BLR Tube Leak Detect System

of Tanjung Jati B Unit 3&4


BTLD Implementation of
Tanjung Jati B #3,4
----- Contents -----
1. The Progress

2. System Overview

3. Sensor Location
4. Need data
5. Sample pictures
6. Installation Schedule
7. Discussion items
1. The Progress

Content Date Remark


Presentation & Aug 12, Sep 8, Oct 15 CJP, PLN
Meeting Aug 20, Sep2 Toshiba, MHI, SCJO
PLN, KPJB,
Site Survey & Mark Aug 30~Sep 2
Hana-Ever Tech
Revise drawings Sep 5 ~ Oct 7 Hana-Ever Tech
Prepare B/M Sep 20 ~ Oct 30 Hana-Ever Tech
Expected delivery
Nov 30 Hana-Ever Tech
date
Installation schedule Dec 2 ~ Dec 20
KPJB, Toshiba,
Function test Dec 21,22
Hana-Ever Tech
2. System Overview

Boiler BLDG
In CCR

In Electronic Room
3. Sensor Location
3.1 Sensor Location Drawing

The location of 20 Sensors


exactly

Leave a space like this size


during the insulation work

L R
400*400

H
3.2 The sensor Location of each type

Need special type sensor Use original type rod at


rod at water wall side backpass, eco tube side
3.3 Sounding Rod Waveguide & Sensor

No 1~14 sensors apply for


special type rod
3.4 Sensor Detail(1)

Change the method of installation


- The direction of welding
- The modification of sensor type
3.5 Sensor Detail(2)

Sensor Guide pipe each type


4. Need data
4.1 BTLD Panel Location

#4 Panel
# 3 Panel
4.2 Panel Layout

Hole size 104mm


60mm
4.3 Configuration Diagram

Interface cable with DCS


- A/O : 5 Points
- D/I : 2 Points
- D/O : 1 Point
4.4 Power Cable Connection Diagram

For lighting and


concent power

For monitoring
system of BTLD Only
4.5 DCS Interface Diagram

Need the terminal number


for I/O signal cable connection
4.6 Cable Connection Diagram

Need the terminal


number for cable
connection DWG
4.7 The Desk Arrangement

Install #4
Install #3 monitor & Desk
monitor & Desk

Install
Printer & Desk

Monitor : 21.3”, Black


Desk : -- Color : 5y7/1,
-- Size : 710/800/1200
4.8 Monitor Display(sample)

BTLD Display of Boryong


Thermal PP #7 in Korea
5. Sample pictures
5.1 Welded status of sensor rod and guide pipe

The welded status The welded status


of sensor on of guide pipe on
membrane wall membrane wall
5.2 The install status of pre-Amp and guide pipe

The installed status Internal part of


of pre-amplifier guide pipe
5.3 The picture of insulation and lagging work

The Finished status


The finished status
of lagging work
of insulation work
5.4 The picture of finished work

Installation status All works finished


of additional plate
6. Installation Schedule
Pro je c t N a m e : Ta njung Ja ti B # 3 BTLD

Planned Planed
Description Oct. Nov. Dec. Remark
Start Finished
5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30
BLR Insulation & lagging 10/10/15 10/12/30
Packing, Shipping & Tranporting 10/10/26 10/11/30
Preparation for Installation 10/12/01 10/12/02
System Panel, Making hole 10/12/03 10/12/05
Preamplifier Stanchion with Enclosure 10/12/06 10/12/09
Conduits 10/12/10 10/12/14
Sounding Rod & Guide Pipe
Sensor
Waveguide Shroud 10/12/15 10/12/20
Accessory
High Temp. Cable
DCS interface cables & Power Cables Pulling 10/12/13 10/12/14
DCS interface cables & Power Cables
10/12/15 10/12/15
Contection
Coaxial Cables Pulling 10/12/16 10/12/19
Coaxial Cable Contection, Line Check 10/12/20 10/12/20
Loop Check 10/12/21 10/12/21
Field Performance Test 10/12/22 10/12/22
Commissioning & Operator Training 10/12/23 10/12/24
7. Discussion items

Items Content Remark


Need breaker No : UPS &
Power cable Toshiba
Normal power
Signal cable Need 8 signal terminal No Toshiba
Space for sensor Leave a space for sensor
MHI,SCJO
install installation
Monitor & Desk Match the color and size KPJB
Cable entrance Making hole size : 104, 60 KPJB
Spare terminal Need to discuss PLN, Toshiba

Schedule From Dec 1 to Dec 23 SCJO,KPJB

WPS On going KPJB