0 оценок0% нашли этот документ полезным (0 голосов)
22 просмотров27 страниц
This document discusses project integration and closure. It defines project integration management as coordinating all aspects of a project to ensure they are unified, consistent and work towards overall project success. Key processes include developing the project charter, scope statement, management plan, directing execution, monitoring work, and integrated change control. When closing, the project manager verifies scope, closes procurements, addresses punch list items, captures lessons learned, writes a transition plan, and creates a closeout report. Post-project, the manager reassigns team members, celebrates successes, and ensures project benefits are realized.
Исходное описание:
Оригинальное название
2020 T2 MN601 Lecture 11.1 Project Integration and Closure.pptx
This document discusses project integration and closure. It defines project integration management as coordinating all aspects of a project to ensure they are unified, consistent and work towards overall project success. Key processes include developing the project charter, scope statement, management plan, directing execution, monitoring work, and integrated change control. When closing, the project manager verifies scope, closes procurements, addresses punch list items, captures lessons learned, writes a transition plan, and creates a closeout report. Post-project, the manager reassigns team members, celebrates successes, and ensures project benefits are realized.
This document discusses project integration and closure. It defines project integration management as coordinating all aspects of a project to ensure they are unified, consistent and work towards overall project success. Key processes include developing the project charter, scope statement, management plan, directing execution, monitoring work, and integrated change control. When closing, the project manager verifies scope, closes procurements, addresses punch list items, captures lessons learned, writes a transition plan, and creates a closeout report. Post-project, the manager reassigns team members, celebrates successes, and ensures project benefits are realized.
Project Integration Management PMBOK • Project Integration Management: “The processes and activities needed to integrate the various elements of project management, which are identified, defined, combined, unified, and coordinated within the Project Management Process Groups.” – PMBOK
2020 T2 Compiled by: Dr Nalin Sharda 3
Project Integration Management • The Key to Overall Project Success: Good Project Integration Management – Project managers must coordinate all of the other knowledge areas throughout a project’s life cycle. – Focus on the big picture and steer the project team toward successful completion. – Project integration management is not the same thing as software integration.
2020 T2 Compiled by: Dr Nalin Sharda 4
Project Integration Management Processes • Develop the project charter: working with stakeholders to create the document that formally authorises a project—the charter. • Develop the preliminary project scope statement: working with stakeholders, especially users of the project’s products, services, or results, to develop the high-level scope requirements and create a preliminary project scope statement. • Develop the project management plan: coordinating all planning efforts to create a consistent, coherent document—the project management plan.
2020 T2 Compiled by: Dr Nalin Sharda 5
Project Integration Management Processes • Direct and manage project execution: carrying out the project management plan by performing the activities included in it. • Monitor and control the project work: overseeing project work to meet the performance objectives of the project. • Perform integrated change control: coordinating changes that affect the project’s deliverables and organisational process assets. • Close the project: finalising all project activities to formally close the project.
2020 T2 Compiled by: Dr Nalin Sharda 6
Project Integration Management Summary
2020 T2 Compiled by: Dr Nalin Sharda 7
Project Integration Management Processes QUIZ: 1. Explain the meaning of Project Integration Management, and the processes followed for the same.
2020 T2 Compiled by: Dr Nalin Sharda 8
Close Project
• A project moves into the closing stage when
customers accept the project deliverables • A project can close as planned or be terminated early • Complete closing activities
2020 T2 Compiled by: Dr Nalin Sharda 9
Close Project • Verify Scope - “the process of formalising acceptance of the completed project deliverables.” - PMBOK – Formal acceptance of project deliverables. – Proceed to closing and realising stage. – Buyer provides the seller with a formal written acceptance. – A project closeout checklist may itemise typical project activities and/or deliverables. • Close Procurements - – Verify that proper methods were used for all purchasing. – Verify all contracts have been successfully completed.
2020 T2 Compiled by: Dr Nalin Sharda 10
“A punch list is a document prepared near the end of a construction project listing work not conforming to contract specifications that the contractor must complete prior to final payment.[1] The work may include incomplete or incorrect installations or incidental damage to existing finishes, material, and structures.” Ref: https://en.wikipedia.org/wiki/Punch_list
2020 T2 Compiled by: Dr Nalin Sharda 11
Close Project Terminate Projects Early: – Mutual Agreements • What deliverables or partial deliverables go to the buyer • What compensation goes to the seller • Resolve outstanding issues. – Terminations for Default • Problems with the project’s cost, schedule, or performance • Lost confidence in the contractor – Terminations for Convenience of Buyer • The buyer faces unexpected difficulties or changing priorities • Customer’s needs change • Invoke a contract clause
2020 T2 Compiled by: Dr Nalin Sharda 12
Close Project • Finalise all activities needed to finish the project – Write transition plan – Knowledge management – Create the closeout report
2020 T2 Compiled by: Dr Nalin Sharda 13
Close Project Write Transition Plan • Charter / instruction manual for how the customer should use the project deliverables • Ensure all responsibilities are considered • Provide appropriate documentation to users • A transition plan helps to ensure: – Quality problems are avoided during transition – Project deliverables transition into operational role – Needed maintenance, upgrades, and training take place
2020 T2 Compiled by: Dr Nalin Sharda 14
Close Project Knowledge Management • Should occur throughout the project life • Most apparent as a project comes to a close • Capture lessons learned • Disseminate and use lessons learned
2020 T2 Compiled by: Dr Nalin Sharda 15
Close Project Project Customer Feedback Form
2020 T2 Compiled by: Dr Nalin Sharda 16
Capture Lessons Learned Knowledge Management: • What worked well? • Where might a different method may yield better results? – At milestones and at the end of a project • Ask participants to identify major project issues. • Go through one top issue at a time to determine what went wrong and how it might be avoided in future projects. • List significant successes and discuss what caused each.
2020 T2 Compiled by: Dr Nalin Sharda 17
Capture Lessons Learned
Knowledge Management:
2020 T2 Compiled by: Dr Nalin Sharda 18
Capture Lessons Learned
Knowledge Management:
2020 T2 Compiled by: Dr Nalin Sharda 19
Close Project
Disseminate & Use Lessons Learned
• Establish a method for documenting and sharing lessons learned. • Decide how to store lessons for easy access. • Code (classify) each lesson by type of project, stage in project life cycle, issue it concerns. • Have one person assigned to “own” the lessons learned database. 2020 T2 Compiled by: Dr Nalin Sharda 20 Close Project
Create the Closeout Report
– Summary status of the project – Lessons learned – Review of project’s original justification – Ensure records are in a workable format – Store records for easy access Did the project accomplish what it was originally approved to do?
2020 T2 Compiled by: Dr Nalin Sharda 21
Close Project QUIZ: 1. When can you consider a project is properly closed? 2. List and describe the essential aspects of proper closing of a project.
2020 T2 Compiled by: Dr Nalin Sharda 22
Post Project Activities • Reassign workers – PMs provide timely updates for personnel records. – PMs make honest recommendations for team members. – PMs help team members secure next assignments. Helping good workers secure follow-on work is one of the most important things a project manager must do. • Celebrate success and reward participants
“the project is over; we will limit any
additional work on this project.”
2020 T2 Compiled by: Dr Nalin Sharda 23
Post Project Activities • Provide Ongoing Support – Training, change management, other services – Project transition plans are a sort of charter for the customer. • “instruction manual” on how the customer should use the project deliverables once the project team has completed its work • Ensure Project Benefits are Realised – How well the customers are able to use the deliverables? – Consider use by direct customers and other stakeholders.
2020 T2 Compiled by: Dr Nalin Sharda 24
Close Project QUIZ: 1. After you close a project, is you responsibility as a project manager over? 2. What must you do after closing a project to become a reputable project manager?
2020 T2 Compiled by: Dr Nalin Sharda 25
Conclusions
1. Project Integration Management implies that we consider the entire
project and its constituent activities as an integrated system. 2. Project Integration Processes should have a clear method for transitioning from the project Charter to Scope to Plan, incorporating all aspects of the project. 3. Capture Lessons Learned in the project’s closing state, such these lessons are disseminated to all concerned in a format that makes it easy to use these lessons in the future. 4. Create the Closeout Report to ensure that the client is satisfied and is able to give feedback, along with that from the project team members. 5. Post Project Activities must ensure that the client gets all support need to use the project deliverables.
2020 T2 Compiled by: Dr Nalin Sharda 26
References Acknowledgement: Some of the text in this lecture is taken almost verbatim from the following references: 1. T. J. Kloppenborg, Contemporary Project Management: Organize, Plan and Perform, South- Western Cengage Learning, 2012. 2. Prepare PM, “Project Integration Management”, Preparepm.com http://www.preparepm.com/notes/integration.html (accessed Sep. 25, 2017).