COST PLUS - DISADVANTAGES
GENERAL
• ALL Risks by Owner
• Uncertainties in Project Price & Schedule
ENGINEERING
• SOW Undefined and NOT CLEAR
• SOW self-developed during project execution
• High Probability of Changes
• Potentially oversized Team
PROCUREMENT
• Procurement Cycle normally longer than LSTK
• Price negotiation advantages missed No incentives
CONSTRUCTION
• Contractor and Subcontractor Controlled by Owner
• Delays and Errors assumed by Owner
• Diffuse Accountability
• PMC not enough empowered
Felipe Revenga - COO, Técnicas Reunidas PMI AGC Energy Forum: DMS Debates June / 2011
WHY OWNERS SHOULD
ADOPT LSTK MODEL?
4
LSTK MODEL – ADVANTAGES
Owner Contractor
Subcontractors Suppliers
ALL KEY PARTIES INVOLVED WITH ACTIVE PARTICIPATION
• Competitive Bids according to Market Value
• Total Cost Fixed. Owners do not have pressure about Costs
• Contractors may contribute to find sources of financing
• Reliable Forecast of Total Investment Cost
• Schedule defined and agreed
• Better definition of SOW since the beginning
GENERAL
ENGINEERING
Felipe Revenga - COO, Técnicas Reunidas PMI AGC Energy Forum: DMS Debates June / 2011
LSTK MODEL – ADVANTAGES
GENERAL PROCUREMENT
ENGINEERING
Felipe Revenga - COO, Técnicas Reunidas PMI AGC Energy Forum: DMS Debates June / 2011
LSTK MODEL – ADVANTAGES
GENERAL PROCUREMENT
ENGINEERING CONSTRUCTION
Felipe Revenga - COO, Técnicas Reunidas PMI AGC Energy Forum: DMS Debates June / 2011
WHO IS THE
RISK OWNER?
9
LSTK MODEL – RISKS
CONSTRUCTION
PROCUREMENT
ENGINEERING
OWNER CONTRACTOR
EPC-LSTK implies
to contract a
specialist in
GLOBAL T ECHNICAL LEGAL / FINANCIAL RESOURCES
Risk Management
FACTORS CONTRACTUAL
Felipe Revenga - COO, Técnicas Reunidas PMI AGC Energy Forum: DMS Debates June / 2011
LSTK – TIPS TO REDUCE & CONTROL RISKS
ENGINEERING
Early Eng. Works and quick mobilization to Taskforce.
Design Changes controlled and Limited at early stages
Enhance Quality Policies (Check Lists, procedures)
12
LSTK MODEL MORE ATTRACTIVE?
4 Incentives Programs
(Quality, HSE, Schedule)
5
Apply Value Engineering
SCHEDULE
Short bidding period, as cost estimate does not need to be
as detailed
Shorten of the overall schedule of the project as time for
Extended FEED and EPC bidding is shortened dramatically.
Felipe Revenga - COO, Técnicas Reunidas PMI AGC Energy Forum: DMS Debates June / 2011
LSTK MODEL MORE ATTRACTIVE?
Felipe Revenga - COO, Técnicas Reunidas PMI AGC Energy Forum: DMS Debates June / 2011
شكرا THANK YOU GRACIAS
Dr. Mohammed Sammur - Executive VP, Larsen & Toubro
Salah Jebara Al Bufalah - Head of Major Projects ZADCO & President PMI AGC UAE
Felipe Revenga - COO, Tecnicas Reunidas
Kuwait City, Kuwait - 12th June 2011