been inspected by the Rockbolting
Engineer and appropriate additional support installed and deemed to be
safe can the temporary barriers be removed.
Thereafter, the Shift Boss should record the millimetre reading of the
relevant telltales until stability has been re-established.
Reading Telltales
IF A TELLTALE
Is
TRIGGERED
GREEN
23
YELLOW, OR
RED
Once per week, the MINER should, in addition to recording his shiftly
observations by colour, record the millimetre reading on each telltale in
his section (active areas).
This information should be recorded on a weekly sheet, which should be
passed to the nominated ROOF CONTROL AUDITOR for trend
analysis.
EACH WEEK
READ BY MILLIMETRES :
0 mm
GREEN 0 - 5 mm
YELLOW >5 - 10 mm
RED >10 mm
January 18, 2020 25
Action Levels –
Auto Warning Telltale on Development
GREEN No action required, continue routine monitoring