Chapter 8 Scheduling
2006 John Wiley and Sons, Inc.
Overview
WBS to Schedule Process PERT Schedule Types CPM
Scheduling
A schedule is the conversion of a project action plan into an operating timetable It serves as the basis for monitoring and controlling project activity Taken together with the plan and budget, it is probably the major tool for the management of projects
Chapter 8-1
Chapter 8-7
Scheduling Terminology
Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete Event - The result of completing one or more activities. An identifiable end state occurring at a particular time. Events use no resources. Network - The combination of all activities and events define the project and the activity precedence relationships
2006 John Wiley and Sons, Inc. Chapter 8-9
Scheduling Terminology
Path - The series of connected activities (or intermediate events) between any two events in a network Critical - Activities, events, or paths which, if delayed, will delay the completion of the project. A projects critical path is understood to mean that sequence of critical activities that connect the projects start event to its finish event
2006 John Wiley and Sons, Inc. Chapter 8-10
Scheduling Terminology
An activity can be in any of these conditions:
It may have a successor(s) but no predecessor(s) starts a network It may have a predecessor(s) but no successor(s) ends a network It may have both predecessor(s) and successor(s) - in the middle of a network
Hypothetical Network
3
13 30 16 5
2
20 6
6
TE=64
m (A)
TE (B)
a
17
m
29
b
47
t(e)
1-2
2-3
2-4
6
16
12
19
24
28
3-5
4-5
13
2
16
5
19
14
5-6
5
2006 John Wiley and Sons, Inc.
a 17 6 16 13
m 29 12 19 16
b 47 24 28 19
t(e) 30 13 20 16
[(b-a)/6]2 Var
4-5 5-6
2 2
5 5
14 8
6 6
TS=67 TE=64
Z Table
Z Value
-2.0 -1.5 -1.0 -0.7 -0.5 -0.3 -0.1
Probability
0.02 0.07 0.16 0.24 0.31 0.38 0.36
Z Value
+2.0 +1.5 +1.0 +0.7 +0.5 +0.3 +0.1
Probability
0.98 0.93 0.84 0.76 0.69 0.62 0.54
Gantt Charts
The Gantt chart shows planned and actual progress for a number of tasks displayed against a horizontal time scale It is an effective and easy-to-read method of indicating the actual current status for each set of tasks compared to the planned progress for each item of the set It can be helpful in expediting, sequencing, and reallocating resources among tasks Gantt charts usually do not show technical dependencies
2006 John Wiley and Sons, Inc. Chapter 8-14
Drawing Networks
Activity-on-Arrow (AOA) networks use arrows to represent activities while nodes stand for events Activity-on-Node (AON) networks use nodes to represent activities with arrows to show precedence relationships The choice between AOA and AON representation is largely a matter of personal preference
Chapter 8-12
Hypothetical Network
3
Install software
79
80
A Application approval
X
1 A 2 C (A) 3
B
4 E
B
1 A 2 C (B) 4 B C 1 A 2 X (C)
2006 John Wiley and Sons, Inc.
X
4 E
X
1 A 2 C
3
D 5
(D)
4 B X A C ? D (E)
2006 John Wiley and Sons, Inc.
E 5
4 0
Y 5
E 15 F 10 6 G 170 7 H 35 8
C 10
D 5
(A)
(C)
Y X Z
Z is preceded by X and Y
AA
AA is preceded by X and Y
(B)
2006 John Wiley and Sons, Inc.
(D)