Академический Документы
Профессиональный Документы
Культура Документы
www.huawei.com
Learning Guide
Before studying this course, you are supposed to complete the study on
OptiX RTN 600 Product Introduction OptiX RTN 600 Networking and Protection Mechanism
Page 1
References
Digital Microwave Communications Basics OptiX RTN 600 Radio Transmission System Configuration Guide
Page 2
Objectives
Page 3
Contents
1. Preparations for the OptiX RTN 600 Commissioning
Page 4
Contents
1. Preparations for the OptiX RTN 600 Commissioning
1.1 Determining Commissioning Items 1.2 Preparing Related Documents 1.3 Preparing Related Tools
Page 5
Remarks
Testing indicators
Required Required
Optional is recommended that you test this item. loopback testTechnologies Co., Ltd. All rights reserved. Page 6 Copyright 2006 Huawei
Remarks
Optional
Required
Optional
Required
Require
Page 8
Remarks It is applicable when the 1+1 HSB/FD/SD protection is configured. It is applicable when the SNCP is configured. according to the actual
Required
Required
Required
Page 9
R2 New Slide
NE Commissioning Items
Commissioning Item Testing the XPIC Cable connection Optional/Required Remarks It is applicable when the IFX is configured.
Optional
ed
required required required It is applicable when the E3 (DS3) service is configured. It is applicable when the XPIC is configured. It is applicable when the N+1 protection is configured.
Page 10
Testing the E3DS3services Testing XPIC function Testing N+1 protection switching
The documents that are required include the engineering design documents and commissioning guide documents.
OptiX RTN 600 Radio Transmission System Network Planning Document OptiX RTN 600 Radio Transmission System Engineering Design Document
OptiX RTN 600 Radio Transmission System Commissioning Guide OptiX RTN 600 Radio Transmission System Quick Installation and Commissioning Guide
Page 11
Preparing Tools
The tools that are required include the common tools, special tools
tool
Instrument
Page 12
The hardware installation of the equipment must be complete, and it should pass the installation check.
The power supply of the equipment must be available. The service signal cables connected to other equipment must be routed well.
The laptop computer must be installed with the Web LCT, and applications should work normally.
Page 13
The hop commissioning items to be checked include the NE commissioning status as well as the weather conditions. The hop commissioning conditions are listed as follows:
between stations.
The on-site conditions and the personnel in charge of antenna commissioning must meet the requirement on the operation at a high altitude.
Page 14
Summary
Page 15
Contents
1. Preparations for the OptiX RTN 600 Commissioning
Page 16
Contents
2. NE Commissioning of the OptiX RTN 600
2.1 Powering On the Equipment 2.2 Testing Indicators 2.3 Accessing the Web LCT 2.4 Configuring the Data
Page 17
Prerequisites
The hardware installation of the equipment must be complete, and it should pass the installation check. The input power must be available.
The power switch of the input power (such as the power box of the cabinet) must be turned off.
Multi-meter Set the SYS-PWR switch on the PXC board to O. Set the ODU-PWR switch on the IF board to O. Turn on the input power switch of the cabinet.
Procedure
Page 18
testing the voltage and polarization of the input power at the access point (such as the output terminal of the power box on the cabinet) by multi-meter. The voltage should range from -38.4 V to -72 V. Set the SYS_PWR switch on the PXC board to I. If the fan is available, first check it is working normally after power on. Wait for about 20 seconds, and then observe indicators of each board installed in the IDU.
The PROG indicator on the SCC board should be first on. After it blinks and is lit green for some time, it should be off. For details on the board indicators, refer to the OptiX RTN 600 Radio Transmission System Product Description.
Note: The SYS-PWR and ODU-PWR switches on PXC and IF boards have the locking device. They need to be slightly pull out before switch them.
Page 19
Testing Indicators
Prerequisites
None.
Procedure
Press the LAMP TEST button on the SCC board, and indicators of all boards should be on. Release the LAMP TEST button, and indicators of all boards should recover to the status before the LAMP TEST button is pressed.
Page 20
Prerequisites
NM interface
Procedure
Start the laptop computer, and log in to the operating system. Run the Web LCT program. Connect the network port on the laptop computer to the ETH interface on the SCC board through the network cable. The green indicators of the ETH interface and network port should be on.
Page 21
Set the IP address information of the computer, and log in to the NE. The IP address should comply with the following conditions:
IP address: The IP address should be in the 129.9.0.0 network section and should be different from the default IP address of the NE (129.9.191.240). Subnet mask: 255.255.0.0. Default gateway: Null.
Double click the shortcut of Web LCT on the desktop. The login interface of the Web LCT is displayed. In the login interface of the Web LCT, enter the user name and corresponding password. Click Login. The default user name is admin, and the default password is T2000. If the user name and password are correct, the NE List page is displayed in the IE.
Page 22
Prerequisites
Web LCT
Before configuring the NE data, create the NE, log in and modify the ID settings of the NE according to the requirements in the Network Planning Document.
The OptiX RTN 600 can be configured in two modes, General Mode and Wizard Mode. Users can choose the proper configuration mode depending on the specific configuration scenarios. For details, refer to the OptiX RTN 600 Radio Transmission System Configuration Guide.
Page 23
Procedure
Prerequisites
The service data must be configured. The 15-minute performance monitoring of the NE must be started. The fiber connections must be normal.
Page 24
Procedure
Disable the automatic laser shutdown (ALS) function of the laser, and ensure that transmission of the laser is enabled. Query the 15-minute performance by using the Web LCT to obtain the values of the transmit and receive optical power.
Based on the queried values along with the specifications of optical modules, judge whether they are within the normal value range. If the values are beyond the normal range, adjust the optical power by increasing or decreasing the number of attenuators to ensure that the receive and transmit optical power is within the normal value range.
Perform the loopback test for the services upon the completion of the optical power test. Ensure that no bit errors occur in five minutes.
Page 25
Prerequisites
The Web LCT must be logged in to successfully and its connection to the NE must be normal.
Page 26
Procedure
Connect the board to be tested to the test instrument. Issue the loopback command and observe the instrument for five minutes. Repeat the above two steps to test each board. The service loopback for the IF board can only be implemented by testing the services of other service boards. Adopt different loopback mode depending on the actually used instrument. If the SDH analyzer is used to test the optical interface board, first use the optical power meter to test the optical power before the test and use the attenuator to ensure that the optical power is within the normal range. This can protect the instrument and the board.
Page 27
Prerequisites
The E1 port must be transferred through the DDF. The service data must be configured.
Procedure
Connect the BER tester to the first E1 port of the OptiX RTN 600 at the DDF. Set the corresponding E1 port to outloop by using the Web LCT. Observe the BER tester. The AIS alarm displayed on the BER tester should be cleared.
Page 28
Release the outloop of the E1 port by using the Web LCT. Observe the BER tester. It should report the AIS alarm. Repeat the above five steps to test other E1 ports.
Tip
Connect all E1 ports in a serial manner and set all of them to outloop by using the Web LCT. In this way, you can check whether all E1 ports are normal at the same time. If any fault occurs, you also need to locate it segmentally.
Page 29
Prerequisites
The service data must be configured and the performance monitoring of the NE must be started. The ATPC function must be disabled. Web LCT In the NE Explorer, select the ODU that requires querying the RF transmit power and query RF Transmit Power in the performance events. Browse the performance events in the window. The difference between the queried value of the RF transmit power and the preset value should be less than 0.1 dB.
Page 30
Procedure
Prerequisites
Page 31
Procedure
Confirm the current working status of active and standby PXC boards and no abnormal alarms by using the Web LCT. Perform active/standby PXC board switching by Web LCT. Query the working status of the active and standby PXC boards to check whether the switching is performed normally. Query the current and history alarms to check whether any alarm is generated during the switching process. After the test, restore the PXC board in slot 1 to the active board. Query the alarms and ensure that the cross-connect board works normally.
If you use the BER tester to monitor the services, few bit errors may occur during the switching process. The services, however, can recover immediately after the switching is complete.
Page 32
Questions
How should the E1 port be set and connected for testing the connections
of E1 cables? What method can we adopt for testing this item quickly?
Why the ATPC function is disabled when the RF transmit power is tested?
What are the two modes in data configuration? What are the differences between them?
Page 33
Summary
Page 34
Contents
1. Preparations for the OptiX RTN 600 Commissioning
Page 35
Table of Contents
3. Hop Commissioning of the OptiX RTN 600
Page 36
Prerequisites
The NE commissioning of the radio equipment at both ends of the same radio link must be complete.
During the commissioning, the weather should be suitable and there should be no rain/fog between stations.
The on-site conditions and personnel in charge of the antenna commissioning must meet the requirements of operation at a high altitude. The ATPC function is disable.
Note: If there are two antennas at each site, it needs to align the main antennas and diversity antennas at both ends respectively. First align the main antennas and then the diversity antennas. Both antennas at local site should be aligned with the main antenna at opposite end.
Page 37
R2 New Slide
Aligning the antennas is the most important activity in the HOP commissioning, and its result has a direct effect on the performance of the radio link. There are two
When you align the single-polarized antennas, you need to align the main lobe of the antenna signals by adjusting the azimuth angle and elevation angle of the
When you align the dual-polarized antennas, you need to align the main lobe of the antenna signals by adjusting the azimuth angle and elevation angle of the
antennas at both ends. You also need to adjust the feed booms of the antennas
and ensure that the Cross-Polarization Discrimination (XPD) meets the specified requirements.
Page 38
Adjust Slide
Procedure
1.
According to the designed received signal level (RSL) along with the relationship curve between the VBNC and RSL described in the user documents (shipped with the equipment) of the ODU reference documents, read the designed value of the VBNC. Align the antennas at both ends approximately by using the specific tool (telescope) or instrument (COMPASS or GPS). If the antennas at both ends are not aligned approximately, the VBNC cannot be adjusted to the designed value. Fix the antenna at the opposite end, and adjust the azimuth (elevation) of the antenna at the local end in a wide range. Use the multi-meter to observe the VBNC value of the ODU at the local end. At least three peak signals should be detected and the voltage of the peak signal in the middle should be maximum. When the VBNC reaches the maximum value, tighten the antenna. When the antenna is being tightened, keep that the VBNC is always the maximum.
Page 39
2.
3.
R2 New Slide
Step 1: Power off the vertically polarized ODUs at both ends of the radio link, power on the horizontally polarized ODUs at both ends of the radio link, and thus ensure that the antennas transmit horizontally polarized signals. Step 2: Adjust the azimuth angle and elevation angle of the antennas at both ends by referring to Aligning the Single-Polarized Antennas, and ensure that the main lobe of the horizontally polarized signals is aligned with the antenna. Step 3: Measure the RSL (P1) of the horizontally polarized signals at the local end.
Use a multimeter to measure the signal level on the RSSI port of the horizontally polarized ODU.
Calculate the RSL (P1) of the horizontally polarized received signals by referring to the curve diagram in the ODU box.
Page 41
R2 New Slide
Step 4: Adjust the feed boom at the local end, and ensure that the RSL of the vertically polarized signals reaches the lower threshold (P2).
Power on the vertically polarized ODU at the local end. Use a multimeter to measure the signal level on the RSSI port of the vertically polarized ODU. Release the holder of the feed boom a little bit, and turn the feed boom slightly until the signal level reaches the lower threshold. Calculate the RSL (P2) of the vertically polarized signals by referring to the curve diagram in the ODU box. The calculated XPD1 (XPD1 = P1 P2) should not be less than 30 dB.
Page 42
R2 New Slide
Step 5: Record the angle (D1) of the current feed boom. Step 6: Power off the horizontally polarized ODUs at both ends of the radio link, power on the vertically polarized ODUs at both ends of the radio link, and thus ensure that the antennas transmit vertically polarized signals.
Step 7: Measure the RSL (P3) of the vertically polarized signals at the local end by referring to 3.
Step 8: Power on the horizontally polarized ODU at the local end, and calculate the level (P4) of the horizontally polarized signals received at
Page 43
R2 New Slide
Step 9: Record the angle (D2) of the current feed boom. Step 10: Repeat 3 through 9 to adjust the feed boom slightly (ranging from D1 to D2), and ensure that XPD1 and XPD2 are not less than 30 dB.
Note: In the actual situation, you can align the dual-polarized antennas by measuring only the vertically polarized signals
Page 44
Prerequisites
Antenna alignment must be complete. The NE must have access to the Web LCT.
Web LCT
Precautions
Procedure
Page 45
In the Add NE page, set the following attributes of the opposite NE:
Click OK. In this case, a row of data for the newly added NE is added in the NE List page. Observe Login Status of the newly added NE. Login Status should be displayed as Logged In.
Page 46
Prerequisites
The E1 service must be available between stations and the service configuration at each station must be correctly delivered. Antenna alignment must be complete. BER tester and Web LCT At local site, connect the BER tester to the first E1 port. At remote site, loopback the first E1 port by cable. If cable loopback is unfeasible, set the software inloop for the first E1 port by Web LCT. Test the BER for 5 to 10 minutes by BER tester. No bit error should occur. Release all loopbacks. Repeat the above four steps to test other E1 ports one by one.
Page 47
Procedure
Prerequisites
None.
Check the status of the order wire at the local equipment side. The status of the order wire should meet the following requirements:
Procedure
Page 48
Pick up the order wire, and press the TALK key on the front panel of the phone. The red indicator on the upper right side of the front panel is on, accompanied by the dial tone. Dial the order wire number of the opposite equipment. Normally, the voice quality is good and the voice is clear.
The maintenance personnel at the opposite equipment side dials the order wire of the local equipment. Normally, the order wire rings and at the same time the red indicator on the upper right side of the front panel is on. Pick up the phone, and press the TALK key to talk. The red indicator on the upper right side of the phone is on. Normally, the voice quality is good
Page 49
Prerequisites
The clock tracing priority list must be configured. Web LCT Query the current clock priority table by using the Web LCT. According to the clock priority table, query whether the current clock tracing source is traced normally. If the active and standby PXC boards are configured, perform the active/standby switching. This operation can check whether the current clock source can be traced normally after the switching. After the test is complete, restore the PXC boards in slot1 as active board.
Procedure
Page 50
Prerequisites
Note: The following procedure considers the E1 service between stations as an example. If no E1 service is configured between stations, perform the test through the configured WS service (only applicable in the SDH radio).
Page 51
Procedure
View the working status of the protection group by using the Web LCT. The Active Board of Device and Active Board of Channel should be the active IF board.
Set the transmission status of the main ODU to mute by using the Web LCT or power off the main ODU. This can trigger the IF 1+1 switching. View the working status of the protection group after the switching by using the Web LCT. The Active Board of Device and Active Board of Channel should be the standby IF board. The HSB_INDI or HSM_INDI alarm should be reported.
Page 52
In the 1+1 HSB protection or 1+1 SD protection, service should recover after a transient interruption. In the 1+1 FD protection, service just has some bit errors without interruption.
After switching is complete, test the BER for 5 to 10 minutes. No bit errors should occur. Set the transmission status of the main ODU to unmute by using the Web LCT or powering on the main ODU.
If the protection mode is set to Revertive mode, test the BER again by using the BER tester. When the restore time arrives, the result should indicate that the service has recovered after a transient interruption. WTR Time is set to 600s by default. Test the BER according to the requirements of the actual configuration.
Page 53
Prerequisites
Precautions
If the 24-hour BER cannot be tested for each hop on the link because of the restrictions of the actual situation, choose the E1 service of the first node and terminal node of each link to perform this test. This operation ensures that the test path covers all the radio links. The following test procedure considers the E1 service between stations as an example. If no E1 service is configured between stations, perform the test through the configured WS service (only applicable in the SDH radio).
Page 54
Procedure
At local site, extract several typical E1 services, and perform the hardware inloop for the E1 ports. If the hardware inloop is unfeasible, perform the software inloop for the E1 ports by using the Web LCT. At remote site, connect the E1 services in a serial manner at the DDF, and access them to the BER tester. Test the 24-hour BER by using the BER tester.
Record the test result. The result should indicate that no bit errors Copyrightoccur. 2006 Huawei Technologies Co., Ltd. All rights reserved.
Page 55
Postrequisites
If bit errors occur in the first 24-hour BER test, remove the fault.
Perform another 24-hour BER test until the test is passed.
If bit errors occur in the test for a serial connection, locate the fault by
Page 56
R2 New Slide
Prerequisites
The equipment must be configured with N+1 protection. Aligning the antenna must be complete.
BER tester
Web LCT
Precautions
The following test procedure takes the E1 services between stations as an example. If the E1 service is not configured between stations, perform the test through other configured services such as WS services.
Page 57
R2 New Slide
Procedure
Connect the BER tester to an E1 port of the equipment on the local side. On the equipment on the opposite side, perform hardware inloop over the E1 port. If the hardware inloop fails, perform software inloop over the E1 port by using the Web LCT. Test the BER by using the BER tester. There should be no bit errors.
Check the working status of the board by using the Web LCT.
Select an NE from the Object Tree in the NE Explorer. Choose Configuration > Link Configuration from the Function Tree. Select the N+1 Protection tab page, and click Query. The Switching Status of the working unit and the protection unit should be Normal.
Power off the ODU through the power switch on the active IF board that transmits E1 services data.
Page 58
R2 New Slide
Check the BER test result. The service should recover immediately after a transient interruption.
After the switching is complete, perform BER test for 5 to 10 minutes. There should be no bit errors.
Power on the ODU through the switch on the active IF board. Test the BER again by using the BER tester. When the WTR time expires, the service should recover immediately after a transient interruption. WTR Time is set to 600s by default. Test the BER depending on the actual configuration. Release the loopback set in 2. Refer to 1 through 10 to test the N+1 protection switching of the equipment on the opposite side.
Page 59
Questions
How long does it take to test the E1 / WS / E3/ DS3 service respectively by using the
BER tester?
How can we ensure that the switching is performed after the SNCP switching is complete?
How should we handle bit errors occurring in the 24-hour BER test?
Page 60
Summary
Aligning the antenna Testing the ECC Testing the E1 service Testing the order wire Testing the clock tracing Testing the IF 1+1 switching Testing the 24-hour BER Testing the N+1 protection switching
Page 61
Thank You
www.huawei.com