Академический Документы
Профессиональный Документы
Культура Документы
Should we
build this
plant?
10-1
Capital Budget
10-2
What is capital budgeting?
10-3
Definition of Capital Budgeting'
10-4
Project Classification
10-5
Steps to capital budgeting
10-6
What is the difference between independent
and mutually exclusive projects?
• Independent projects –
• Mutually exclusive projects –
10-7
Methods to decide weather the project should
be accepted or not .
• Payback Period
• Discounted Payback Period
• NPV
• IRR
• Profitability Index
10-8
What is the payback period?
10-9
Calculating payback
0 1 2 2.4 3
Project L
CFt -100 10 60 100 80
0 1 1.6 2 3
Project S
CFt -100 70 100 50 20
10-11
Strengths and weaknesses of payback
• Strengths
• Provides an indication of a project’s risk and liquidity.
• Easy to calculate and understand.
• Weaknesses
• Ignores the time value of money.
• Ignores CFs occurring after the payback period.(Example)
10-12
Discounted payback period
10-13
Discounted payback period
0 10% 1 2 2.7 3
CFt -100 10 60 80
PV of CFt -100 9.09 49.59 60.11
10-14
WHAT IS THE DIFFERENCE BETWEEN THE
REGULAR AND DISCOUNTED PAYBACK
PERIODS?
10-15
Net Present Value
10-16
Discount Rate
• The rate used to discount future cash flows to the present value is a
key variable of this process.
• A firm's Weighted average cost of capital (after tax) is often used, but
many people believe that it is appropriate to use higher discount
rates to adjust for risk or other factors.
10-17
Selection of discount rate
10-18
Net Present Value (NPV)
n
CFt
NPV t
t 0 ( 1 k )
10-19
What is Project L’s NPV?
NPVS = $19.98
10-20
Solving for NPV:
Financial calculator solution
• Enter CFs into the calculator’s CFLO register.
• CF0 = -100
• CF1 = 10
• CF2 = 60
• CF3 = 80
10-21
Rationale for the NPV method
10-23
Internal Rate of Return (IRR)
• IRR is defined as the discount rate that equates the present value of
a project’s expected cash inflows to the present value of the
project’s cost.
OR
10-24
Internal Rate of Return (IRR)
10-25
How is a project’s IRR similar to a
bond’s YTM?
• They are the same thing.
10-26
• IRR IS THE EXPECTED RATE OF RETURN ON THE PROJECT, JUST AS
THE YTM IS THE PROMISED RATE OF RETURN ON A BOND.
10-27
Rationale for the IRR method
• Hurdle Rate:
• The discount rate (cost of capital) that IRR must exceed if a
project is to be accepted.
• If IRR > WACC, the project’s rate of return is greater than its
costs. There is some return left over to boost stockholders’
returns.
10-28
IRR Acceptance Criteria
10-29
• If an independent project is being evaluated, then the NPV and IRR
criteria always lead to the same accept/reject decision.
• Because whenever a project’s cost of capital is less than its IRR , its
NPV is positive.
10-30
• However when evaluating mutually exclusive projects, the NPV
method should be used.
10-31
WOULD THE PROJECTS’ IRRs CHANGE IF
THE COST OF CAPITAL CHANGED?
• ANSWER: IRRs ARE INDEPENDENT OF THE COST OF CAPITAL.
THEREFORE IRR WILL NOT CHANGE IF k CHANGES.
10-32
Advantages of IRR
10-33
Problems with IRR
• There are a number of projects for which using IRR is not as effective as
using NPV to discount cash flows: it uses one single discount rate to
evaluate the whole investment. (discount rate usually changes with
time).
10-34
• The advantage to using the NPV method here is that NPV can handle
multiple discount rates without any problems.
10-35
Drawing NPV profiles
NPV 60
($)
50 .
40 .
. Crossover Point = 8.7%
30 .
20 . IRRL = 18.1%
.. S IRRS = 23.6%
10
L . .
0 . Discount Rate (%)
5 10 15 20 23.6
-10
10-36
Reinvestment rate assumptions
10-37
Project P has cash flows (in 000s): CF0 = -
$800, CF1 = $5,000, and CF2 = -$5,000. Find
Project P’s NPV and IRR.
0 1 2
k = 10%
10-38
Multiple IRRs
IRR2 = 400%
450
0 k
100 400
IRR1 = 25%
-800
10-39
Why are there multiple IRRs?
10-40
Profitability Index (Benefit-cost Ratio)
10-42
EXAMPLE:
• PROJECT OUTLAY £10M
• PRESENT VALUE £14M
• NPV £4M
• PI = £14M / £10M = 1.4
• WHY?
10-43
• IF THE GOAL IS ASSUMED TO MAXIMISE THE SHARE PRICE
THEN THIS IMPLIES MAXIMISING NPV FOR THE MINIMUM
AMOUNT OF INVESTMENT.
10-44
• HOWEVER,
• IF THE GOAL IS MAX V│MAX P THEN THIS TELLS US TO MAXIMISE THE
SCALE OF THE BUSINESS, ie TO MAX PV AS WELL AS NPV.
10-45
• BECAUSE OUTLAY IS NOT A COST BUT REPRESENTS THE SIZE OF THE
INVESTMENT.
10-46
• THE DENOMINATOR REPRESENTS THE SIZE OF THE INVESTMENT i.e.
£10M
10-47
• FINALLY, UNDER CAPITAL RATIONING THE GOAL IS MAX V│MAX P (AND
THEREFORE MAX PV│MAX NPV) SUBJECT TO THE AMOUNT OF CAPITAL
AVAILABLE.
10-48
CONCLUSION
• UNDER NORMAL, NON-RATIONING CONDITIONS P.I. IS A TOTALLY
MISLEADING RATIO, SINCE, FOR A GIVEN NPV, A LOW P.I. IS BETTER
THAN A HIGH ONE
10-49
• Post Audit
-improve forecasts
-improve operations.
10-50