Академический Документы
Профессиональный Документы
Культура Документы
O P M
PROJECT MANAGEMENT
By: HAKEEM UR REHMAN PCBA UCP
WHAT IS A PROJECT?
Non Routine, one time effort, limited by time and resources, and performance specifications designed to meet customer needs. (or) Special operations designed to accomplish a set of objectives in a limited time frame.
Good project management deals with three factors: factors: time, cost and performance. performance. Some specific ones include
Gantt charts, PERT charts, critical path analysis (time) Cost estimates and Earned Value Analysis (cost) A hierarchical method that successively subdivides the work of the project into smaller details. details. Such a structure defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities, and measurement and control of the project. project.
Level 2
Level 3
GANTT CHART
0
Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work
Month 4 |
| 8
|10
3 Month
Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Slack: amount of time an activity can be delayed without delaying the project
3.
4. 5.
6.
7.
8.
Networks typically flow from left to right. An Activity cannot begin until all preceding activities have been completed. Arrows on networks indicate precedence and flow. Arrows can cross over each other. Each activity should have a unique identification number. An activity identification number must be larger than that of any activities preceding it. Looping in not allowed (in other words recycling through a set of activities cannot take place). Conditional statements are not allowed (i.e. this type of statement should not appear: if successful, do something; if not, do nothing) When there are multiple starts, a common start node can be used to indicate a clear project beginning on the network. Similarly, a single project end, node can be used to indicate a clear ending.
Activity
An element of the project that require time; may or may not required resources Description of activities should use verb/noun format; develop project specifications More than one activity immediately preceding it ( more than one arrow flowing to it) Activities that can take place at the same time, if the manager wishes; may or may not occur simultaneously A sequence of connected, dependent activities Longest path (s) through the network; if an activity on the path is delayed, the project is delayed the same amount of time. A point in time when the activity is started or finished; does not consume time More than one activities immediately following it ( more than one dependency arrow flowing from it) A dummy activity, which is normally depicted by a dashed arrow, consumes no time or resources.
Merge Activity
Parallel Activities
Path
Critical Path
Event
Burst Activity
Dummy Activity
Z
Y and Z can begin at the same time, if you wish
(A)
(B)
Activity
J K L
On
J,K & L can begin at the same time, if you wish (they need not occur simultaneously)
AA
AA is preceded by X and Y
(C)
(D)
Activity
On
1. Activity C can start immediately after A and B are completed. 2. Activity E can start immediately after only B is completed. A 1 D B 2 E
Immediate Predecessor(s) A B B A C D A E, G, H F, I, J
AOA Network:
F 2 C 3 1 5 B D E 4 6 H I 7 G J K 9 8
A B C D E F G H I
Procurement of parts for sub Procurement of parts for sub Procurement of parts for sub Building sub Building sub Building sub Building sub assembly 1 assembly 2 assembly 4 assembly 3
PROGRAM/PROJECT EVALUATION & REVIEW TECHNIQUE (PERT) (PERT) & CRITICAL PATH METHOD (CPM) (CPM)
In 1957 the Critical Path Method (CPM) was developed as a network model for project management. CPM is a deterministic management. method that uses a fixed time estimate for each activity. While activity. CPM is easy to understand and use, it does not consider the time variations that can have a great impact on the completion time of a complex project. project. The Program Evaluation and Review Technique (PERT) is a network model that allows for randomness in activity completion times. times. PERT was developed in the late 1950's for the U.S. Navy's 1950's Polaris project having thousands of contractors. It has the potential to reduce both the time and cost contractors. required to complete a project. project.
CPM: EXAMPLE
CPM Network
2
f, 15 g, 17
6
a, 6
h, 9 i, 6
8
b, 8
3
d, 13
7
j, 12
c, 5 e, 9
4
Performing few simple computations allows PM to complete a process know as Forward and Backward Pass FORWARD PASS
1. 2. 3.
EARLIEST TIMES
ES) EF) ET)
How soon can the activity start? (early start How soon can the activity finish? (early finish
BACKWARD PASS
1. 2. 3.
LATEST TIMES
LS) LF)
How late can the activity start? (late start How late can the activity finish? (late finish
Which activities represent critical path (CP)? This is the longest path in the network which, when delayed, will delay the project How long can the activity be delayed? (slack or float SL)
4.
CPM Example
ES and EF Times
2
f, 15 6 21 g, 17 6 23
6
a, 6 0 6
1
i, 6 23 29
h, 9 21 30
b, 8 0 8 c, 5 0 5
4 3
d, 13 8 21 e, 9 5 14
7
j, 12 21 33 Projects EF = 33
Backward Pass
1. Subtract
CPM Example
LS and LF Times
2
a, 6 0 6 3 9 b, 8 0 8 0 8 c, 5 0 5 7 12
f, 15 6 21 9 24 g, 17 6 23 6 10 27 d, 13 8 21 8 21 e, 9 5 14 12 21
i, 6 23 29 27 33
h, 9 21 30 24 33
j, 12
7
21 33 21 33
SL
Forward & Backward Passes Computed Possible to determine which activities can be delayed by computing Slack or Float LS LF ES = SL EF = SL
Total Slack: tells us the amount of time an activity can be delayed; not delay project
CPM Example
SLACK
a, 6 3 0 6 3 9 b, 8 0 0 8 0 8 c, 5 0 5 7 7 12 f, 15 3 6 21 9 24 2 g, 17 6 4 6 23 10 27 d, 13 8 21 0 8 21 e, 9 5 14 7 12 21
5
i, 6 23 29 4 27 33
h, 9 3 21 30 24 33
j, 12 21 33 0 21 33
CRITICAL PATH
a, 6
CPM Example
f, 15
2 5
g, 17
6
h, 9 i, 6
8
b, 8
3
d, 13
j, 12
7
c, 5 e, 9
4
CPM Example
Critical Path: 1 3 7 8
PRACTICE QUESTION
Network Information Country Engineers Design Department
ACTIVITY
A B C D E F G H
DESCRIPTION
Application Approval Construction Plans Traffic Study Service Availability Check Staff Report Commission Approval Wait for Construction Occupancy
PROCEDING ACTIVITY
None A A A B,C B,C,D F E,G
The technique is based on the that an activity s duration probability distribution instead single value. value. The probabilistic information activities is translated into information about the project. project.
PERT
Three time estimates are required to compute the parameters of an activity s duration distribution:
Pessimistic Time (tp ) - the longest time that an activity might require. require. Three standard deviations from the mean is commonly used for the pessimistic time. Most Likely Time (tm ) - the completion time having the highest probability. Note that this time is different from the expected time probability. Optimistic Time (to ) - generally the shortest time in which the activity can be completed. It is common practice to specify optimistic times to be three completed. standard deviations from the mean so that there is approximately a 1% chance that the activity will be completed within the optimistic time.
PERT
PERT assumes a beta probability distribution for the time estimates. estimates. For a beta distribution, the expected time and variance for each activity can be: be: Expected time = ( Optimistic + 4 x Most likely + Pessimistic ) / 6 te = ( to + 4tm + tp ) / 6 Variance = [ (Pessimistic Optimistic) / 6 ] 2 Vt = [ ( tp - to ) / 6 ] 2
PERT : EXAMPLE
Immed. Immed. Optimistic Most Likely Pessimistic Predec. (Hr.) Time (Hr.) Activity Predec. Time (Hr.) Time (Hr.) A -4 6 8 B -1 4.5 5 C A 3 3 3 D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 K G,I 3 5 7
PERT : EXAMPLE
PERT NETWORK
D
C B F G I K
PERT : EXAMPLE
Activity A B C D E F G H I J K Expected Time 6 4 3 5 1 4 2 6 5 3 5 Variance 4/9 4/9 0 1/9 1/36 1/9 4/9 1/9 1 1/9 4/9
SOLUTION
EARLIEST/LATEST TIMES:
Activity A B C D E F G H I J K ES 0 0 6 6 6 9 9 13 13 19 18 EF 6 4 9 11 7 13 11 19 18 22 23 LS 0 5 6 15 12 9 16 14 13 20 18 LF 6 9 9 20 13 13 18 20 18 23 23 Slack 0 *critical 5 0* 9 6 0* 7 1 0* 1 0*
PERT : EXAMPLE
Activities on the Critical Path: A C F I K Total Project Time: 6+3+4+5+5 = 23
PERT : EXAMPLE
Activity A B C D E F G H I J K Expected Time 6 4 3 5 1 4 2 6 5 3 5 Variance 4/9* 4/9 0* 1/9 1/36 1/9* 4/9 1/9 1* 1/9 4/9*
PERT : EXAMPLE
Probability the project will be completed within 24 hours Vpath = VA + VC + VF + VI + VK = 4/9 + 0 + 1/9 + 1 + 4/9 = 2 Wpath = 1.414 Expected Time = EA + EC + EF + EI + EK =6+ 3 +4 +5 +5 = 23
What is the probability that the project will be completed within the 24 hours?
PERT : EXAMPLE
.2612 .5000
23
24
From the Standard Normal Distribution table: P(z < .71) = .5 + .2612 = .7612
PRACTICE QUESTION
A medical institute is planning to hold an annual conference on eradication of cancer. In order to coordinate the project, it was decided to use PERT network. The major activities and time estimates a, m, and b for each activity are carefully computed and gives as follows.
Activities A B C D E F G Predecessors a A A A B, C D 2 10 8 10 7 9 3 Estimates m 4 12 9 15 7.5 9 3.5 b 12 26 10 20 11 9 7
H E, F, G 5 5 5 1) Draw the PERT diagram for the project. 2) Compute Expected Time and Variance for each activity. 3) Compute ES, EF, LS, LF and Slack time.
4) Identify the critical path and find its length and variance. 5) What is the probability that the project will be completed within 30 days?
QUESTIONS