Вы находитесь на странице: 1из 30

HEARTY WELCOME APUFIDC.

Quality Control/ Quality Assurance In Construction

3rd PQA UIDSSMT Agencies


Selected through Tendering Process. Agencies appointed M/s NCPE Hyderabad Aarvee Associates. M/s DHV Consultants.

APPROVALS
G.O 487 MA dated23.10.2003 ---CCF G.O.Rt No.512 dated1.4.08---- UIDSSMT G.O.Rt. No.639 dated 25.4.09- UIDSSMT.

Quality Control wings


Departmental QC one division for two circles. Conducting the specified tests in accordance with the sampling criteria at all stages of process to ensure the required quality parameters.

Quality Assurance (QA)


Managerial methods designed to plan, monitor and control to assure the Quality of all the processes such that the end product satisfies the desired properties.

carry out random tests during preconstruction, construction and post construction stages.

Quality Assurance (QA)


Eliminates poor services and induces greater professionalism in the process, instills public confidence and acceptance. Avoids inefficiency and litigation.

Eliminates the interferiences.

Quality Management benifits


Quality of the design process Quality of the construction process Quality of the products Quality of maintenance.

Frequency of Reporting
QA Reports to 1.Executive Engineer. 2.Supertending Engineer. 3.SLNA. At Twice in a month Satisfactory. Immediate reporting Adverse reports. Action taken reports monitored by SLNA

Quality Standards -Roads


IRC: 58 Guidelines for the Design of Plain Jointed Rigid Pavements for Highways IRC 15:2002 Code of practice for construction of rigid pavements IRC SP: 62 Guidelines for the Design and Construction of CC Pavements for Rural Roads

Frequency of sampling- Concrete


Test results shall comply with IS: 456-2000 1-5 cum 6-15 cum 16-30 cum 31-50 cum 51 and above 1 sample 2 samples 3 samples 4 samples 4 +1 addl. sample for addl. 50 m3 or part

At least one sample shall be taken from each shift Core tests to be conducted as per IS: 456 for the purpose of detailed information.

Sampling -continue
SWG..I S 651-2007 PSCI S 784.2001 BWRC I S 15155-2002 PVC.I S 4985-2000 GRP.I S 12709-1994 Di..I S 8329-2000 HDPEI S4984-1995

Tests-Building Materials
Bricks---IS 1077-1992.

Cement bricks..IS 2185-1979. Aggregates---------I S 2386- Part 1to7

Quality Control Tests

Test
(i) (ii) (iii) (iv) (v) Aggregate Impact Value Grading of aggregate and screenings Flakiness Index Atterberg limits of binding material, if required Water absorption

Frequency
1 test per 250 cum or per day 2 tests per 250 cum or per day 1 test per 250 cum or per day 1 test per 50 cum or per day 1 test per source (three representative specimens for each source) Regularly

(vi)

Thickness

Quality Control Tests and their frequency


Test
(i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix) Quality of Binder Aggregate Impact Value (or Los Angeles Abrasion Value) Flakiness and Elongation Index Stripping value Water absorption Grading Soundess (Magnesium and Sodium Sulphate) Temperature of binder at application Rate of spread of materials (binder and stone chips)

Frequency
1 test per lot of 10 tonnes 1 test per 250 cum 1 test per 250 cum or per day 1 test per source (three representative specimens for each source) 1 test per source (three representative specimens for each source) 1 test per 100 cum or per day 1 test per source Regular close intervals 1 test per 1000 sq m or per day

Quality Control Tests and their frequency


Test
(i) Quality of Binder

Frequency
1 test per lot of 10 tonnes

(ii)
(iii) (iv) (v) (vi) (vii)

Aggregate Impact Value (or Los Angeles Abrasion Value)


Flakiness and Elongation Index Stripping value Water absorption Grading Soundess (Magnesium and Sodium Sulphate)

1 test per 250 cum or per day


1 test per 250 cum 1 test per source (three representative specimens for each source) 1 test per source (three representative specimens for each source) 1 test per 100 cum or per day 1 test per source

(viii)
(ix) (x)

Temperature of binder at application


Binder content Thickness of BM Layer

Regular close intervals


2 tests per day Regularly

(xi)

Density of compacted layer

1 test per 1000 sq.m. area or per day

Frequency of visits-concrete
Based on the type and importance of the work. 1 No---material pre construction 1no- Reinforcement for each component 1no-For concreting of each component. 1no- Columns at each staging. 2nospost construction.

Frequency of visits-pipelines
Material testing ------Factory Laying &Joiting. 1no---- 1km upto 200 mm dia 1no----.50Km upto 500 mm dia 1no----.25 Km beyond 500mm dia. Hydraulic test; 1no on Average 5 kms

Testing - Cores
In case of doubt regarding the

comp.strength tests on cores and/or load test shall be carried out. Core tests: the ave. equivalent cube
strength of the cores is equal to at least 85% of the cube strength of the grade of concrete specified for the corresponding age and no individual core has strength less than 75%

Acceptance criteria- CC Roads


The Test results of the sample variation is more than + 15% of the average,the test results of the sample are invalid. The mean strength results complies with the appropriate limits in col.2 of table 11 of IS:4562000 Any individual test result complies with the appropriate limits in col.3 of Table 11 of IS:4562000

Payment in case of deficiency in thickness CC roads


Up to 5mm 6-10mm 11-15mm More than 15mm 100% of rate 87% of rate 81% of rate Rejection

A days work is considered for thickness. If average deficiency is more than 15mm identified by cores, such slabs shall be Removed by contractor.

Penalties can be levied as per agreement conditions for defective works

Acceptance/Recovery-CC slab
Mastic pads not used/defective material used- Deduction of twice/equal to cost of mastic pads . Joint sealing not done.Deduction of twice/equal to cost of joint sealant. Failure of CC cubes- payment based on core tests at the cost of contractor @2 cores/150cum of Progressive surface damage-Withholding payment until defects liability period.

Recovery criteria-CC pavements


Metal exposed- Affected area of CC road to be rejected Water stagnation- Payment to be made after rectification. Improper curing- deduction of cost of pavement for the affected area and payment based on core tests at the cost of contractor.

Acceptance criteria-CC (1:4:8)


Deficient thickness up to 10% of ave. Proportionate recovery of affected area Deficient thickness above 10%-Proportionate recovery of twice the cost of affected area Improper curing- Deduction of twice the curing charges and payment based on core tests at the cost of contractor. Improper compaction-Payment based on cube tests

Acceptance criteria-CC lean concrete


Oversize metal upto 10%- No recovery Oversize metal 10% to 20%- recovery at 25% of difference in basic rate of metal and next higher size metal

Oversize above 20%- Rejection

Acceptance criteria-WBM roads


Verify for over size Verify density of metal in an area of 0.50 m x 0.50 m for each layer In respect of thickness and less quantity in gravel and WBM layers, a maximum tolerance of 20% may be allowed In respect of recoveries upto 10%, estimate cost is to be recovered From 11 to 20%, 1 times estimate cost is to be recovered

Acceptance criteria-WBM roads-Contd.


Over size metal upto 10% - no reecovery Over size metal 10%to20% - recovery at 25% of difference in basic cost of metal and the next higher size metal Over size of metal between 30% to 40% - Rate of next higher size metal shall be allowed Over size metal above 40% - Rejection of metal

Acceptance criteria-Bituminous layers


A maximum of 10% variation may be allowed in respect of less thickness and less quantity Deficient thickness upto 10%-Estimate cost is to be recovered Deficient thickness above 10%- Rejection of the layer Bitumen content deficient upto 0.30%by weight of the total mix- Recovery of cost of bitumen for reduced quantity Bitumen content deficient by more than 0.30%Rejection of the work.

Thanking You Project Manager APUFIDC.

Вам также может понравиться