Evaluation
Chapter # 5
b) Future status: Are significant schedule changes likely? If so, indicate the nature of
the changes.
c) Status of crucial tasks: What progress has been made on tasks that could decide
Audit Report the success or failure of the project?
d) Risk assessment: What is the potential for project failure or monetary loss?
Components e) Information pertinent to other projects.: What lessons learned from the project
being audited, can be applied to other projects being undertaken by the
organization?
f) Limitations of the audit: What assumptions or limitations affect the data in the
audit?
Introduction
Cost: This section compares actual costs to budgeted costs. The time periods
for which the comparisons are made should be clearly defined. the report
should focus on the direct charges made to the project. If it is also necessary
to show project total costs, complete with all overheads, this cost data
2. Current Status
should be presented in an additional set of tables.
All issues that the auditor feels require close monitoring by senior
management should be included in this section, along with a brief
4. Critical
explanation of the relationships between these issues and the
5. Risk time/cost/performance.
Auditor/Evaluat 6) Distribute the report to the PM and project team for their
response
or
7) Follow up to see if the recommendations have been
implemented
Project Project
Audit Audit
Termination Initiation
Preliminary Establishing
Analysis of Audit
the Project Database
This step involves starting the audit
process, defining the purpose and
on Audit The required database for project audits should be specified in the
project master plan. If this is done, the necessary information will be
Database available when needed. Nonetheless, it is important to avoid collecting
“anything that might be useful,” since this can place extraordinary
information collection and storage requirements on the project
The auditor must analyze the data and then present the analysis to
managers in ways that communicate the real meaning of the
4. Preliminary audit’s findings. It is the auditor’s duty to brief the PM on all
findings and judgments before releasing the audit report. The
Analysis of the purpose of the audit is to improve the project being audited as
well as to improve the entire process of managing projects. It is not
project intended as a device to embarrass the PM.
This part of the audit life cycle includes the preparation of the
audit report, organized by whatever format has been selected for
use. A set of recommendations, together with a plan for
implementing them, is also a part of the audit report. If the
5. Audit Report recommendations go beyond normal practices of the organization,
they will need support from the policy-making level of
Preparation
management. This support should be sought and verified before
the recommendations are published.
As with the project itself, after the audit has accomplished its
designated task, the audit process should be terminated. When the
final report and recommendations are released, there will be a
6. Project Audit review of the audit process. This is done in order to improve the
methods for conducting the audit. When the review is finished, the
Termination audit is truly complete and the audit team should be formally
disbanded.