BUILDING A HOUSE
THE NETWORK
DIAGRAM IS ABOUT
CREATING
RELATIONSHIPSBET
WEEN ACTIVITIES
3
BUILDING A HOUSE
RELATIONSHIPS ARE
ALSO REFERRED TO
AS DEPENDENCIES –
THE MOST BASIC IS
“FINISH TO START”
4
BUILDING A HOUSE
BUILDING A HOUSE
THE USE OF AN
ARROW
(SPECIFICALLY IN
THE NOTATION
USED IN THIS
EXAMPLE) SHOWS
THIS RELATIONSHIP
A B
BUILDING A HOUSE
Sheet
Rock
H
THE USE OF AN
E ARROW
(SPECIFICALLY IN
Frame D HVAC
THE NOTATION
USED IN THIS
F EXAMPLE) SHOWS
THIS RELATIONSHIP
Rough
Electric
G
BUILDING A HOUSE
Sheet
Rock
H
THE USE OF AN
E ARROW
(SPECIFICALLY IN
Frame D HVAC
THE NOTATION
USED IN THIS
F EXAMPLE) SHOWS
THIS RELATIONSHIP
Rough
Electric
G
Note That E, F and G Don’t Have to Start and Finish At The Same Time
8
BUILDING A HOUSE
Sheet
Rock
H
THE USE OF AN
E ARROW
(SPECIFICALLY IN
Frame D HVAC
THE NOTATION
USED IN THIS
F EXAMPLE) SHOWS
THIS RELATIONSHIP
Rough
Electric
G
SUMMARY OF ACTIVITIES
Time Immediate
Required Predecessor
Activity Description (in days) Activities
A Excavate
B Lay foundation
C Rough plumbing
D Frame
E Finish exterior
F Install HVAC
G Rough electric
H Sheet rock
I Install cabinets
J Paint
K Final plumbing
L Final electric
M Install flooring
11
SUMMARY OF ACTIVITIES
Time Immediate
Required Predecessor
Activity Description (in days) Activities
A Excavate --
B Lay foundation A
C Rough plumbing B
D Frame B
E Finish exterior D
F Install HVAC D
G Rough electric D
H Sheet rock C, E, F, G
I Install cabinets H
J Paint H
K Final plumbing I
L Final electric J
M Install flooring K, L
Task 2
TEST THE LOGIC BY CONSTRUCTING
THE NETWORK DIAGRAM
13
C I K
Sheet
Excavate Rock
Lay
A B Foundation Finish
Exterior
H M
Install
E Flooring
J L
Frame D HVAC
Paint Final
Electric
F
Rough
Electric
G
14
SUMMARY OF ACTIVITIES
Time Immediate
Required Predecessor
Activity Description (in days) Activities
A Excavate 3 --
B Lay foundation 4 A
C Rough plumbing 3 B
D Frame 10 B
E Finish exterior 8 D
F Install HVAC 4 D
G Rough electric 6 D
H Sheet rock 8 C, E, F, G
I Install cabinets 5 H
J Paint 5 H
K Final plumbing 4 I
L Final electric 2 J
M Install flooring 4 K, L
Task 4
FILL EACH NODE AS FOLLOWS
18
ESTi EFTi
i ti
LSTi LFTi
7 10 33 38 38 42
C 3 I 5 K 4
0 3 3 7 25 33 42 46
A 3 B 4 H 8 M 4
17 25
E 8
33 38 38 40
7 17 J 5 L 2
D 10
17 21
F 4
17 23
Note:
G 6 ESTH=MAX(EFTC,EFTE,EFTF,EFTG)=25
23
7 10 33 38 38 42
C 3 I 5 K 4
22 25 33 38 38 42
0 3 3 7 25 33 42 46
A 3 B 4 H 8 M 4
0 3 3 7 25 33 42 46
17 25
E 8
33 38 38 40
17 25
7 17 J 5 L 2
D 10 35 40 40 42
7 17
17 21
F 4
21 25
Note:
17 23
LFTH=MIN(LSTI,LSTJ)=33
G 6 LFTD=MIN(LSTE,LSTF ,LSTG)=17
19 25
LFTB=MIN(LSTC,LSTD)=7
Task 6
DETERMINE THE CRITICAL PATH
26
C 3 I 5 K 4
22 25 33 38 38 42
A 3 B 4 H 8 M 4
0 3 3 7 25 33 42 46
17 25
Slack=0 Slack=0 Slack=0 Slack=0
E 8
33 38 38 40
17 25
7 17 J 5 L 2
Slack=0
D 10 35 40 40 42
7 17
Slack=2 Slack=2
17 21
Slack=0
F 4
21 25
Slack=4
Note:
17 23
Slack = LSTi-ESTi and LFTi-EFTi
G 6
19 25
Slack=2
28