Вы находитесь на странице: 1из 114

Power Sector Western Region Technology Day

11th May 2009

Power Sector Western Region TECHNOLOGICAL TOOLS

Power Sector Western Region


Use of Electrical Torque wrench for Tightening
Boiler Structure Bolts At 1 x 500 MW Khaperkheda

Cycle time reduction in tightening boiler structure bolts


Background
At boiler erection site thousands of BOLTED JOINTS are to be tightened MANUALLY using DE Spanners for snug tightening & Torque tightening by trip torque type long handle torque spanner. The process of bolting arrangement consumes enormous time for achieving desired results, including uniform tightening & ensuring a designed torque value. This process was identified for taking up Improvement project because of the following being repetitive in nature

time consuming
labour intensive having substantial amount of preparatory work to be done before the starting actual process (set up time)

high level of risk involved (some locations for actual work place are above 80 meter above ground level & are to be performed on temporarily erected scaffoldings
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

Cycle time reduction in tightening boiler structure bolts


Objective
Reduction in time taken for complete bolting arrangement necessary for a 500 MW Boiler erection (at Khaperkheda site about 40, 000 no. M24 Bolts of lengths 70 160 mm are used) Ensuring designed tightness of bolting arrangement without further need of cross checking by Quality representative Safer working conditions for Operator

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

Cycle time reduction in tightening boiler structure bolts


Evaluation of alternatives
1. Pneumatic torque wrench
Benefits
Available with leading hand tool manufacturers like Bosch, Ingersoll Rand & others. Widely used in manufacturing plants (automotive assembly lines) where high turnover per day is the hour of need (but here the Operator has a fixed place & jobs move to his operating area one after another). These wrenches are comparatively lighter.

Drawbacks for us
Difficulties in ensuring dry air to the wrench in all weather conditions Maintaining desired air pressure at a long distance through a compressor

Requirement of supports since length of air pipes may extend up to 100 meters
Thus making the whole arrangement very clumsy & big.
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

Cycle time reduction in tightening boiler structure bolts


Evaluation of alternatives
2. Hydraulic torque wrench Benefits
Available with leading hand tool manufacturers Widely used in manufacturing plants

Drawbacks for us
Need sophisticated hydraulic equipment (difficult to maintain) Require very good quality pressure hoses to feed optimum liquid pressure to the wrench limiting factors

Practically impossible to provide such facilities at sites

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

Cycle time reduction in tightening boiler structure bolts


Evaluation of alternatives
3. Electrically operated torque wrench Benefits
Such wrenches are popular in assembly lines especially where job sizes are bigger & operator has to move around the job Available with leading hand tool manufacturers

Electrical cables maneuverable

are

much

smaller,

lighter

&

easily

Operate at 1 phase ac supply abundantly available at all areas of sites

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

Cycle time reduction in tightening boiler structure bolts


Electrically operated torque wrench (contd..)
Results of Field Trial
M/s Tristar Industrial Tools Pvt limited was a source located for making a demo at Khaperkheda Trial was successfully done on 10th April 2009 at a height of about 10 meters on Column number 19. Time taken to fully tighten bolted joint by ETW was about 15 seconds as against 3 to 4 minutes by a handle type Trip Torque Wrench Substantial saving in operation time for the activity Saving in manual effort by Operator Positive assurance of Quality of bolted joint.
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

Electric wrench for tightening boiler structure bolts

Technische Daten DEA Technical data DEA

PLARAD GERMANY Make


Technische Daten DEA Technical data DEA

Our selection Type DEA 12 TLX Torque 200 1220 NM

Weight

6,8 kg

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

10

Electric wrench tightening of boiler structure bolts

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

11

Electric wrench tightening of boiler structure bolts

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

12

Cycle time reduction in tightening boiler structure bolts


Expected Benefits
Tangible
Saving in Time - On average saving of about 3 minutes per bolt Saving in manpower cost No need for Quality representative to ensure desired objective of proper tightness Additional helper to hold spanner and a trip torque wrench, not required.

Intangible
Safety of Operating Personnel (Operators & others assisting him) from any Accidental fall due to Slipping Slipping / Falling of the job from temporary scaffolding Better safety of personnel on ground from falling of long torque wrench etc.
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

13

Power Sector Western Region

Measurement of Face Run- out of IP & LP Rotors by improvised technique at site

Measurement of Face Run- out of IP & LP Rotors


Normal Practice
Normal practice of measurement of face run-outs of IP & LP Turbine Rotors is
To place them on saddle supports and rotate them (There is only an arc of contact between the saddle and the rotor).
A pin is made and inserted in one of the coupling holes. A wire rope is wound around the rotor with the pin at one end and the crane hook of the EOT at the other. Lifting action of the crane hook causes rotation of the rotor. To aid in rotation of the rotor, copper sheets are placed in between the saddle and the rotor and, grease is smeared to reduce friction during rotation.
Contd
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

15

Measurement of Face Run- out of IP & LP Rotors


Normal Practice (Contd..)
The normal method has few problems associated with it
1. It is not possible to restrict axial movement of the rotor in order to avoid overshooting the range of the dial gauge.

2. Area of contact being very small, it requires extreme care and control while operating the EOT, lest it should cause an irreparable accident and lead to loss to both men and material.
3. It has often been noticed that there is quite an error between the measurement made at shop and those made at site leading to avoidable loss of time in correspondence, summoning experts from MUs, etc. 4. It gives the feeling of using a very primitive and un-reliable method of measurement. 5. Overall, it is never like measuring the run-outs by anchoring the rotor on a lathe to take the measurements and thats exactly the cause of the error.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

16

Measurement of Face Run- out of IP & LP Rotors


Suggested New Method
A simple device is made at site using the following material Shaft of 40mm x 1000mm long Ball Bearings with Plummer block for above shaft Supports to anchor the Plummer blocks Cross arm 1 no. 2 nos. 2 nos. 1 no.

Dial Gauges for mounting to X-arm

2 nos.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

17

Measurement of Face Run- out of IP & LP Rotors


Fixture developed and used
Brg with Plummer Block

Dia 40 Shaft

Cross Arm

Dial Pointers

External Support for anchoring the Plummer Block

Shaft Support provided by Unit

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

18

Measurement of Face Run- out of IP & LP Rotors


Advantages
User friendly and costs only Rs.5000/- to make. Does not require too much of a precision in machining the shaft. Does away with repeated rotation of the rotor for every reading. Reduces the risk of the rotor toppling during rotation by EOT crane.

Compares well with the values attained at works on a lathe.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

19

Stator lifting by Strand Jack Method at 1x250MW Unit#8 TATA Trombay

This was the 1st time the Generator Stator has been lifted by Strand Jack Method in PS-WR. Also, this is the 1st for 250MW Stators in the whole of BHEL. Picture shows Stator lifted off the Blocks.

Stator lifting by Strand Jack Method at 1x250MW Unit#8 TATA Trombay.Contd

Stator lifting in progress

Stator lifting by Strand Jack Method at 1x250MW Unit#8 TATA Trombay.Contd

Stator lifted and being moved inside the A-Row of TG Building

Stator lifting by Strand Jack Method at 1x250MW Unit#8 TATA Trombay.Contd

Stator lifted above the bottom of TG Deck and ready to be moved inside for placement.

Stator lifting by Strand Jack Method at 1x250MW Unit#8 TATA Trombay.Contd

Picture shows the Strand Jack Hydraulic Control System

Stator lifting by Strand Jack Method at 1x250MW Unit#8 TATA Trombay.Contd

Picture shows stator in position The entire operation was completed in 4 hrs from the start.

Power Sector Western Region

PORTABLE INDUCTION HEATING MACHINE

INDUCTION HEATING MACHINE


Conventionally, we at BHEL Power Sector Sites have been using the Induction Heating Machines of EDN Bangalore make. There are certain disadvantages of using this equipment listed below:
1. Too bulky and comes in two parts one the Induction Heating Equipment proper and the other, the operators panel. Weighs a few tonnes. 2. Due to its bulk, moving the machine to different areas of work is an arduous task. Each shift of the machine is a 1 days activity. 3. Often, it has been seen that when the machine is moved from one location to the other is has not been in use for a few months, the next restart is faced with quite a few problems. The reason is not known. 4. Getting spares on time for the equipment is a big issue. This results in machines with minor repairs and requiring spares quarantined. 5. Overall the machine is not user-friendly

6. Costs around Rs. 75 Lakhs per machine

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

27

Induction Heating Machine -.Contd

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

28

Induction Heating Machine -.Contd


Alternatively, there are machines available in the market and being used by our competitors that is a vast improvement on the EDN Make machine and has the following advantages:
1. Very small and easily portable, thus rendering easy movement of the machines to various locations without loss of vital erection cycle time. Requires only a 2-3 hrs for shifting and re-connecting. The entire machine is as compact as welding transformer and is single modular. Weighs approx. 105Kgs. 2. The connections are very simple and does not need expertise. 3. Though imported, has a presence in the Indian market for the last 3 years and has been used to weld pipes of 94mm thick at Sipat. The machine can be used to thicknesses in excess of 100mm pipes as well. The size of MS Pipe for the proposed 660MW Unit with Full Flow is 660 x 102mm. 4. Costs only Rs.30 Lakhs. For every one machine of EDN Make, one can two of this kind.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

29

Induction Heating Machine -.Contd

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

30

Induction Heating Machine -.Contd


660 MW
System MS - Half Flow MS Full Flow HP Bypass U/S HRH Half Flow HRH Full Flow Material P91 P91 P91 P91 P91 Size OD 508 x 80 OD 660 x 102 OD 355.6 x 52 OD 711 x 40 OD 864x48 Material P91 P91 P91 P91 P91

800 MW
Size ID 370 x 66 ID 480 x 90 OD 355.6 x 54 OD 813 x 49 OD 1016 x 58

LP Bypass U/S & D/S

P91

OD 711 x 40 / OD 1219 x10 (SA691 2 Cr)

P91

OD 864 x 50 / OD 965 x 35

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

31

Power Sector Western Region


Induction Heating for Opening & Tightening Casing fasteners of Steam Turbine

Induction Heating for opening & tightening Casing of Steam Turbine

Introduction
Casing of steam turbines are tightened together by using threaded fasteners of M48 to M140 size . These fasteners referred commonly as studs and cap nuts have to be tightened firmly to withstand the high internal pressure and temperature. During the tightening process, specified value of elongation has to be achieved so that during working at high temperature, the nuts will not slacken . A recommended practice for tightening these fasteners is heat tightening.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

33

Induction Heating for opening & tightening Casing of Steam Turbine


Commonly used devices for heating the fasteners
Electric heaters - which include heater elements, cables, power source /transformer of high capacity etc. Gas heaters. This is relatively simpler method which uses the specially fabricated bolt heating devices - Gas Torches with special nozzles, and oxy-acetylene cylinders , compressed air supply etc. Main disadvantages of the above two methods Long time taken for the operation Due to the slower rate of heating, effectiveness of these methods is less and some other problems such as seizure of the threads also occur quite frequently. Apart from this, the arrangements required are also complex and time wasted in maintenance / repairs of the equipment in case of defects is quite considerable.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

34

Induction Heating for opening & tightening Casing of Steam Turbine


Induction heating method for threaded fasteners Induction heating method is being used in other site applications such as preheating of joints for special welding of alloy steel pipe lines in thermal power stations. This method is very quick and effective means for heating. By using some modified gadgets, it was found suitable for loosening and tightening of the big size threaded fasteners of steam turbines, valves etc. SAS Nagpur decided to use the induction heating method for loosening and tightening of threaded fasteners. This method has resulted in saving valuable time for dismantling and assembly of steam turbines during overhauls. The method is simple and highly effective. With the use of induction heating method, the problem of seizure of threads necessitating cutting and gouging of the nuts and studs, in LMW design, has been minimized.
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

35

Induction Heating for opening & tightening Casing of Steam Turbine


Comparison of time required for bolt opening
210 MW /500 MW KWU HP inner casing IP Outer casing IP inner casing Electric/ Gas Heating 6 hrs 10 hrs 14 hrs Induction Heating 3 hrs 7 hrs 8 hrs

Time saved for overhauling is 3 days .


For a 210 MW set this translates into a gain of 5.04 million units perday i.e approx. Rs. 2 crore per day For 500 mw set, 12 million units per day i.e.approx. Rs.4.8 crore perday

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

36

LASER ALIGNMENT KIT


OBJECTIVE
To carry out various alignment works in Turbine erection With high precision. At a reduced cycle time.

WORKS CARRIED OUT


Catenary of pedestals Centering of bores of Diaphragms, Pedestals, Shaft Seals etc. Alignment of Rotors.

CATENARY OF PEDESTALS
Accuracy of 10 Microns achievable. Source equipments to be placed at extreme pedestals. Mobile equipment placed in intermediate pedestals. Laser is passed thro mobile equipment and adjustments carried out as per requirement.
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

37

LASER ALIGNMENT KIT


Centering of Bores of diaphragms,pedestals,shaft seals etc Source Laser device fixed in one extreme end pedestal Receiver end device fixed in other extreme pedestal. Special fixtures used for centering of intermediate pedestals. Online adjustment possible.

Alignment of Rotors
Can cater to Coupling Dia from 100 mm to 1200 mm. Alignment Device fixed on couplings to be aligned Total misalignment is indicated by just 60 degree rotation of Rotors. Misalignment values as well as correction required indicated in display.

Salient Advantages
Saving in Cycle time. Accuracy of Measurement. Indication of correction factors.
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

38

LASER ALIGNMENT KIT


CONCLUSION
The Laser Alignment kit is a useful equipment that is State of the Art in Technology and can be used very effectively in Turbine activities at high precision and reduced cycle time, as has been proved in Kudankulam site. Hence extensive use of this equipment has to be practiced.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

39

ORBITAL WELDING
Purpose To provide leak proof joint between Tube to tube sheet in Condenser in addition to Forced expansion
Process GTAW without filler wire addition SIGNIFICANT ASPECTS

Material-Titanium
Large Qty of welding Welding in position & at site Material supply by Russians TITANIUM TUBES Grade Tube Sheet Material B 265 Gr 1 CLAD
05/05/2012

: ASTM B 338 Gr2 : 35 + 5 mm thick : ASTM A516Gr 70 + ASTM

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

40

ORBITAL WELDING
Why Titanium is used?
Provides excellent resistance to general and localized attack under most oxidizing, neutral and inhibited reducing conditions in aqueous environments.

Corrosion Resistance due to stable, protective strongly adherent oxide film which forms instantly when a fresh surface is exposed to air moisture.
This film is transparent and not deducted by visual means.

Titanium resist corrosion by sea water to temperature as high as 260 0 C.


Even exposed to sea water for many years at a depth of over a mile shows no measurable corrosion.

Provides over 25 years of trouble free sea water service for chemical refinery de-salination and nuclear industries
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

41

ORBITAL WELDING
Has the ability to resist erosion by high velocity sea water
The presence of abrasive particles such as sand has only a small effect on the corrosion resistance of Titanium Production began in the late 1950s

Most widely used titanium is commercial pure (99.5 % Ti)


Manufacturing Process Ingot slab Hot strip cold strip Slitting Forming TIG Welding Stress relieving Eddy Current & Ultrasonic testing

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

42

ORBITAL WELDING Physical Testing


Tensile, flare, flattening & reverse flattening

Visual Inspection
Cleanliness, ID, OD, Surface condition, end condition and marking.

Tube to tube sheet joining


Contact Rolling (0 to 5 % wall thinning for a length of 10 mm)

Orbital Welding For highly reliable leak tightness Forced Rolling (8 to 10 % wall thinning for a length of 25mm)

PROCESS FLOW CHART Sh 1 of 3 Front / Rear end tube sheet cleaning wire brush mounted in portable drilling machine followed by acetone

Visual inspection
Titanium tube insertion Initial cleaning before contact rolling Initial contact rolling up to 10mm

PROCESS FLOW CHART CONTD

Sh 2 of 3

End facing of tube & tube sheet up to 0.05 mm Welding

Excess length trimming in the rear side


Visual inspection Rectification of repair work Final expansion 8 to 10 % by lubricating SAE 40 oil

PROCESS FLOW CHART CONTD

Sh 3 of 3

Final cleaning by acetone


Dye Penetrant testing Tube tightness test by MAUS Gun G-150

TUBE SPECIFICATION

TUBE INSERTION AT KODAMKULAM

PROGRAMABLE ORBITAL WELDING MACHINES

FRONIUS MODEL - FPA 2000 (AUSTRIAN MAKE)

AFTER TUBE INSERTION

TUBE SHEET PROTECTION

Welding parameters for FRONIUS MODEL - FPA 2000


Process : GTAW (Automatic ) No of weld passes Argon Gas flow rate Pre Gas time Post Gas time Pre Fusion current Pre fusion current time 1

4 to 6 ltr /min
T10 T11 I21 T21 30 Sec 30 Sec 90A 0.1Sec

Pulse current
Time of pulse current

I22
T22

90A
100msec

USE OF HYDRAULIC OPERATED TORQUE CONTROLLED BOLT TIGHTNING KIT

OBJECTIVE
To adopt a safe State of the Art methodology in bolt stretching of coupling bolts of TG Couplings.

GENERAL COUPLINNGS IN TG
HP Tubine to IP Turbine IP Turbine to LP Turbine LP Turbine to Generator Shaft

REQUIREMENT
The coupling bolts which are like pins, having a clearance of 0.03mm diametrically, have to be stretched up to 0.55 mm ,depending on the bolt dimensions to ensure uniform tightening .

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

53

USE OF HYDRAULIC OPERATED TORQUE CONTROLLED BOLT TIGHTNING KIT

Prevalent practice
Nut of the Coupling bolt is tightened by a box spanner Leverage applied on end of the spanner by EOT crane through slings. Differential expansion monitored by Dial Gauge positioned at bolt ends.

Sources of Error
Dial gauge at the nut end has to be fitted with a long extension rod,which may lead to error in reading. Disturbances in the nut also can lead to erratic readings.

Safety element
The whole stretching operation dependent on skill of the Fitter and EOT Crane operator Fine movements in EOT Crane not possible Danger of slipping/shearing always present.
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

54

USE OF HYDRAULIC OPERATED TORQUE CONTROLLED BOLT TIGHTNING KIT

RECOMMENDATION
Hydraulically operated Torque controlled Bolt tightening kit can be used. Manufacturing Unit to specify Torque tightening values of individual couplings.

ADVANTAGES
No error in reading. Uniformity in bolt stretching Safe for the working personnel Safe for the equipment

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

55

Power Sector Western Region IMPROVED PROCESSES

ALL-VOLATILE & OXYGENATED TREATMENT AVT : The basic idea of AVT is to minimize corrosion & erosion corrosion in the low temperature region by using deaerated high purity water with elevated PH. The actual PH range depend on cycle metallurgy In absence of Oxygen, the primary reaction of iron dissolution is inhibited by increasing PH. The solubility of ferrous hydrazine rises with increase in temperature and then decreases with steep drop to the solubility of magnetite between 200 250 0C. This results in undesirable magnetite deposit in this temperature range.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

57

ALL-VOLATILE & OXYGENATED TREATMENT To maintain the solubility of ferrous hydroxide in feed water below or equal to that of magnetite at 250 0C and to exclude the possibility of over saturation, a minimum PH of 9.6 should be maintained. A PH of 10 would be even better. Hydrazine acts both as a O2 scavenger & corrosion ` inhibitor by formation of ferrous oxide hydrate. OXYGENATED TREATMENT : This process uses oxygenated high purity water to minimize corrosion & erosion corrosion in the feed water train. Oxygen, Hydrazine peroxide, air are used as oxidants

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

58

ALL-VOLATILE & OXYGENATED TREATMENT Oxygen level should be 30-50 ppb for drum units and 30150 ppb for Once Through Units. Ph level shall be 9-9.6 at Drum units and 8-8.5 for Once Through Units In oxygenated system, p rotective layer consists of `Magnetite(FE O ) and Hematite(FE O ) layers 3 4 2 3 For temperature ranges upto 250 0C the addition of oxygen allows the formation of oxide protective layer which have a very low corrosion product release rate in the following water

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

59

ALL-VOLATILE & OXYGENATED TREATMENT


AL L VOLATILE TREATMENT (AVT)
Ferrous or mixed feedwater train Cation conductivity 0.2-0.4 S/cm pH 8.8 9.6 (Dependent on feedwater metallurgy) Fe 10ppb O2 <5ppb Boiler HP HP Heaters Heaters BFP BFP DA N2H4 ( >3x02) NH3 ( 0. 15-2 . 3 ppm) CP CEP Condenser

LP Heaters

Fe <2 ppb

O2 ( >30 ppb )

O2 ( >30 ppb ) NH3 ( 20 -70 ppb )

OXYGENATED TREATMENT (OT) All ferrous feedwater train Cation conductivity < 0. 15 S /cm pH 8.0 8.5
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

60

LP BYPASS SYSTEM
LP BYPASS SYSTEM
MODIFICATION CARRIED OUT IN OLD LPBP SYSTEM In case of Turbine trip, direct command will be issued to LP Bypass valves for opening upto 45% for 3 secs. It is expected that within this 3 secs., the spray valves will open and the spray water pressure will be achieved. However, if the spray water pressure has not reached a value of 5 kg/cm2 within 3.5 secs., or the condenser wall temperature has become more than 90 0C, the LP Bypass trip command will be issued

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

61

LP BYPASS SYSTEM
The sensing of pressure is done by installation of additional pressure transmitters at the downstream of spray water valves
The modification was implemented first in Vindhyachal U#10 and two occasions since the modification, the turbine has tripped and LP Bypass valves opened within 5 secs thereby saving the boiler trip

LBPB SYSTEM FOR NEW 250 MW SETS


To address this issue, now BHEL, Hwr has gone for a new High Pressure LP Bypass system which has much better response time. Such system have been supplied at 1 x 250 MW Parli, 1 x 250 MW Paras, 4 x 250 MW JPL and 2 x 250 MW Bhilai sites.
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

62

LP BYPASS SYSTEM
The logic provided for the operation of the LB Bypass valves are similar to that of the older low pressure LPBP valves. However, the following are the new features of High Pressure LPBP valves The LPBP valves on sensing increase HRH Pressure, automatically opens without looking for adequate water pressure For the water injection spray control valves, two curves have been implemented, one for control and the other for protection based on down stream pressure of LPBP valves.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

63

LP BYPASS SYSTEM
If the actual water injection flow is less than flow corresponding the protection flow, then the LPBP valves closes on water injection flow protection.
The following problems have been noticed in the new system As per the water injection curve, a continuous water flow is required to the system which is unnecessary and wasteful. The spray water flow element and flow transmitter is showing 0 reading upto 50% of spray control valve opening. The problem has been taken up with BHEL, Haridwar
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

64

LP BYPASS SYSTEM
Conclusions : The new High Pressure system is working satisfactorily and therefore, the boiler tripping due to reheater protection in the new system has been avoided in the recently commissioned units. By implementing the modification in the old units as done at NTPC Vindhyachal U#9, 10, the problem of the old units can also be resolved.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

65

Power Sector Western Region BEST PRACTICES

Best Practices, TSX PSWR


CARD BOARD BLASTING OF LUB OIL AND CONTROL OIL LINES OF STEAM TURBINES
GENERAL PRACTICE Only mechanical cleaning is done before start of oil flushing for lub oil and control oil system of steam turbines. BEST PRACTICE Exhaustive card board blasting along with mechanical cleaning is carried out for all the control and lub oil system before start of oil flushing. This practice is being followed in almost all the sites now. ADVANTAGES Effective cleaning and time reduction.
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

67

Best Practices, TSX PSWR


USE OF PORTABLE CENTRIFUGE DURING LUB OIL FLUSHING OF ROTARY MACHINES
GENERAL PRACTICE
Generally oil flushing were carried out at ambient temperature without any centrifuging arrangement for rotary machines such as BFP, ID Fans, FD Fans and Mills.

BEST PRACTICE
Oil flushing is carried out with portable oil centrifuge having inbuilt heating arrangement . ADVANTAGES Effective cleaning and time cycle reduction.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

68

Best Practices, TSX PSWR


CHEMICAL CLEANING OF PRE BOILER SYSTEM WITH CEP
GENERAL PRACTICE Carried out by using temporary pumps, tanks and piping along with boiler acid cleaning setup BEST PRACTICE Existing CEP and Hotwell are used for the purpose of circulation in the entire system ADVANTAGE Effective cleaning of the entire system with minimum number of temporary loops Cost and time cycle reduction
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

69

Best Practices, TSX PSWR


USE OF DEAERATOR AS MIXING TANK FOR PREBOILER FLUSHING
GENERAL PRACTICE
Mixing tanks and associated pipings are arranged for carrying out the pre boiler flushing activities.

BEST PRACTICE
For industrial sets, Deaerator itself is used as mixing tank for carrying out chemical cleaning of pre-Boiler system. This results in cost and time cycle reduction.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

70

Best Practices, TSX PSWR


CHEMICAL CLEANING OF BOILER (WW, SH) AND MS LINES IN INDUSTRIAL PROJECTS
GENERAL PRACTICE Stages are : Alkali boilout, Acid cleaning and passivation BEST PRACTICE Alkali flushing, Citric acid cleaning, passivation of the entire system ADVANTAGE Chemical cleaning activities can be completed even before Boiler light up Since both SH and MS lines are acid cleaned & steam blowing cycle is considerably reduced Cost and time cycle reduction
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

71

Best Practices, TSX PSWR


CHEMICAL CLEANING OF HSD AND NAPHTHA LINES IN CCPP
GENERAL PRACTICE
Cleaned by card board blasting BEST PRACTICE Citric acid cleaning with passivation ADVANTAGE Where the length of HSD and Naphtha lines is more than 500 meters cardboard blasting shall not be very effective. Hence, citric acid cleaning is a most effective way of ensuring cleanliness of the entire piping Time cycle reduction and trouble free operation
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

72

Best Practices, TSX PSWR


USE OF THERMIC FLUID HEATER FOR COMMISSIONING ACTIVITIES IN GREEN FIELD PROJECTS

GENERAL PRACTICE Auxiliary boiler is used for generation of steam for precommissioning activities like flushing of Boiler Feed Line, Condensate Lines, Drip Lines etc.

BEST PRACTICE
Thermic fluid heater is used in green field projects in place of auxiliary boiler for carrying out chemical cleaning activities. This results in cost and time saving.
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

73

Best Practices, TSX PSWR


ACID CLEANING WITH EDTA
GENERAL PRACTICE Generally HCL is used for acid cleaning of main boiler.

BEST PRACTICE HCL is replaced by EDTA for all green field projects especially, where auxiliary steam is not available. This is safe, environment friendly and reduces time cycle.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

74

Best Practices, TSX PSWR


PROVISION OF ADDITIONAL INTERSTAGE VALVES FOR STEAM BLOWING
GENERAL PRACTICE Interstage valves are not used during steam blowing operations resulting in three to four days shut down for start of subsequent steam blowing operations.

BEST PRACTICE

Additional temporary valves are used at Main Steam HP Bypass lines, CRH Lines during steam blowing operations.
This has resulted in cycle time reduction.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

75

Best Practices, TSX PSWR


CONTINUOUS STEAM BLOWING IN CCPP
GENERAL PRACTICE Puffing method is used due to limitation of fuel firing system

BEST PRACTICE Continuous blowing method (30 minutes) is used in stages

ADVANTAGE Effective cleaning and time cycle reduction

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

76

Best Practices, TSX PSWR


HIGHER STEAM BLOWING PARAMETERS
GENERAL PRACTICE

Steam blowing is carried out at 40 Kg / sq cm and 300 350 deg C


BEST PRACTICE Steam blowing carried out at 50 Kg / sqcm and 370 400 deg C

ADVANTAGE
Effective cleaning due to higher disturbance factor at elevated parameters Time cycle reduction

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

77

Best Practices, TSX PSWR


USE OF FRESH LUB OIL BOTH FOR FLUSHING AND REUSE IN ALL INDUSTRIAL SETS
GENERAL PRACTICE Flushing oil is used for oil flushing operation, fresh oil is used for normal operation

BEST PRACTICE
After cleaning of entire lub oil system by cardboard blasting fresh oil is used both for flushing and normal use ADVANTAGE Cost and time cycle reduction

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

78

Best Practices, TSX PSWR


AIR LEAK TEST OF LUB OIL, CONTROL OIL, AND CONTROL FLUID SYSTEM
GENERAL PRACTICE No separate test conducted before start of flushing resulting in leakage of oil / fluids BEST PRACTICE Entire system is pressure tested with compressed air at 5 to 6 Kg/sqcm before start of flushing operation ADVANTAGE Leakage of oil and control fluid is minimised Cost and time cycle reduction
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

79

Best Practices, TSX PSWR


GENERATOR SEAL OIL FLUSHING

GENERAL PRACTICE Seal oil flushing is done for the site erected pipes upto the inlet nozzle in the end shield BEST PRACTICE Pre-fabricated pipes from the end shield upto seal ring inlet are also included in the final stage of flushing. ADVANTAGE Avoids damage to Generator seal from the entrapped foreign material.
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

80

Best Practices, TSX PSWR


HYDRAULIC TEST OF LUB OIL, CONTROL OIL AND SEAL OIL LINES
GENERAL PRACTICE Jacking oil pumps were used for carrying out hydraulic test of lub oil, control oil and seal oil line after flushing. BEST PRACTICE AC seal oil pimp is used for the purpose of hydraulic test of the above system. ADVANTAGE Avoids damage to Jacking oil pumps.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

81

Best Practices, TSX PSWR


CONDENSER MASS FLUSHING
GENERAL PRACTICE

Cleaning of condenser is normally carried out during steam dumping operation


BEST PRACTICE Condenser tubes are thoroughly flushed through high pressure jets (fire fighting water) before commissioning of CEP ADVANTAGE Duration of steam dumping operation reduced

Cost and time cycle reduction

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

82

Best Practices, TSX PSWR


CLEANING OF VACUUM PUMP SUCTION LINES
GENERAL PRACTICE No structured cleaning is envisaged except draining the system through drain valves (NB50) during initial commissioning of vacuum pumps BEST PRACTICE Vacuum pumps suction lines are throughly cleaned through cardboard blasting before commissioning of vacuum pumps ADVANTAGE

Smooth trouble free operation


Damage of vacuum pumps due to entry of foreign material is avoided
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

83

Best Practices, TSX PSWR


OLTC COMMISSIONING
GENERAL PRACTICE
OLTC is commissioned normally after attaining continuous operation of unit, i.e., CW system has been put into service for prolonged period BEST PRACTICE OLTC is commissioned either Immediately after running of CW pump or Before conductance of PG test after thorough cleaning of condenser tubes ADVANTAGE Collection efficiency of balls increase

Trouble free condenser operation


05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

84

Best Practices, TSX PSWR


SELF CONTAINED BEARING COOLING ARRANGEMENT AT EPC PROJECT
GENERAL PRACTICE Lub oil coolers for ID, FD and PA Fans are kept charged through the bearing cooling water system

BEST PRACTICE
In EPC project where due to certain circumstances there is a delay in commissioning of Cooling Water system a separate self contained cooling arrangement (Sintex tank, pumps and suitable hoses) to facilitate initial commissioning ADVANTAGE Trial operation of all major boiler auxiliaries can be completed by this method leading to time cycle reduction
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

85

Best Practices, TSX PSWR


PRE ERECTION CHECKING OF BUS-DUCTS
General Practice Bus-ducts are cleaned and erected

Commissioning jobs taken up later


Best Practice While at ground, check tightness of all electrical connections of heaters, thermostats etc Check heaters healthiness and adjust thermostat tripping points easily now Check drain pad holes before lifting so that any corrections, if required can now be done easily Trial assembly of Bus-duct structure on ground before erection Avoids difficulty in commissioning / troubleshooting
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

86

Best Practices, TSX PSWR


TURBINE X-CRITERIA

General Practice

In X1 criteria for turbine rolling, main steam inlet temperature to turbine has been used for criteria calculation. During any boiler trip and restart, X1 criteria gets fulfilled even though boiler outlet temperature is less. This leads to cold steam entering the turbine.
.

.Best Practice Additional criteria X11 introduced using Temperature before HP bypass.
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

87

Best Practices, TSX PSWR


ADDITIONAL TRIPPING DURING ATT

General Practice

Tripping criteria during conductance of ATT does not include many vital trip inputs
.

.Best Practice Conditions like MFT, Turbine Bearing temperature VH, axial shift VH, vacuum low, cold gas temp trip, seal oil temp trip etc are added

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

88

Best Practices, TSX PSWR


COMMISSIONING OF ATRS, ATT & AUTOSYNCHRONIZER
General Practice Normally, ATRS, ATT and Auto-synchroniser are getting commissioned as pending points and not as a part of normal plant commissioning. So after the pending point is cleared, customer is normally not using the system.

Best Practice
We are putting efforts for commissioning these system in the first rolling synchronisation itself. Recently at Bhilai and Tata Trombay, ATRS and Auto-synchroniser have been commissioned during first few start-ups. At Tata Trombay, ATT is also commissioned.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

89

Best Practices, TSX PSWR


DC EOP AND SOP LATCH RELAY
General Practice Lub Oil pressure low switch starts DC EOP through max system SLC latch relay contract..

.
Best Practice

SLC latch relay contract in DC EOP and SOP cabinet looped so that lub oil pressure low switch contact starts DC EOP and SOP directly, bypassing MAX system SLC ON. This safeguards machine in the event of AC as well as failure of max system

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

90

Best Practices, TSX PSWR


AUTOSYNCHRONIZATION
General Practice As per circuit configuration, auto synchronizer after fulfilling its set condition directly closes the Generator circuit breaker..

.Best Practice Additional contact of check synchronization relay wired up in auto synchronization circuit. Here autosynchroniser setting are coordinated with setting of check synchronizing relay so that autosynchroniser and check synchronization relay operates at the same time.
This helps in safeguarding the machine during malfunctioning of autosynchronizer.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

91

Best Practices, TSX PSWR


AUTOSYNCHRONIZER TESTING
General Practice As per normal practice, autosynchronizer is tested and its output command is verified within the panel terminals.. Best Practice Autosynchronizer is tested in cold condition with supply of PT voltages through injection kit and actual Generator breaker closing (ensuring that isolators are open) This helps in optimization of autosynchronizer setting more correctly and also total circuit gets checked.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

92

Best Practices, TSX PSWR


USE OF MULTIPLE FILTRATION MACHINES FOR TRANSFORMER DRYOUT

General Practice One Oil filtering machine (about 6 KL capacity) engaged for dryout

Best Practice More than one such machine put in parallel operation to optimally utilise transformer drain header flow capacity Advantage Cycle time reduced around 50%

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

93

Best Practices, TSX PSWR


TURBINE BEARING METAL TEMPERATURE CHECKING

General Practice As per normal practice, cabling from bearing metal temperature JB to control room/Cold Junction Compensation(CJC) JB are checked after installation of thermocouple in bearings.. .Best Practice Before installation of thermocouples in bearing, signal upto DCS checked by heating the thermocouple tag wise.

This ensures correctness of connection, readings and also ambiguity of polarity change is avoided.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

94

Best Practices, TSX PSWR


DAVR DUMMY LOAD TESTING
General Practice As per normal practice, the AVR/DAVR dummy load testing is carried out at site with the help of 500W lamp or any available resistive load.. .Best Practice Dummy load testing is carried out with same type of resistive load which is identical in ratio to that of factory testing. With this type of testing, exact and identical readings with factory can be ensured. Customer as well as commissioning engineer gets better confidence on DAVR working.
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

95

Best Practices, TSX PSWR


PAINTING OF TRANSFORMERS AND BUS-DUCTS
General Practice Painting works for busducts and transformers are attempted at very late stages Becomes difficult because of shutdown requirement and thus opportunity may not be there Best Practice At least Station transformer and its busducts may be painted immediately after erection completion (before first charging). This transformer hardly goes into shutdown later Better to paint the other transformers and busducts as well as soon as possible before charging However, customer opinion / permission may be required since they may insist on painting only after all works are completed
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

96

Best Practices, TSX PSWR


SEQUENCE STARTUP OF HT DRIVES
General Practice

All HT drives are generally started individually during first commissioning of the drives This lead to a pending point as we do not get suitable opportunity to commission the HT drives in sequence mode Best Practice
All the HT drives to be started in sequence during first startup of the any HT drive

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

97

Power Sector Western Region


Process improvements Adopted During Overhaul by PSWR-SAS Nagpur

Introduction
Implementation of Best Practices during Overhauling
of T.G. has resulted into the following -

Overhauling cost reduction.


Reduce overhauling periods. Improvement in quality.

Introduce latest technologies.


Improve customer satisfaction

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

99

Implementation of Best practices


Use of latest technology like induction heating for dismantling and assembly of turbine.
Unit de-synchronization at 480 C of HP shaft temp by decreasing the load before shut down..

Turbine oil pump stop at 125C (HPS temp).


Barring gear stop at 125C (HPS temp). To initiate overhauling activities as soon as machine comes to barring gear.

Decoupling of Generator rotor from turbine rotor and put back turbine rotor in barring.
Start dismantling of generator and O/H activities thereafter.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

100

Review by Site and follow-up from HQ


Site reviews all activities minutely Time taking processes, idle times between activities, delay in arranging spares and mobilization of experts from units etc are identified well in advance. HQ also involves in reviewing processes and all important issues and HQ inputs are duly incorporated on activity planning at site. Reduction in overhauling duration to the target schedule is attributed to meticulously planning and follow-up of critical activities, which is accomplished in a shortest duration.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

101

Strategic Planning
List out the History of past problems
Pre-overhaul survey record. Analyze Present running behavior. Input from MOUs and utilities. Timely arrange experts service from MOUs Milestone based review. Mobilization of resources 3 days before start of Overhaul. Scheduling of sequential & parallel activities Identification of idle time & to avoid them by detailed planning in advance All the anticipated spares required for completion of the overhauling work arranged at T.G. Floor before start of the work.
05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

102

Generator work starts within 36 hrs of De-synchronization


0000 hrs : De-synchronization (HP shaft temp at 480 Deg.C)
17.5 hrs : Barring gear stop (HP shaft temp at 400 Deg C) 17.5 hrs. to 20.5 hrs:

AOP stop
Lub oil to brg. 5,6,7 blanked & brg. 4 minimized LP-Gen coupling decoupling

Hand barring will continue during this period


20.5 hrs : B/G re-started With this practice Generator rotor thread out work starts within 36 hrs of de-synchronization.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

103

Procedure for decoupling of LP-Generator in hot conditions


Turbine is on Turning Gear. JOP in service, AOP in service.
Loosening of pedestal cover bolts, removal of Vibration probes. Close turning gear valve to reduce the speed. Simultaneously loosen and remove pedestal cover bolts. When Turbine speed becomes zero. Stop AOP while JOP is continuously kept in service. Continue Hand Barring. Remove pedestal 4 cover. Close Lubricating oil throttle valve to the minimum possible. Simultaneously blank lub oil supply to bearing 5,6 and 7 by putting gasket in lub oil supply line. (parallel, by 3 gangs). Keep watch on bearing 1,2 and 3 metal temperature and simultaneously do hand barring.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

104

Procedure for decoupling of LP-Generator in hot conditions


Put tin sheet/polythene to cover on bearing 4. Start EOP and continue hand Barring.
Loosen LP-Generator coupling bolts and decouple LP-generator by continuing hand barring.

Shift generator rotor away from turbine Stop EOP and Adjust brg. 4 lubricating oil throttle valve to normal. Put pedestal cover back and start EOP & barring gear.
Dismantling & prepare for rotor thread out.

At the time of rotor thread out, stop turning gear again and stop EOP. Remove pedestal 4 cover.
After thread out put pedestal 4 cover back. Turbine on Barring gear with AOP in service till HP shaft temp comes to 125 deg C .

Note: Jacking oil pump is throughout kept in service.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

105

PSWRs Best records on TG overhauls


Overhauling of IP-LP Turbine & Generator including LP Turbine blades MPI have been carried out in record lowest time of 8 days barring to barring. (13 days Bar to Bar) on year 2007 at 250MW U#2 Dahanu TPS. Overhauling of LP Turbine & Generator have been carried out in record lowest time of 9 days barring to barring. (15 days Bar to Bar) on year 2005 at 250MW U#2 Dahanu TPS . This was achieved as an exceptional case to avoid power problem in Mumbai. Overhauling of HP- LP Turbine & Generator including HP rotor replacement & HP/IP coupling hole reaming, LP free standing blades MPI & NFT along with bearings 1,2 & 4 replacement have been carried out in record lowest time of 13 days baring to barring. (18 days Bar to Bar) on year 2006 at 250MW U#1 Dahanu TPS.
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

106

PSWRs Best records on TG overhauls


Overhauling of IP-LP Turbine & Generator including LP Turbine blades MPI & NFT have been carried out in record lowest time of 12 days barring to barring. (17 days Bar to Bar) in year 2008 at 250MW U#2 Dahanu TPS.
Unit-3 HP Module overhauled in 14 days barring to barring (19days bar to bar) in year 2006 at 200MW U-3 KSTPS NTPC Korba. Capital Overhauling of HP-IP-LP Turbine & Generator including HP rotor replacement & HP/IP coupling hole reaming, LP free standing blades MPI & NFT have been carried out in record lowest time of 35 days barring to barring in year 2008 at 500MW U#8 NTPC VSTPS Vindhyachal .

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

107

Schedule comparison
Sl.
No Capacity (MW) Previous Best Record Present Record

Capital Overhauling TG SET (Barring to Barring)

500
(All three module + Gen)

36 Days Unit-6, NTPC,KSTPS Korba on year 1996

35 days Unit-, NTPC, VSTPS Vindhyachal on year 2008

250

(HP-LP&GEN)

30 Days Unit-U-2 REL, Dahanu TPS on year 2002

13 days Unit-U-2 REL, Dahanu TPS on year 2006

250 (IP-LP&GEN)

8 days Unit-U-2 REL, Dahanu TPS on year 2007

200/210
(HP Module)

28 Days Unit-2 NTPC KSTPS on year 2001

15 Days Unit-3 NTPC KSTPS on year 2006

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

108

Conclusion
A benchmark on record minimum duration in KWU design TG set overhaul could be achieved.
It was the determination, commitment, monitoring and follow-up of associated activities that ascertained to achieve a challenging target. Working out activities well in advance with subcontractor agencies/ partners and round the clock execution of job with new strategies helped to meet schedule deadlines.

Work can be started as soon as machine comes to Barring gear.


Cooling Down period can be saved relatively by 4 days during the Generator overhauling.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

109

Power Sector Western Region IMPROVED SITE FACILITIES

Porta Cabins - to overcome delay in site mobilisation


Award of Enabling works and its construction takes considerable time, after receipt of confirm order. This delays posting of site staff and material management including posting of Construction Manager. PSWR has decided to procure Porta Cabins with all amenities as replacement of Conventional Site office sheds. This will be provided in all new sites like Satpura, Mauda, Chandrapur, Raigarh, Vindhyachal, Bela Ideal Energy including all forthcoming sites. NIT has been floated and tender is likely to be finalized by end April 2009.

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

111

05/05/2012

Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

112

Porta Cabins - to overcome delay in site mobilisation


Advantages of Porta Cabins
1. 2. 3. 4. Quick mobilization Quick realization of mobilization advance from customer Quick demobilization Flexibility in use & can be installed as per the site condition

5.
6. 7. 8.

Environmental friendly due to cleanness & easy maintenance


Provide better facility to site staff Light weight (Easy in handling and transportation) Aesthetic look.

9.

Durable and Termite proof

10. Seismic-resistant 11. Economical in long term because of repetition 12. Thermal Insulation
Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence Power Sector Western Region

05/05/2012

113

Вам также может понравиться