Академический Документы
Профессиональный Документы
Культура Документы
2003-04
2004-05 2005-06 2006-07 2007-08
84574
87906 93255 100715 108866
75066
77652 81792 86818 90793
-9508
-10254 -11463 -13897 -18073
-11.2
-11.7 -12.3 -13.8 -16.6
April-March 2008 Peak Met Surplus/Deficit (-) (MW) (%) 275 0 0 4030 -45 -1.1 4821 -135 -2.7 1010 -51 -4.8 1444 -506 -25.9 7340 --1332 -15.4 5559 -815 -12.8 8568 -2536 -22.8 1150 -50 -4.2 29495 -2967 -9.1
(In MW)
April-March 2008 Peak Met Surplus/Deficit (-) (MW) (%) 2188 8885 -233 -3234 -9.6 -26.7
MP
Maharashtra Goa Western Region
7200
18441 457 38277
6436
13575 408 29385
-764
-4866 -49 -8892
-10.6
-26.4 -10.7 -23.2
(In MW)
April-March 2008 Peak Met Surplus/Deficit (-) (MW) (%) 9162 5567 -929 -1016 -9.2 -15.4
Kerala
Tamil Nadu
2918
10334
2742
8690
-176
-1644
-6.0
-15.9
Pondichery
Southern Region
276
26777
276
24368
0
-2409
0.0
-9.0
ER
State
NER
State Peak Demand Arunachal Pradesh Assam Manipur Meghalay a Mizoram Nagaland Tripura 101 848 119 455 97 91 171
(In MW)
April-March 2008 Peak Met Surplus/Deficit (-) (MW) (%) 75 766 97 279 58 88 141 -26 -82 -22 --176 -39 -3 -30 -25.7 -9.7 -18.5 --38.7 -40.2 -3.3 --17.5
NERegion
ALL India
1742
108866
1347
90793
-395
-18073
--22.7
--16.6
2002-03
2003-04 2004-05 2005-06 2006-07 2007-08
545983
559264 591373 631757 690587 737052
497890
519398 548115 578819 624495 664660
-48093
-39866 -43258 -52938 -66092 -72392
-8.8
-7.1 -7.3 -8.4 -9.6 -9.8
Requirement Availability
Bihar DVC Jharkhand Orissa West Bengal + Sikkim Eastern Region 9242 13373 5048 18833 28979 297 75772 7930 13033 4416 18489 27865 283 72016
Arunachal Pradesh Assam Manipur Meghalaya Mizoram Nagaland Tripura NERegion ALL India
594 2246
2006-07
Mar-07
2012
2022
2032
Site Selection
Chimney should not fall within the approach funnel of the runway. 500 mts. Away from National Highway, Railway and Flood Plains of the Riverine Systems 10 kms away from archaeological, historical, cultural, religious or tourist importance and defence installations No forest or prime agricultural land should be utilized for setting up of TPS, or for ash disposal. Should not be on coal bearing area.
5.5
11
18
35
CONTENTS OF FR
Need and Justification of the Scheme. Preliminary Analysis of Alternatives Linkage/Availability of Various Inputs Availability of Various Clearances. Energy Absorption Plan Energy Evacuation Plan Financial and Executing Capabilities Plant Technical Features incl. Bill of Quantities Environmental Aspects Project Execution and Mgt. incl Implementation Schedule Cost Estimates Financial Package Tariff Calculations. Establishment Project Viability
Agency
State Government State Irrigation Deptt. CWC / MOWR Dept. of Coal (SLC) Ministry of Petroleum & Natural Gas Railways / GAIL/Oil Companies
CLEARANCES REQUIRED
Clearance
Clearance for Chimney height Defence Clearance Public Hearing
Agency
Airports Authority of India Ministry of Defence SPCB
OTHER REQUIREMENTS
Item
Power Evacuation Power Purchase Agreement Financing ICB Clearance Mega Certificate, wherever applicable
Agency
Powergrid/CEA Beneficiaries MOP/DEA MOP MOP
a) an inter-state thermal power plant of a capacity of 700 MW or more, located in the States of Jammu and Kashmir, Sikkim, Arunachal Pradesh, Assam, Meghalaya, Manipur, Mizoram, Nagaland and Tripura; or
b) an inter-state thermal power plant of a capacity of 1000 MW or more, located in States other than those specified in clause (a) above; or c) an inter-state hydel power plant of a capacity of 350 MW or more, located in the States of Jammu and Kashmir, Sikkim, Arunachal Pradesh, Assam, Meghalaya, Manipur, Mizoram, Nagaland and Tripura; or d) an inter-state hydel power plant of a capacity of 500 MW or more, located in States other than those specified in clause (c) above
Goods required for setting up of any mega power project, qualify for the above fiscal benefits after it is certified by an officer not below the rank of a Joint Secretary to the Govt. of India in the Ministry of Power that (i)the power purchasing States have constituted the Regulatory Commissions with full powers to fix tariffs;
(ii)the power purchasing States undertakes, in principle, to privatize distribution in all cities, in that State, each of which has a population of more than one million, within a period to be fixed by the Ministry of Power.
Appraisal is based on
Technical Feasibility Comprehensiveness Tie-up of Inputs Availability of Clearances Consent from GSI on Geological aspect Consent from CWC on Hydrology Cost Estimates Comparison with other Similar Projects (Least Cost Solution) Power Evacuation Arrangement
Investment Approval
Enhanced Delegations of Powers to Navratnas (From July, 1997; revised w.e.f 5.8.05) Identified Navratna PSEs incl. NTPC have been delegated powers including to
Incur capital expenditure on purchase of new items or for replacement without any monetary ceiling. Establish Financial JVs and wholly owned subsidiary in India or abroad with the stipulation that the ceiling of equity investment of the PSE shall be 15%(5% earlier) of the net worth of the PSE limited to Rs1000crs (Rs.200 Crs. earlier) in any one project and 30%(15% earlier) of the net worth of the PSE in all JVs Wavier of Ceiling of Rs 1000Crs for participating in bidding of Ultra Mega Projects (s.t implementation of 2 projects) (Special approval conveyed on 14.11.2006)
Enhanced Delegations of Powers to Navratnas (From July, 1997; revised w.e.f 5.8.05)
mergers
and
acquisitions
(i) it should be as per the growth plan and in the core area of functioning of the PSE, (ii) Conditions / limits would be as in the case of establishing joint ventures/subsidiaries, and (iii) the CCEA would be kept informed in case of investments abroad.
Powers to be exercised in such a manner that it should not lead to any change in the public sector character of the concerned PSEs (28.5.07)
FR/DPR to be approved by the Project Sub-Committee of the Board comprising Chairman & Managing Director, Director (Finance), Director (Projects), Director (Operations), Director (Technical), Director (Commercial), Joint Secretary (Thermal) and One (1) Non-Official/Parttime Director as Members. The Chairman & Managing Director shall be the Chairman of the Project SubCommittee. The quorum for the Sub-Committee shall be four (4) Members including one (1) Part-time Director.
FR/DPR submitted to CEA, wherever applicable FR/DPR approved by Project SubCommittee of the Board. Project identified in the Annual Plan.
Techno-Economic Clearance from CEA, wherever applicable. For other projects, Appraisal by independent agency. Necessary Budgetary Provision
CMD shall approve issue of NIT for various packages including Main Plant Package in case of New/Expansion Projects before Boards investment approval after FR/DPR is approved by Project Sub-Committee of the Board subject to following and relevant Govt. guidelines : i) FR approved by Project Sub-Committee of the Board.
ii) CEAs TE Clearance for the project is available, wherever applicable / Appraised by independent agency in case of other Projects
Availability of Inputs
Land availability confirmation. Water linkage from State Irrigation Dept. and Concurrence of CWC/MOWR, if it is inter-State jurisdiction. Fuel linkage, wherever applicable Signing of Fuel Supply Agreement, wherever applicable
Availability of Clearances SPCB clearance. MOEF clearance Forest clearance, if necessary Civil Aviation Clearance, wherever applicable Defence/Archaeological clearance, if necessary. CEAs Techno-Economic Clearance, wherever applicable
Capacity in MW
1980
Korba-III
Farakka-III NCTPP-II Simhadri-II Mauda
500
500 980 1000 1000
Bongaigaon
Barh-II Koldam Loharinag Pala
750
1320 800 600
Tapovan Vishnugad
520
(MW)
1990 16680 3760
22430
2500
MW), Vindhyachal-IV (2x500 MW), Vallur-II (1x500 MW) & Muzaffarpur Exp. (2x250 MW) Critical units for comm. in XI Plan: 2820 MW- North Karanpura-U1, Barh-II-U2, Mauda -U2, Rihand-III- U2 and Vindhyachal-IV- U2 Capacity at the end of XI Plan- 49834 MW - Coal 39879 MW, Gas-8035 MW and Hydro 1920 MW
Project
ON GOING PROJECTS
Capacity (MW) 1500
Kahalgaon-II
Sipat-II Sipat-I Barh Korba-III Bhilai Exp.- JV NCTPP-II Farakka-III Simhadri-II Aravali STPP-JV Vallur-I -JV
1000 1980 1980 500 500 980 500 1000 1500 1000
500 1980 1980 500 250 980 500 1000 1500 1000
ON GOING PROJECTS
Project Capacity (MW) Balance Capacity In XI Plan (MW)
Nabinagar-JV Bongaigaon Mauda* Barh-II** Koldam HEPP LohariNag Pala Tapovan Vishnugad TOTAL * LOI issues, LOA yet to be placed.
**
PROJECTS FOR WHICH MAIN PLANT BIDS HAVE BEEN RECEIVED/INVITED Project Capacity (MW) 1980 1000 1300 1300 Capacity In XI Plan (MW) 660 500 1300 1300 3760
BACK UP CAPACITY FOR XI PLAN Project Capacity (MW) 1000 1000 500 Capacity In XI Plan (MW) 500 1000 500
500
500
2500
Exercise
Q WHAT ARE DIFFERENCES IN TIE-UP & CLEARANCE OF THERMAL & HYDRO PROJECT
SOLUTION
S.N. THERMAL
1. 2. Coal/gas/liquid fuel Chimney
HYDRO
No such issue No such issue
3.
4. 5. 6.
No such issue
No such issue No such issue No such issue
DISCUSSIONS
Jai Wardhan Kumar Senior Engineer Project (Control & Instrumentation) VSTPP, Singrauli, MP Email-jaiwardhankumar@ntpc.co.in Mobile-9425823405, Intercom-1297,3730 More Interaction-jaiwardhankumar@hotmail.com (orkut/facebook/twitter/linkedin)
WEBSITE
http://sites.google.com/site/investntaxcare http://www.wrldc.com/ http://www.cercind.org/ http://www.indianelectricity.com/ http://cea.nic.in http://www.ntpc.co.in http://www.pfcindia.com
THANKING YOU
Rs in Crs.
Cost Mega
770 3200 98 78
1 77 846 4992
Cost Non-mega
770 3200 110 503 133 # 302 # 68 926
5509
Purchase Preference
Since 1971 Price Preference not exceeding 10% was admissible to products and services produced by a CPSE and being offered to other CPSEs. Consequent to economic liberalization, this was reviewed in 1991. Purchase Preference Policy was introduced in January, 1992 replacing the Price Preference Policy with validity for 3 years. Under this if the price quoted by a CPSE was within 10% of the lowest valid bid price (L-1) in a tender, other things being equal, preference to be accorded to CPSE at L-1 price. This is to enable CPSEs to adjust to new environment of competition in the wake of Globalization (falling tariff/custom duties) and liberalized industrial policy (pruning the list of industries reserved exclusively for public sector)
Purchase Preference Subsequently extended several times; presently valid till 31.3.2008. it was stipulated that it will be terminated w.e.f 31.3.2008. (18.7.05) Presently it is valid for contracts of the value of Rs 5 Crs and above but not exceeding Rs 100 Crs. A minimum value addition of 20% by the CPSE would be a pre-requisite. MOP is granted exemption from PPP, s.t condition that they will place certain orders upon BHEL on a negotiated basis price benchmarked through competitvely bid projects every year.
Price Preference
World Bank/ADB Guidelines ICB to be followed Evaluation of tenders to be done with out duties (customs duty & excise duty) Price Preference of 15% to domestic bidders allowed with the stipulation that value addition is more than 20%. Price Preference is to offset domestic duty/levies such as sales tax, octroi, etc and certain disadvantages due to inadequate infrastructure and higher cost of finance Mega Policy understood to have borrowed bidding provisions of World Bank funded Projects In the Evaluation, 15% of CIF price difference is loaded to the foreign bidder.
27404
22430
49834
Firmed up Projects 1. North Karanpura 2. Tanda-II 3. Meja 4. New Nabinagar 5. Solapur 6. Lata Tapovan 7. Rammam-III 8. Rupsiyabagar Khasiyabara 9 Darlipali 10 Lalitpur II Other projects 11. Gadarwara 12. RGCCPP-II 13. Lara 14. Markanam 15. Etalin & Attunil 16. Nuclear Power Project 17. Non-Conventional
1320 1320 1320 1980 1320 171 120 260 3200 4000
Balance capacity identified 19430 MW. Out of this 10000 MW to be firmed up for 12th