Power Cost Efficiency Program

Joint Program Between Huawei Service and XL AXIATA

Proposal on XL Investment for Power


Efficiency Solutions

Quick-win Solutions: Indoor to Outdoor shelterless


Content

Indoor to outdoor
solution:
Site layout
Mutual parts of products
Site Selection Process
Detailed Swapping Procedure
Special Scenario
SOW Description
Indoor to Outdoor scenario – Site layout Before Swap
MW Antenna & ODU Before
All indoor equipment room has transmission
PVC Cable Trough equipment installation rack
FE/E1 cable
Grounding cable Antenna
AC power cable
DC power cable
Feeder Grounding bar
Jumper
MW IF Cable
Optical Fiber
Alarm Cable

Shelter

ATS Feeder
Cable ladder
window Tower Grounding bar

Main power

ACPDB

IDU or
router
D.G. DDF
ODF
Power & Battery 2G BTS 3G BTS
Indoor to outdoor scenario – Site layout After Swap
Scenario A (RRU Mount on Top tower)
Final
Alarm Cable MW ODU &
Optical Fiber Antenna
Grounding Cable
AC Power Cable
DC Power Cable
MW IF Cable
Jumper Cable
Antenna
PVC Cable Trough
RRU 3-9 PCS

TP48200A
ATS
New BBU
Grounding Bar Grounding Bar

New IDU
950/950A
Main power
AC
DCDU
AC

ACPDB
Grounding
Bar
New Foundation
Footprint (1m*1m)
Grounding Bar
Content

Indoor to outdoor
solution:
Site layout
Mutual parts of products
Site Selection Process
Detailed Swapping Procedure
Special Scenario
SOW Description
Indoor to Outdoor – Power design

Cable Space(2U) R R
R …… R Mobile APP
POWER U U NetEco
(6U)
OSS
BBU(2U) In-band
IDU(2U)
DCDU-12B(1U)
SPARE ( 4
U) BBU(2U)

IDU(2U)
BATTERY DCDU-12B(1U)

SPARE ( 4U)

1. TP48200A has total 9U space for other equipments.


2. DCDU-12B provides the power for RRU modules.

Outdoor power
Indoor to Outdoor - Power MCB distributions

Final DC and AC Distribution of TP48200A


Final

Grid power
ATS
LLVD 80A
63A/3P
80A DCDU-12B …… RRU(3~9Pcs)
DG

32A
Spare
32A
BBU
ACPDB PSU
BLVD 16A
RTN950

16A
Spare

10A
Spare

BAT 125A
BAT 1

125A
BAT 2

16A
Maintenance
Socket
AC
Output 1. BBU and RRU connect to LLVD breaker.
16A
Spare
2. Transmission equipments connect to BLVD
breaker.
Outdoor Power System Overview

Stackable Outdoor Power System


Mini-shelter
We are here
Integrated Outdoor Power System

Hub site DBS site /Roof top DBS site


TP48200A Specification

650mm(W)×650mm(D)×1500mm(H) (excluding
Dimension
base)
Weight ≤100kg (without rectifier module)
Power cabin: Heat exchange 850W
Cooling mode
Battery cabin: direct ventilation
System
Installation mode Grounding\rooftop\wall against
Power cabin: IP55
Protection level
Battery cabin: IP45
Battery space 16U (Maximum 2*190Ah)
User space 9U
Input mode Three phase compatible with single phase
Input voltage 380V/220VAC
Input capacity 1×63A/3P
AC 20kA/40kA, 8/20μs
Distribution SPD
Maintenance Universal 220Vac socket (with 16A MCB
protection)
socket
AC output 1*16A/1P MCB, 220Vac output

Output voltage 42~58VDC, rated value: 53.5VDC

Maximum capacity 12kW (4*3000W)


DC 2*125A MCB
Distribution Battery branch
LLVD branch 2*80A MCB, 2*32A MCB

BLVD branch 2*16A MCB, 1*10A MCB

Operating
Environment -10℃~+45℃ (+ solar radiation)
temperature
High Efficiency Rectifier Module

We are here
Existing Industry Super

94% 96% 98%

Existing Industry level Huawei


Separate Temperature Control Based On Ambient Temperature

 Global coverage TC
solution
Regio E B
n cabinet cabinet
TEC

HEX
TEC

FV

FV
HEX
TEC

We are here iHEX A/C

Cold area Cool in summer and warm in winter

Tropical area High temperature area Warm Temperate area


Full Scenarios Covered Temperature Control

Equipment
Battery Cabinet
Cabinet

 Considering ambient temperature, load power, grid condition,


Huawei provides full series of TC solution
 Each TC solution is professionally designed and critically verified
before massive application
Maximizing Network Energy Efficiency
1 98% PSU Module ,lead the industry ~ /

• Reduce PLN cost • Increase MTBF 550000
• Intelligent domancy hours
mode • Super high efficiency is
trend
2 Site visible on Neteco

• Assessment Visible • Reduce opex


• Battery SOH Visible • 0 transmission cost(hw)
• Alarms Visible • Continuous optimization advice
• energy trend report • App anytime anywhere

Expansion
• Ready for
3 Increase Network availability
LTE/6sector/9sector… • Increase power availability and Network availability
• Ready for Expansion

4 Professional Design 5 Reference in Region & Global

• 560 sites in XL • 3200 +sites in celcom


• 3684 sites in ISAT Malasia
• 8 R&D centers in global • 19305 sites in H3I
• 400+ Patents, 20+ Core • 1385 sites in TESL
• 600 sites in FM
Patents • 1310 sites in Berca Leadership Award
Frost & Sullivan
• 2500 Engineers of R&D • 170+ Countries 2014
Equipment Air duct • 1.8M+ Commercial Applications DC Power market
Heat simulation simulation • 24.7% Market Share
3G NodeB after Modernization
Blade RRU Weight: 15 kg
Dimensions: 400(H)*300(W)*100(D)

Power Saving 10%


Coverage improve 20%
3G Capacity improve 50%

UMPT
LTE Ready
Co-2G/3G/LTE Control, simplify transmission
3G Capacity improve 50%

UBBP
LTE Ready
3G/LTE Shared, simplify transmission
CE Capacity increase 30%

14
2G NodeB after Modernization
Blade RRU

Power Saving 10%


Coverage improve 20%
LTE ready with 2T4R

UMPT
LTE Ready
Co-2G/3G/LTE Control, simplify transmission

All the hardware can be reuse to LTE.

15
Content

Indoor to outdoor
solution:
Site layout
Mutual parts of products
Site Selection Process
Detailed Swapping Procedure
Special Scenario
SoW and RM
Site Selection Procedure

Start Existing indoor site


(not IBS site)
1
2 3 4 5
No No
OSN and No MW is Tower Space Yes Enough space for Yes
RRU >6 Router/3rd party hub site? and Load new foundation?
Equipment
>2 direction readiness
No

No No
Site in flood Yes
plain?
Yes Yes
Yes Special
scenario
Don’t Touch

Indoor to
Outdoor
Swap
Content

Indoor to outdoor
solution:
Site layout
Mutual parts of products
Site Selection Process
Detailed Swapping Procedure
Special Scenario
SOW Description
Indoor to Outdoor --Detailed Scenario Changing Procedure

Site integration scenario

Scenario\prior 1st Step 2nd Step 3rd Step 4th Step

TK construction TP48200A installation RF optimization

MW IDU
outdoorization Shelter and inner
Outdoor ACPDB
Indoor -> Installation
New BBU installation equipment dismantle
and delivery
Outdoor New BBU
Integration
Shelter foundation
ATS outdoorization New RRU Installation
dismantle
Indoor to Outdoor—Swap Procedure ( new foundation space
enough)
Preparation before outdoorization Final
1. Site Survey & Design
2. Build new foundation and cable ladder
3. Install outdoor ACPDB and ATS outdoorization
4. Install outdoor power system with DCDU
5. Install new RRU including laying CPRI and power cable
6. Install New BBU
7. Install New IDU
AC power cable New
Power & 2G 3G MW
DC power cable Battery BTS BTS IDU RRU
Grounding cable
1/2” jumper
7/8” feeder
MW IF cable TP48200A
New BBU

ATS

New MW IDU

DCDU
Main power

AC AC

ACPDB
New Foundation

Grounding Bar
Indoor to Outdoor—Swap Procedure ( new foundation space
enough)
Implementation of Outdoorization
1. Backup data for MW and Wireless
2. Patching jumpers &AISG cable from RRU to antenna
3. Laying IF cable to IDU
4. Integration BBU to IDU (transmission)
5. Integration BBU and RRU (wireless)
6. Test and Service verification
7. Indoor BTS and power dismantle and delivery New
Power & 2G 3G MW
8. Shelter dismantle Battery BTS BTS IDU RRU
AC power cable
DC power cable
Grounding cable
1/2” jumper
TP48200A
7/8” feeder
New BBU
MW IF cable
ATS

New IDU

DCDU
Main power

AC AC

ACPDB
New Foundation

Grounding Bar
CME Swap Procedure

SOW
oSurvey & Detail Design(without Tower analysis)
oAs built Drawing
oOutdoor foundation for cabinet
oSupply, delivery and installation RRU mounting bracket (HTI site only)
oDismantle Shelter Body (include all material inside shelter; air cond, tray, cabling, duct, etc)
oDismantle & Disposal Shelter Foundation
oDisposal Shelter Body
oDelivery of Shelter Body site to XL WH
oDelivery Back shelter & Auxiliary materials to XL WH
oSupply .Delivery & Installation of ACPDB Outdoor , Power, Grounding Cable & Auxiliary
Accessories
oTower Load analysis & strengthening
Risk and Solution
oThe site space is not enough to build new cabinet foundation
Solution: dismantle existing shelter foundation first and then make new outdoor cabinet foundation
oThe dismantled shelter need pack and follow customer quality requirement and avoid any damage
Solution: let customer check and sign the acceptance documents at the time when before packing and
reach customer ware house

SOP
Connect to
Dismantle dismantle Install
Build new existing
existing existing ACPDB RFI
foundation grounding
shelter foundatio panel
system
n
Power Swap Procedure

SOW
oSwap Rectifier (Dismantle indoor and install outdoor)
oPower System Analysis and Design
oDelivery Outdoor Rectifier Cabinet to site & indoor rectifier back to WH
oObsolete power system/battery scrap

Risk and Solution


oNo new foundation space to install TP48200A
Solution: Install TP48200A in existing shelter for temporary solution.

SOP
Install Power on
Install Connect
New Install Connect Connect and
Rectifier Alarm
Power battery DC cable AC cable commissi
Module cable
cabinet oning
Wireless Swap SOW and Risk

SOW
oSite survey
oWireless site design
oRequire new CPRI cable as backup
oSRAN modernization if require
oIP migration if need
oInstall new RRU on tower
oInstall new BTS3900A
oReconfiguration script
oService verification
oKPI monitor
oATP
oDismantle feeder /cabinet

Risk and Solution


oNeed some new cables in case of existing broken like RRU CPRI cables, power cables and CAT5e
oNeed new jumpers replacing old one for good engineering quality
oNeed new cabinet BTS3900A /BTS3900AL if still using RFU
oCannot install BBU in TP cabinet if site is close to sea.
Wireless Swap Procedure

Wireless Site Solution


Design
design

DBS3900 ( use TP48200A)


Evaluation design & all RRU for G900+GL1800+U2100
Tower ECRF

no
feasible end
?

yes
implementation

Foundation &Power Ready


Backup script

Install RRU on Tower

Install BBU to TP

service down Integration BBU with IDU


2 hour And RRU

Service Verification
Transmission(MW) Swap Procedure

Risk and solution Final


MW site Solution Design

1.HUT/HUB can’t proceed due to


design

Evaluation design many limitation(space,service .etc)


Hub ,Hut ,Lease line

2.Site with Lease line service


Available end terminated indoor, need identification
? no
yes
3.Huawei Microwave 1st priority,
RFI Ericsson microwave site 2nd priority
implementation

(plan to Swap before September)


Install IF cable in advance

Installation and integration


with new IDU and
accessories

Service Verification

Material dismantle and


collection
Content

Indoor to outdoor
solution:
Site layout
Mutual parts of products
Site Selection Process
Detailed Swapping Procedure
Special Scenario
SOW Description
Special Scenario -1: Flood Region

For flooding area, we will raise the equipment pad based on the flooding
Water level, following is the example design.
Special Scenario -2: No new foundation space
1. Install outdoor ACPDB and ATS
outdoorization
2. Install outdoor power system in shelter
3. Install DCDU
4. Install new RRU
5. Install New BBU
6. Install New IDU
7. Backup data for MW and Wireless
8. Patching jumpers &AISG cable from New BBU
RRU to antenna
9. Laying IF cable to IDU
New IDU TP48200A
10. Integration BBU to IDU (transmission)
11. Integration BBU and RRU (wireless)
12. Test and Service verification
13. Dismantle half shelter
14. Construct new foundation
DCDU
15. Move power cabinet to new foundation
ATS

Main power

Power & 2G 3G MW IDU


AC AC Battery BTS BTS
New Foundation

Grounding Bar

ACPDB AC power cable


DC power cable
Grounding cable
1/2” jumper
7/8” feeder
MW IF cable
Special Scenario -3: RRU number >6 PCS

R R R R R
Cable Space(2U) R
9
……
RRU
R R R R
U U U U U
POWER
(6U)

BBU(2U) BBU(2U)
IDU(2U)
IDU(2U)
DCDU-12B(1U)
SPARE ( 4 DCDU-12B(1U)
U) SPARE ( 4U)

Equipment Per Unit Qty Total Power Battery Back up


Power consumption time
consumption (W)
BATTERY (W)
( New)
BBU 250 1 2480 190AH*2 4.6 Hours

IDU 200~250 1

RRU 220 9 (e.g.)


Outdoor power
RRU quantity >6 pcs scenario, new battery 190AH*2 replace existing 105AH to
guarantee >4H back up time when PLN down
Special Scenario -4 : RRU Mount at Bottom of Tower

Grounding Cable
AC Power Cable 1. RRU >= 6 PCS MW ODU &
DC Power Cable
MW IF Cable
2. Top of tower cannot support RRUs after analysis Antenna

1/2” jumper 3. Install RRUs at bottom of tower


7/8” feeder 4. Reuse part of existing 7/8’’ feeder
PVC Cable Trough
Antenna

ATS
TP48200A
New BBU
Grounding Bar Grounding Bar

New IDU
950/950A
Main power
AC
DCDU
AC

RRU 6-9 PCS

ACPDB
Grounding
Bar

Grounding Bar
Content

Indoor to outdoor
solution:
Site layout
Mutual parts of products
Site Selection Process
Detailed Swapping Procedure
Special Scenario
SOW Description
Shelterless Service SOW Description

Scope in (Mandatory) BAU (HTI) Optional

2G/3G Modernization service LTE Deployment Outdoorization


• Outdoor Cabinet Installation • Project management • Dismantle & Disposal Shelter
• Delivery Cabinet to site & back to WH system Foundation
• Reconfiguration 2G/3G for Single RAN (HTI site • Site permit • Delivery Back shelter &
only) • Delivery of Cabinet and Auxiliary materials to XL WH
• Basic Optimization 2G & 3G (HTI site only) other accessories • Supply .Delivery & Installation
• Feeder Dismantle • Warehousing of ACPDB Outdoor , Power,
• Dismantle & Packaging Cabinet • LTE Network planning Grounding Cable & Auxiliary
Outdoorization: • CDR for LTE Accessories
• CME Scope: • LTE Initial Tuning for 1 • Tower Load analysis &
oSurvey & Detail Design(without Tower analysis) system strengthening
oAs built Drawing • Reconfiguration for Single • SITAC for new location
oOutdoor foundation for cabinet RAN (remotely) 2G
oSupply, delivery and installation RRU mounting • Site Survey (exclude RF
bracket (HTI site only) survey)
oDismantle & Disposal Shelter Body (include all • RF Survey
material inside shelter; air cond, tray, cabling, duct, • Cabinet Installation
etc) • LTE Expansion (RRU)
• MW Scope • LTE Frequency Re-
oDismantle MW IDU farming
oInstall MW IDU in Outdoor
oLayering new IF Cable
oMW Validation Services (end to end validation)
• Power Solutions:
oSwap Rectifier (Dismantle indoor and install
outdoor)
oPower System Analysis and Design
oDelivery Outdoor Rectifier Cabinet to site 33