Академический Документы
Профессиональный Документы
Культура Документы
Forecasting or Predicting
Planning
Organising
Motivating
Controlling
Co-ordinating
Communication
Concept of Planning
Project Planning
Project Scheduling
Project Control
Concept of Planning
Advantages Disadvantages
ACTIVITY
ES LS ARROW EF LF
A
1 8
2
DURATION
NODE
Critical Path
Method(CPM/AOA)
EARLY START (ES)
The earliest possible time to start an activity. It is determine by
forward pass calculation through every paths of the network
EARLY FINISH
The earliest possible time to finish an activity (ES+Duration)
LATE START
The latest possible time to start an activity without delaying
the overall completion of the project
LATE FINISH
The latest possible time to finish an activity without
delaying the overall completion of the project It is determine
by backward pass calculation through every paths of the
network
Critical Path Method(CPM/AOA)
1 3
Second
- When several activities lead into and out of
an event, and all the following activities do not
depend upon the completion of all the
preceding activities
A B
1
DUMMY
C D
1
EXAMPLE CPM
Critical Path Method(CPM/AOA)
TOTAL FLOAT
The time available to delay the start or finish of an
activity without delaying the completion of the
project
TF = LF – ES - DURATION
FREE FLOAT
The time available to delay the start or finish of an
activity without delaying the EARLY START TIME (ES) of
the proceeding activity/ies
Example :
Activity Event No. Activity Description Duration
A 1-2 Site Survey 1
B 2-3 Excavation Foundation A 2
C 2-6 Excavation Foundation B 4
D 3-4 Concrete Foundation A 1
E 6-7 Concrete Foundation B 3
F 4-5 Levelling Base A 1
G 7-8 Erect Plinth 2
H 5-9 Erect Tower A 1
I 8-9 Erect Tower B 1
J 9-10 Erect Steelframe 1
A 1 0 0 1 1 0
B 2 1 1 3 8 5
C 4 1 1 5 5 0
D 1 3 8 4 9 5
E 3 5 5 8 8 0
F 1 4 9 5 10 5
G 2 8 8 10 10 0
H 1 5 10 11 11 5
I 1 10 10 11 11 0
J 1 11 11 12 12 0
Exercise 1
ACTIVITY EVENT DURATION(WEEK) PREDECESSOR
A 1-2 5 -
B 2-3 4 A
C 2-4 3 A
D 2-5 3 A
E 3-9 5 B
F 3-6 5 B
G 4-6 0 C
H 4-8 6 C
I 5-7 7 D
J 6-8 3 F-G
K 7-8 4 I
L 8-9 3 J-H-K
Based on the following information:
1. Draw the arrow network diagram.
2. Draw the critical path network.
3. Formulate the value of ES, EF, LS, LF, and TF for each activity
Exercise 2
Event Activity Duration(Weeks)
1-2 A 2
1-3 B 3
2-4 C 4
3-4 D 3
4-5 E 2
4-6 F 2
5-7 G 3
6-8 H 4
7-9 I 3
8-9 J 3
A 1 0 0 1 1 0
B 2 1 1 3 8 5
C 4 1 1 5 5 0
D 1 3 8 4 9 5
E 3 5 5 8 8 0
F 1 4 9 5 10 5
G 2 8 8 10 10 0
H 1 5 10 11 11 5
I 1 10 10 11 11 0
J 1 11 11 12 12 0
S-Curve