Академический Документы
Профессиональный Документы
Культура Документы
1- 1
Anggaran
Proyek
Jadwal Waktu
Kualitas Kinerja
Function-driven organization
Risk management influences the project plan and changes assumptions in the project rules
A Gantt chart is a simple horizontal bar chart that depicts project tasks against a calendar. Each bar represents a named project task. The tasks are listed vertically in the left-hand column. The horizontal axis is a calendar timeline.
PERT Chart
Project Initiation
5-3-2001 5-3-2001 N/A N/A Task Scheduled Scheduled Start Finish Actual Actual Start Finish intertask dependency
Legend
Task Scheduled Scheduled Start Finish Actual Actual Start Finish
Problem Analysis
5-12-2001 5-12-2001 6-12-2001 6-14-2001
Requirements Analysis
5-28-2001 5-30-2001 7-15-2001 7-18-2001
Decision Analysis
6-13-2001 6-13-2001 7-30-2001 8-3-2001
Design
7-3-2001 7-5-2001 9-25-2001 10-9-2001
Construction
7-19-2001 7-20-2001 11-13-2001 In Progress
Implementation
9-10-2001 TBD 12-14-2001 TBD
Gantt Chart
2001 ID 1 2 3 4 5 Task Name May Preliminary investigation Problem analysis Requirements analysis Decision analysis Design Jun Jul Aug Sep Oct Nov Dec
6
7
Construction
Implementation
Today
Complete Task
Legend
Incomplete Task
SCHEDULE
DEVELOPMENT
SCOPE DEFINITION
COST ESTIMATING
PROJECT PLAN
FACILITATING PROCESSES
CORE PROCESSES
SCOPE PLANNING Setiap proyek harus jelas lingkup pekerjaannya, sehingga bisa dibuat struktur penjabaran pekerjaan (WBS) yang lebih detail, dalam hal ini perlu dibuat perencanaan lingkup pekerjaan Dari WBS yang ada harus disusun urutan pekerjaan yang sesuai dengan logika ketergantungan, sehingga diperoleh suatu metoda pelaksanaan yang benar/logis.
ACTIVITY
SEQUENCING
SCOPE DEFINITION Dari perencanaan lingkup pekerjaan harus dilakukan pendefinisian/ ketentuan lingkup pekerjaan itu sendiri
ACTIVITY DEFINITION Dari definisi lingkup pekerjaan harus dilakukan pendefinisian/ ketentuan setiap aktivitas pekerjaan
Dari setiap aktivitas harus dihitung durasi masing2 aktivitas, berdasarkan kapasitas produksi dan sumber daya (orang, bahan dan alat) yang tersedia
CORE PROCESSES
Dari WBS yang ada harus disusun urutan pekerjaan yang sesuai dengan logika ketergantungan ACTIVITY
SEQUENCING
SCHEDULE
Durasi masing2 aktivitas, berdasarkan kapasitas produksi dan sumber daya (orang, bahan dan alat) yang tersedia Dari definisi lingkup pekerjaan harus dilakukan pendefinisian/ ketentuan setiap aktivitas pekerjaan SCOPE DEFINITION
DEVELOPMENT
Berdasarkan WBS, logika ketergantungan dan durasi disusun Time Schedule rencana
RESOURCE PLANNING
Berdasarkan lingkup pekerjaan harus direncanakan sumber daya (bahan, alat, SDM) yang akan digunakan Berdasarkan lingkup pekerjaan dan sumber daya dihitung estimasi biaya pelaksanaan
COST ESTIMATING
CORE PROCESSES
Berdasarkan WBS, logika ketergantungan dan durasi disusun Time Schedule rencana
SCHEDULE
DEVELOPMENT
COST BUDGETING
Berdasarkan Time Schedule rencana dan Estimasi Biaya Pelaksanaan disusun Rencana Biaya Pelaksanaan (RAP) yang paling optimal
COST ESTIMATING Berdasarkan lingkup pekerjaan dan sumber daya dihitung estimasi biaya pelaksanaan PROJECT PLAN
Diharapkan diperoleh Project Plan yang paling optimal, ditinjau dari segi waktu, mutu dan biaya
PLANNING PROCESSES
CORE Processes FACILITATING Processes
QUALITY PLANNING
COMMUNICATION PLANNING RISK IDENTIFICATION
Identifikasi Resiko Rencana Struktur Organisasi Perencanaan Pengadaan Bahan
Perencanaan mutu proyek, sesuai dengan spesifikasi dan sistem QA/QC, misalnya Project Quality Plan
Perencanaan sistem komunikasi, baik intern maupun ekstern, misalnya mekanisme pelaporan progress proyek. dsb
RISK QUANTIFICATION
Perhitungan Resiko
Statement of Work
I. II. Purpose Background A. Problem, opportunity, or directive statement B. History leading to project request C. Project goal and objectives D. Product description Scope (notice the use of your information system building blocks) A. Stakeholders B. Data C. Processes D. Locations Project Approach A. Route B. Deliverables Managerial Approach A. Team building considerations B. Manager and experience C. Training requirements D. Meeting schedules E. Reporting methods and frequency F. Conflict management G. Scope management (continued)
III.
IV. V.
VII. VIII.
IX.
PROJECT GOAL
2
PHASE
3
PHASE
PHASE
2.1
ACTIVITY
2.2
ACTIVITY
2.3
ACTIVITY
2.2.1
TASK
2.2.2
TASK
2.2.3
TASK
Activity 4: Specify Intertask Dependencies Finish-to-start (FS)The finish of one task triggers the start of another task. Start-to-start (SS)The start of one task triggers the start of another task. Finish-to-finish (FF)Two tasks must finish at the same time. Start-to-finish (SF)The start of one task signifies the finish of another task.
Scheduling Strategies
Forward scheduling establishes a project start date and then schedules forward from that date. Based on the planned duration of required tasks, their interdependencies, and the allocation of resources to complete those tasks, a projected project completion date is calculated.
Reverse scheduling establishes a project deadline and then schedules backward from that date. Essentially, tasks, their duration, interdependencies, and resources must be considered to ensure that the project can be completed by the deadline.
A Project Calendar
Resource Leveling Resource leveling is a strategy used to correct resource overallocations by some combination of delaying or splitting tasks.
There are two techniques for resource leveling: task delaying task splitting
FORMING
Supervision resources The DEADLINE A Novel About Project Management The One Minute Manager The Care and Feeding of Monkeys Stages of Team Maturity (see figure to the right)
INTERNAL PROBLEM-SOLVING STAGE Resolve interpersonal conflict Further clarify rules and goals Develop a participative climate
STORMING
GROWTH AND PRODUCTIVITY STAGE Direct team activity toward goals Provide and get feedback Share ideasgrowing cohesion Individuals feel good about each other
NORMING
EVALUATION AND CONTROL STAGE More feedback and evaluation Adherence to team norms Roles of team strengthened Strong team motivation to share goals
PERFORMING
Expectations Management
An expectations management matrix is a rule-driven tool for helping management understand the dynamics and impact of changing project parameters such as cost, schedule, scope, and quality.
PRIORITIES MEASURES OF SUCCESS Max or Min Constrain Accept
Cost
Schedule
Max or Min
Constrain
Accept
x x x
Scope and/or Quality Land a man on the moon Get him back safely
Max or Min
Constrain
Accept
Cost
x x x
Schedule
Adjusting Expectations
PRIORITIES MEASURES OF SUCCESS Cost Adjusted budget Increase budget Schedule Adjusted deadline Extend deadline Scope and/or Quality Adjusted scope Accept expanded requirements Max or Min Constrain Accept
X+
X-
X+
Figure 4.16
Changing Priorities
PRIORITIES MEASURES OF SUCCESS Max or Min Constrain Accept
Cost
x x
Schedule
Critical Path
TASK D
Duration
TASK A
TASK B
TASK C
TASK E
TASK I
3 days 0 days
2 days 0 days
2 days 0 days
TASK F
TASK G
Fri 2/16/01
2 days
Slack Time
TASK H Thu 2/15/01 1 day