Вы находитесь на странице: 1из 11

PM Project:

E-commerce website for


bhavna furnitures
Shubham Bagdare (N003)
Sonakshi Darak (N006)
Madhumita Joshi (N015)
Aditya Khandelwal (N235)
Devesh Mungad (N250)
Introduction

 Before the pandemic, Bhavna Furnitures had been operating as a B2B furniture supplier mainly to educational institutes
and business was booming. However, due to the lockdown they had to convert to a B2C model as their primary customers
were not operating. Initially, the work-from-home scenario created a problem for Bhavna Furnitures who felt that the
transition would be tough. Nevertheless, their product catalogue was large and customer service was very good. Locals
began to buy furniture from them and with rising popularity, people from nearby regions also started to visit their
showrooms.

 Initially they were only operating through whatsapp and printed catalogues but with the lifting of lockdown for the
foreseeable long-term future and increased popularity in B2C space, they found it would be prudent to create a website
for their catalogue. This project report is a study on the same, where the aim is to create a website for their business
within stipulated time and cost. The website must be attractive, simple to navigate, user friendly and must be able to
display entire catalogue in all available variations. The application will help to improve customer base size, automate
buying and viewing process and allow the organization to invest into high profile clients more immersively.
Closure Project Life Cycle
Successfully deploying the
website. 5
Monitoring
Continuous monitoring for bugs,
4 12
updating and improvements. 11 1
10 2
A 5-step framework designed to
Execution
Basic Layouts, Content Gathering
and Inputs, Prototype Assembly,
3 9 3 help project managers guide
their projects successfully from
Coding & Integration, Testing & start to finish
Review
8 4
Planning 7 5
Website Breakdown, Software &
Hardware Requirements,
2 6
Budgeting & Scheduling,
Milestone Setting

Initiation
Information Gathering, Client
Requirement, Setting Project
Outcomes and Expectations
1
WBS
CPM Tabular Form
Activity Description Predecessor Duration ES EF LS LF Slack Resources
(Weeks)
A Information Gathering - 2 0 2 0 2 0 2
B Software and Hardware Procurement A 2 2 4 2 4 0 2
C Wireframes and Sitemap B 3 4 7 4 7 0 3
D Design: Page Layout C 5 7 12 7 12 0 4
E Review, Changes and Approval E 4 12 16 12 16 0 4
F Content Research C 2 7 9 11 13 4 2
G Content Writing F 3 9 12 13 16 4 3
H Assembly E,G 2 16 18 16 18 0 5
I Frontend Development H 8 18 26 18 26 0 4
J Backend Development H 6 18 24 20 26 2 4
K Final Product Integration I,J 3 26 29 26 29 0 6
L Final Testing, Review and
Deployment K 4 29 33 29 33 0 5
CPM
Gantt Chart for Resource Allocation
Gantt Chart for Resource Allocation

Resource Allocation Gantt Chart (Developers)


9

6
Developers Required

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

Weeks

A B C D E F G
H I J K L Developers
Budget Estimation
Description PV AV EV

Information Gathering 60000 40000 65000

Software and Hardware Procurement 780000 970000 650000

Wireframes and Sitemap 135000 150000 60000

Design: Page Layout & Review, Changes and Approval 540000 600000 300000

Content Research & Content Writing 195000 165000 50000

Assembly 150000 175000 145000

Frontend + Backend 840000 1000000 1200000

Final Product Integration 270000 350000 350000

Final Testing, Review and Deployment 300000 320000 450000

Total BAC = 3270000 3770000 3270000


Budget Estimation
Earned Value Management (EVM)
4000000
3770000

3500000
3270000

3000000

2500000
Value

2100000
2000000
1860000

1500000
1270000

1000000

500000

0
1 2 3 4 5 6 7 8 9

Time by Activity Completion

Planned Value Actual Value Earned Value


Limitations

 Output is dependent on input data.


 It is difficult to specify the constraints even
after the determination of objective function
 It gives results on past data

Вам также может понравиться