Академический Документы
Профессиональный Документы
Культура Документы
SCHEDULING
HOW DO MANAGERS USE THE PLANNING
PROCESS?
• PLANNING IS ONE OF THE FOUR FUNCTIONS OF
MANAGEMENT
• PLANNING IMPROVES COORDINATION AND CONTROL
Conceptual
Pre-feasibility
Feasibility
Construction
Operation
• WHEREAS
• MANUFACTURING/
• RETAILING = “JUST-IN-TIME”
• MINING = “JUST-IN-CASE”
• RESEARCH APPROACHES
• SMART MINING SYSTEMS
• SMART MINING MACHINES
• STEP-CHANGE MINING SYSTEMS
POSITIVE EVALUATION METHODS 3
• INVESTMENT
DETERMINE THE MINABLE ORE
RESERVE
• ASSUME ECONOMICS FOR MATERIAL REMOVAL
• LOOK AT GEOLOGY FOR HOW STEEP THE PIT SLOPES CAN
STAND WITHOUT SLIDING IN
• HAVE THE COMPUTER ANALYZE THE LARGEST SET OF
BLOCKS THAT CAN BE REMOVED WITHOUT TAKING STUFF
THAT LOOSES MONEY
• THIS SET MEASURES THE SIZE OF THE PIT THAT CAN ULTIMATELY BE
MINED (CALLED THE ULTIMATE PIT)
• TOO COMPLEX TO VISUALIZE
• DONE WITH EITHER A FLOATING CONE MINER OR LEARCH-
GROSSMAN COMPUTER ROUTINE (EASILY AVAILABLE IN MINESIGHT)
COMPUTER VIEWS OF PITS
THE TIME VALUE OF MONEY
• A REVIEW FOR THOSE WITH ENGINEERING ECON
• SOME NEW THOUGHTS FOR OTHERS
• WOULD YOU RATHER GET $100 NOW OR $100 FIVE YEARS FROM NOW
• MOST WOULD PICK NOW
• ONE REASON – IF YOU PUT MONEY IN CD AT 3% INTEREST IN 5 YEARS YOU WOULD HAVE
$116
• YOU’D ONLY NEED $86 NOW TO EARN TO $100 IN FIVE YEARS SO HOW CAN $100 NOT DELIVERED
FOR FIVE YEARS BE WORTH MORE THAN $86?
HANDLING THE TIME VALUE OF MONEY
• MONEY CAN BE MULTIPLIED BY A DISCOUNT FACTOR TO
ADJUST TO HOW MUCH RIGHT NOW MONEY IT IS EQUAL TO.
• MINING COMMONLY LOOKS FOR INVESTMENTS TO EARN 15%
• IF YOU GET $100 NOW ITS $100
• IF YOU GET $100 IN 1 YEAR ITS LIKE $87
• IF YOU GET $100 IN 5 YEARS ITS LIKE $50
• IF YOU GET $100 IN 10 YEARS ITS LIKE $25
• YOU SEE THE PATTERN – THE LONGER THE MONEY TAKES TO GET
HERE THE LESS IT IS WORTH
WHAT DOES THE TIME VALUE OF
MONEY DO TO MINE PLANS?
$100,000,000
0 1 2 3
4 5 6 7 8 9 10 11 12 13
$100,000,000
Just adding up money gives $600,000,000 Total
ut not all the money got here at the same time – if we apply discount factors and
hen add we get $1,670,000 – almost even money (at 15% interest)
$50,000,000
0 1 2 3
4 5 6 7 8 9 10 11 12 13
$100,000,000
Same money but I collect more money sooner and less later
$0 $50,000,000
0 1 2 3
4 5 6 7 8 9 10 11 12 13
$100,000,000
Same Money Again but now the NPV is $197,374,000
Getting money early and putting off expenses makes project values improve
A WHOLE LOT!
HOW CAN I MAKE THAT HAPPEN IN THE
FIELD
• SUPPOSE I MINE MY BEST AND MOST VALUABLE ORE FIRST?
• SUPPOSE I DELAY SPENDING MONEY STRIPPING WASTE
MATERIAL
• IF I MINE FROM THE TOP DOWN I WILL USUALLY MINE MOSTLY
WASTE AT FIRST
• AND WAIT A LONG TIME TO GET DOWN TO THE BEST ORE
• WHAT I WOULD LIKE TO DO FOR A SEQUENCE IS TO ASK THE
COMPUTER TO FIND ME THE BEST ORE WITH THE LEAST
STRIPPING FIRST
• I WILL GET THE COMPUTER TO IDENTIFY A SERIES OF NESTED PITS
THAT HAVE THE MOST VALUE AND USE THAT AS MY DRAFT
SEQUENCE
DEVELOPING A PRACTICAL LAYOUT
• WITH A SERIES OF NESTED PIT SHELLS AS A GUIDE DESIGN A SET OF
PITS THAT FOLLOWS THE GUIDES BUT HAS BENCHES, AND ROADS
REQUIRED FOR PRACTICAL MINING.
• MINESIGHT IS A 3D CAD PROGRAM SO I CAN DRAW IN MY ROADS AND BENCHES
• LOOK AT FURTHER BOOSTING EARNINGS BY RUNNING ARTIFICIALLY
HIGH CUT-OFF GRADES AT FIRST AND SIZING MINE PRODUCTION
• CAN BE DONE WITH VALP IN MINESIGHT
• SIZE UP YOUR EQUIPMENT FLEETS AND HAULAGE TIMES
• MINESIGHTS HAULAGE PROGRAM IS STILL WEAK (WE WILL USE FPC)
• DEVELOP DETAILED LONG TERM SCHEDULES OF WHAT WILL BE MINED
FROM WHERE
• MINESIGHT STRATEGIC PLANNER CAN DO THIS
• IN FOR MAJOR REFINEMENT IN MARCH OR APRIL
• COLLECTIVELY THESE STEPS ARE CALLED LONG TERM MINE PLANNING
STAGES OF EVALUATION
• EVALUATION OF A MINERAL RESOURCE IS THE PROCESS OF
DETERMINING IF THE RESOURCE WILL SUPPORT ECONOMIC
EXPLOITATION
STAGES OF EVALUATION
• FORMAL RESOURCE PROJECT EVALUATION IS AN
ITERATIVE PROCESS USUALLY ACCOMPLISHED VIA A
SERIES OF
• PROGRESSIVELY MORE DETAILED STUDIES THAT
PUNCTUATE AND DRIVE ONGOING DATA COLLECTION
PROGRAMS
STAGES ARE
• SCOPING (CONCEPTUAL)
• PREFEASIBILITY
• FEASIBILITY
STAGES OF EVALUATION
• SCOPING TO IDENTIFY:
Estimating a
point here:
extrapolation
Interpolating a Surface From Sampled Point Data
Regular Random
Interpolating a Surface From Sampled Point Data
Global Interpolation
Uses all known sample points to estimate a
value at an unsampled location
Sampl
e data
Interpolating a Surface From Sampled Point Data
Local Interpolation
Uses a neighborhood of sample points to
estimate a value at an unsampled location
Sampl
e data
Uses a local
neighborhood to
estimate value, i.e.
closest n number of
points, or within a
given search radius
INVERSE DISTANCE
WEIGHTED (IDW)
Inverse Distance Weighted
Local method
Exact
Can be linear or non-linear
1
i i i
n
d
p
i 1
i
10
0 IDW:
4 Closest 3
3 16 neighbors,
0 r=2
2
20
0
KRIGING
INTERPOLATION
KRIGING INTERPOLATION
z ( p) w z ( p )
e i i
This estimated value will most likely differ from the actual
value at point p, Za(p), and this difference is called the
estimation error:
p ze ( p ) z a ( p )
PUNCTUAL (ORDINARY) KRIGING
If no drift exists and the weights used in the
estimation sum to one, then the estimated value
is said to be unbiased. The scatter of the
estimates about the true value is termed the
error or estimation variance,
[ z e
( p i ) z a ( p i )] 2
i
σ
2
z
i 1
n
CLASSIC OPEN PIT MINING
ISSUES AND CHARACTERISTICS
CLASSIC OPEN PITS CHARACTERIZED BY
OVAL SHAPE, BENCHES, SPIRALING ROADS
Daylighted fracture
Offers an opportunity Non-Daylighted fracture offers little
To slide off. Risk
PROBABILITY OF FAILURE
Can tolerate
daylighted Daylighted fractures on over-all
Fractures on Pit slope are another matter
benches
A LESSON IN OPEN PIT TERMINOLOGY
Berm
Localized single bench failures from a steep toe to crest slope are much
Tolerable than an over-all pit slope failure over the entire side of a pit.
PIT SLOPES
• WHY BENCHES?
• BENCHES STOP ROLLING ROCKS (A ROCK
ROLLING DOWN 600 FT AND HITTING YOU IN THE
HEAD WILL SPLIT YOUR SCULL – EVEN IF THERE
ARE NO BRAINS)
• BENCHES ACT AS ROCK CATCHERS – THEY NEED TO BE
WIDE ENOUGH FOR THIS – WITH THE AID OF A BERM
(AROUND 10-15 FEET)
Woops! DIGGING HEIGHT
• BENCHES MATCH EQUIPMENT
Bigger shovels allow bigger bench
Height – but require bigger trucks
WHY BENCHES CONTINUED
• FLAT AREA ON BENCHES PROVIDES ROOM FOR
EQUIPMENT TO MOVE
• BIGGER TRUCKS HAVE BIGGER TURNING RADIUS
Truck
Shovel
At least 20 ft
75 ft Turning Radius
Shovel
5 ft wall clearance
5 + 75 ft turn radius + 37 feet length + 5 foot from edge = 122
(say about 125 foot bench width for working.)
THE DEPTH EFFECT
• NOTE THAT AS A PIT GOES DEEPER THE STRIPPING RATIO INCREASES UNTIL
IT REACHES AN ECONOMIC LIMIT
• RULE 1 – AS SLOPE DECREASES S.R. INCREASES
• RULE 2 – AS DEPTH INCREASES S.R. INCREASES
PRACTICAL STEEPENING CONSIDERATIONS
• THE SLOPE LIMITING FACTOR WAS THE NEED TO HAVE WORKING ROOM FOR
THE EQUIPMENT
• BUT DO I NEED TO BE ABLE TO WORK ON EVERY BENCH AT THE SAME TIME?
• THERE ARE USUALLY PRACTICAL LIMITS TO THE NUMBER OF LOADERS AND TRUCKS YOU CAN RUN
WITHOUT GOING NUTS
• MOST MINES WILL HAVE ABOUT 2 TO 5 LOADERS.
• USUALLY THEY WILL HAVE SOME EXTRA WORK PLACES TO MOVE THE LOADERS TO SO THEY CAN
PREPARE AHEAD
• TRICK #2 – DOES THE PIT HAVE TO EXPAND IN ALL DIRECTIONS AT THE
SAME TIME.
• CAN USE “PUSH BACKS” – HAVE A FULL WORKING SLOPE ONLY IN CERTAIN DIRECTIONS AT ANY
ONE TIME.
WORKING PITS
• SOMETIMES THE IMPACT OF DISTANCE CAN LIMIT THE PIT DEPTH BEFORE
THE STRIPPING RATIO DOES
IMPACT OF DISTANCE
• IN-PIT CRUSHING AND CONVEYING – HAVE THE TRUCKS CARRY THE ORE TO A
POINT IN THE PIT A CONSTANT DISTANCE AWAY – THEN CRUSH AND CONVEY
• RESULT – YOU KEEP THE FLEXIBILITY OF HAUL TRUCKS FOR MINING BUT THE
INCREASED HAUL DISTANCES IN MORE MINED OUT UPPER AREAS OF THE PIT ARE
HANDLED BY CONVEYORS WHICH HAVE A LOWER UNIT COST FOR MOVING
MATERIAL
RADICAL IDEAS
• PUTTING INCLINED HOISTS ON THE PIT SURFACE OR JUST IN THE WALL AND
HAULING THE ORE STRAIGHT UP THE SIDE WITH A SKIP
• WAS DONE AT LEAST ONCE IN NEW MEXICO
• HAS BEEN THE OBJECT OF MANY STUDIES OVER TIME
CALCULATING STRIPPING RATIOS
FOR SIMPLE OPEN PITS
OPEN PIT ON PIPE SHAPED
DISSEMINATED DEPOSIT
Cone
1/3*Base*Height
Cylinder
Base * Height
You’ve seen these
Formulas derived in
Your calculus classes
GETTING OUR CONE
We assumed no material
Stripping Ratio = Overburden / Ore
Was rehandled and all
Ore was recovered
$45
-$5.40 $34.20 > 0
-$5.40
=$34.20
ACTION
-$5.40 -$5.40 $0 $0 $0 $0 $0
-$5 -$5 -$5 -$5 -$5 -$5 -$5 -$5 -$5 -$5
-$5 -$5 -$5 $10 -$5 -$5 -$5 -$5 -$5 -$5
$25 $25 -$5 -$5 -$5 $70 -$5 -$5 -$5 -$5
WORKING ON WOOPS
-$40 + $70 = $30
-$5 -$5 -$5 -$5 -$5 -$5 -$5 -$5 -$5 -$5
-$5 -$5 -$5 $10 -$5 -$5 -$5 -$5 -$5 -$5
$25 $25 -$5 -$5 -$5 $70 -$5 -$5 -$5 -$5
CYBERMINING
Now the Cone Is Profitable
-$5 -$5 $25 $25 -$5 -$5 -$5 $0 -$5 -$5 -$5 -$5
WEAKNESSES OF FLOATING CONES
This Pit is Profitable
-$5 -$5 $25 $25 -$5 -$5 -$5 $0 -$5 -$5 -$5 -$5
Figure 1:
Integrating
Stages of
Mining and
Mine Closure
Planning
(adopted from DITR
2006a, ICMM 2006)
BUILDING THE
BUSINESS CASE
FOR FUTURE
MITIGATION OF RISK
KEY CLOSURE PLANNING CONSIDERATIONS
INTEGRATIO
N INTO
BUSINESS
PRACTICES
WHERE ARE THE TREES?
WHAT ABOUT THE SLUDGE?
EXAMPLE
CASE STUDY
REHABILITATION OF ENSHAM OPEN-CUT COAL MINE SITE
Rehabilitation of the Ensham
open-cut coal mine near Emerald
in Central Queensland.
‘Spoil’ is the overburden removed to reveal the coal seam. Previous spoil is piled
behind the pit. In this way, the pit advances, progressively filled with new spoil.
Rehabilitation will ultimately occur over the previous spoil behind the mine.
Direction of
advance of the pit
10 A slope of 1 in 10
A bulldozer follows the pegs to deep rip along the contours to a depth of
about one metre. This increases infiltration of water and provides a rough
surface to reduce runoff and erosion. Once grass has established itself on
this surface, the contours will completely eliminate any rainwater runoff.
Small rock walls called ‘rills’ are constructed around the rehabilitation area
to stop runoff from the mine washing away the topsoil or killing the grass.
Grass is seeded at the rate of 25kg of seed per hectare by a contract farmer.
The seed is spread by a fertiliser spreader on the back of a farm tractor.
Some mines are required to return a certain number of acacia and eucalypt
stems per square metre. At Ensham, where the land will ultimately be restored
as grazing land, trees are not always desired by farmers.
Trees can only be planted on this site after the grass is established.
Otherwise, trees can get out-competed by the grass from the outset or
trees can hold up the growth of the grass and result in erosion. The most
effective way to stabilise the slopes against erosion is with grasses.
Oresomeresources.com
Some other mines have a rehabilitation requirement defined as "native self sustaining
ecosystem," so any native species able to grow on that site are encouraged.
The government provides a financial incentive to rehabilitate because the bond that
mining companies are charged for their use of the land applies only to disturbed land.
Every hectare of rehabilitation reduces this bond.
At Ensham, between 150 and 200 hectares of land are rehabilitated every year. The
company set a Queensland record in 2009 with a total of 280 hectares rehabilitated.
Oresomeresources.com