Академический Документы
Профессиональный Документы
Культура Документы
RADIATION PROTECTION IN
DIAGNOSTIC AND
INTERVENTIONAL RADIOLOGY
IAEA
International Atomic Energy Agency
Introduction
IAEA
International Atomic Energy Agency
Purpose of Shielding
• To protect:
• the X Ray department staff
• the patients (when not being examined)
• visitors and the public
• persons working adjacent to or near the X Ray
facility
Equipment
• What equipment is to be used?
• General radiography
• Fluoroscopy (with or without radiography)
• Dental (oral or OPG)
• Mammography
• CT
Usage
• Different X Ray equipment have very
different usage.
• For example, a dental unit uses low mAs
and low (~70) kVp, and takes relatively few
X Rays each week
• A CT scanner uses high (~130) kVp, high
mAs, and takes very many scans each
week.
IAEA 12: Shielding and X Ray room design 10
Shielding Design (IV)
Positioning
• The location and orientation of the X Ray
unit is very important:
• distances are measured from the equipment
(inverse square law will affect dose)
• the directions the direct (primary) X Ray beam
will be used depend on the position and
orientation
A to G are points
used to calculate
shielding
Surrounding areas
• The X Ray room must not be designed
without knowing the location and use of all
rooms which adjoin the X Ray room
• Obviously a toilet will need less shielding
than an office
• First, obtain a plan of the X Ray room and
surroundings (including level above and
below)
IAEA 12: Shielding and X Ray room design 15
Radiation Shielding - Design Detail
Must consider:
• appropriate calculation points, covering all
critical locations
• design parameters such as workload,
occupancy, use factor, leakage, target dose
(see later)
• these must be either assumed or taken from
actual data
• use a reasonable worst case more than typical
case, since undershielding is worse than
overshielding
IAEA 12: Shielding and X Ray room design 16
IAEA Training Material on Radiation Protection in Diagnostic and Interventional Radiology
IAEA
International Atomic Energy Agency
Radiation Shielding Parameters (I)
U - use factor
• fraction of time the primary beam is in a
particular direction i.e.: the chosen
calculation point
• must allow for realistic use
• for all points, sum may exceed 1
T - Occupancy
• T = fraction of time a particular place is
occupied by staff, patients or public
• Has to be conservative
• Ranges from 1 for all work areas to 1/20 for
toilets and 1/40 for unattended car parks
W - Workload
• A measure of the radiation output in one
week
• Measured in mA-minutes
• Varies greatly with assumed maximum kVp
of X Ray unit
• Usually a gross overestimation
• Actual dose/mAs can be estimated
IAEA 12: Shielding and X Ray room design 27
Workload (I)
SO HOW DO WE ESTIMATE W ?
IAEA
International Atomic Energy Agency
Shielding - Construction I
Materials available:
• lead (sheet, composite, vinyl)
• brick
• gypsum or baryte plasterboard
• concrete block
• lead glass/acrylic
Average dose per unit workload of 4.72mGy [2,3] Field size of 1000cm². Relate this
per week at 1 meter distance. to the standard 400cm²
IAEA
Solution (a) 1/8
W = (mAs/film) x (patients/day) x
(films/patient) x (days/week)
= 20 x 100 x 3 x 7
= 42,000 mAs/week
= 700mAmin/week
IAEA 12: Shielding and X Ray room design 52
Solution (a) 2/8
P1 = (mAmin/week) x (Average
dose per unit workload in mGy/week)
= 700 x 4.72
= 3,304mGy/week
P = (P1 x U x T)/d²
= (3,304 x 0.25 x 1)/2.5²
= 132.16mGy/week
= 0.006/137.59
= 0.000044
IAEA 12: Shielding and X Ray room design 58
Solution (a) 8/8 Shielding Calculation
From graph below a lead of thickness approximately
2.6mm is necessary.
Reduction factor
50 75 kV 100 150 200 kV
105
250
104
300 kV
103
102
10 Lead Required
1 2 3 4 5 6 7 8 mm
IAEA 12: Shielding and X Ray room design 59
Question for shielding calculation
Computer Tomography
IAEA
Solution (b) 1/9
1
0.5703 B 1 ( / ) 316 .5991
1 ( / ) 5.0991
x= 0.5703 x ln(316.5991/5.0991)
x= 2.35 mm of lead
1
380519 B 1 ( / ) 314 .4338
1 ( / ) 2.9338
IAEA 12: Shielding and X Ray room design 70
Solution (b) 9/9
x = 38.0519 x ln(314.4338/2.9338)
x =177.8727mm of concrete