Академический Документы
Профессиональный Документы
Культура Документы
Cost Management
is “ the completion of the project management triple constraint of
cost, schedule, and scope.”
If the project team does not properly control cost, the project will invariably
go out of control and more money will be spent than anticipated.
It is the purpose of cost management to prevent this.
• Lately it has become important to consider the cost of the project for the FULL
LIFE OF THE SERVICE that is created
• With regard to project life cycle, Cost decisions are made with a clearer picture of
the future commitments that the project will require .
Cost Management processes
Project cost management includes the processes required to ensure that the project
is completed within the approved budget.
Expected
Cash flow
Cost Baseline is a time-phased
CUMMULATIVE VALUES
It is developed by summing
estimated costs by period and is
usually displayed in the form of
Cost Performance S- curve
Baseline
TIME
Many projects , especially larger ones, may have multiple cost baselines to measure different
aspects of cost performance . Ex. A spending plan or cash flow forecast is a cost baseline for
measuring disbursements
Cost Estimating
• A Cost Estimate is “ a prediction o the likely cost of the resources that will be
required to complete all of the work of the project”.
• Cost estimating is done throughout the project.
• Types of Estimates: depending on the accuracy required for the estimate and the cost and
effort that can be expended.
Bottom Up Estimates
Are used when the project baselines are required or a definitive type of estimate is needed
“ Bottom Up” cause they begin by estimating the details of the project and then
summarizing the details into summary level. WBS can be used for this roll up.
Advantage : produce accurate results .Accuracy depends on the level of detail.
Disadvantage : higher cost for detailed estimating. Longer time to produce
Analogous Estimates
Are a form of Top Down estimates.
Uses the actual cost of previously completed projects
to predict the cost of the project, thus there is an analogy between one project and the other
Advantage : If the project being used in the analogy and the project being estimated are
very similar, then the estimates could be quite accurate
Disadvantage : If projects are not similar, then the estimates will not be accurate at all.
Parametric Estimates
Are also Top Down estimates.
Their inherent accuracy is no beter or worse than analogous estimates.
Accomplished by finding a parameter of the project that changes proportionately with
project cost. A model is built mathematically based on one or more parameter . When the
values of the parameters are entered into the model the cost of the project results.
Accuracy can be improved if there is a closed relationship between the parameters and cost
and parameters are easy to quantify.
Definitive Estimates
Are a form of Bottom Up estimates.
Used to establish a project baseline or any other important estimate.
WBS can be used as the level of detail for the estimate.
Advantage : Accuracy quite high
Disadvantage : Cost of development of the estimate can be quite high and lengthy
Cost Budgeting
“Is the process of allocating cost to the individual work items in the project”
“Is the process of controlling the project and taking correction action when
the control indicates that corrective action is necessary”
Plan
0
UNDER Actuals
TIME
If the project follows the project plan, each of these three parameters
are exactly the same . Significant deviations between the values of the
three parameters PV,AC, EV are cause of concern
Glossary of Terms
$500 125%
EAC
ACWP Actual Cost
$300 75%
BCWP
$200 50% Earned Value
CV
$100 25%
SV
10 20 30 40
Project Duration
Project Cost Summary Report
1 6 8 (-2) 6 8 (-2)
2 10 4 6 20 18 2
3 15 6 9 30 35 (-5)
4 16 12 4 24 30 (-6)
5 0 2 (-2) 16 18 (-2)
6 16 20 (-4)
7 10 10 0
8 15 15 0