Вы находитесь на странице: 1из 30

Strategic Capacity Management

Capacity Planning

Capacity can be defined as the ability to hold, receive, store, or accommodate. It can also be defined as output attained within the normal operating schedule/conditions

Time Horizon for Capacity Planning


Long Range - Building, Equipments and Facilities (Greater than one year)

Intermediate Range - Hiring, layoffs, new tools, minor equipment purchase and subcontracting. (Quarterly or monthly) Short Range Daily and weekly scheduling, overtime, personnel transfer.

Strategic Capacity Planning

Strategic capacity planning is an approach for determining the overall capacity level of capital intensive resources, including facilities, equipment, and overall labor force size that best supports companies long term competitive strategy. Planning for capacity for a long run

How much should a plant be able to produce? How many customers should a service facility be able to serve? What kind of issues arise as the production system expands?

Strategic Capacity Planning


Capacity strategies are formulated keeping in mine;

The growth rate and variability in demand Cost of building and operating facilities of various sizes The rate and direction of technological innovation The likely behavior of competitors Availability of capital and other resources

Steps involved in Capacity Planning Process


Estimate future capacity requirements Evaluate existing capacity and facilities and identify gaps Identify alternatives for meeting requirements. Conduct financial analyses of each alternative Assess key qualitative issues for each alternative. Select one alternative to pursue.

Implement the selected alternative.


Monitor results

Capacity Utilization
Capacity used Capacity utilizatio n rate Best operating level

Where

Capacity used

rate of output actually achieved

Best operating level

capacity for which the process was designed


Volume of output at which average unit cost is minimum

Best Operating Level


Example: Engineers design engines and assembly lines to operate at an ideal or best operating level to maximize output and minimize ware

Average unit cost of output Underutilization Overutilization

Best Operating Level

Volume

Example of Capacity Utilization

During one week of production, a plant produced 83 units of a product. Its historic highest or best utilization recorded was 120 units per week. What is this plants capacity utilization rate? Answer:
Capacity utilization rate = Capacity used . Best operating level = 83/120 =0.69 or 69%

Economies & Diseconomies of Scale


Economies of Scale and the Experience Curve working

Average unit cost of output

100-unit plant 200-unit plant 300-unit plant 400-unit plant

Diseconomies of Scale start working Volume

The Experience Curve

As plants produce more products, they gain experience in the best production methods and reduce their costs per unit

Yesterday

Cost or price per unit

Today Tomorrow

Total accumulated production of units

Underlying Principles of Learning Curves 1. Each time you perform a task it takes less time than the last time you performed the same task 2. The extent of task time decreases over time 3. The reduction in time will follow a predictable pattern

Example of a Learning Curve


Suppose you start a term paper typing business. You time yourself on the first paper, then the second, and so on.

Term paper 1 2

Time (in Minutes) 100 90

3
4 5 6

84.62
81.00 78.30 76.16

Note that only 90 of 100 minutes are used in the second repetition. This is an example of a 90% learning curve.

Plotting the Learning Curve

All learning curves have this downward sloping curve.

90 % Learning Curve 120 100 80 60 40 20 0 0 1000 2000 Unit 3000 4000 5000

Production Time(Minutes)

Capacity Planning
Considerations in adding capacity;

Maintaining System Balance

Frequency of Capacity Additions

External Sources of Capacity

Capacity Planning: Balance


Unbalanced stages of production

Units per month

Stage 1 6,000

Stage 2 7,000

Stage 3 5,000

Maintaining System Balance: Output of one stage is the exact input requirements for the next stage
Balanced stages of production

Units per month

Stage 1 6,000

Stage 2 6,000

Stage 3 6,000

Determining Capacity Requirements


1. Forecast sales within each individual product line 2. Calculate equipment and labor requirements to meet the forecasts 3. Project equipment and labor availability over the planning horizon

Example of Capacity Requirements


A manufacturer produces two lines of mustard, FancyFine and Generic line. Each is sold in small and family-size plastic bottles. The following table shows forecast demand for the next four years.
Year: FancyFine Small (000s) Family (000s) Generic Small (000s) Family (000s) 1 50 35 100 80 2 60 50 110 90 3 80 70 120 100 4 100 90 140 110

Example of Capacity Requirements (Continued): Product from a Capacity Viewpoint

Question: Are we really producing two different types of mustards from the standpoint of capacity requirements? Answer: No, its the same product just packaged differently.

Example of Capacity Requirements (Continued) : Equipment and Labor Requirements


Year: Small (000s) Family (000s) 1 150 115 2 170 140 3 200 170 4 240 200

Three 100,000 units-per-year machines are available for small-bottle production. Two operators required per machine. Two 120,000 units-per-year machines are available for family-sized-bottle production. Three operators required per machine.

Question: What are the Year 1 values for capacity, machine, and labor?

Year: Small (000s) Family (000s)

1 150 115

2 170 140

3 200 170

4 240 200

Small Mach. Cap. 300,000 Labor 6 Family-size Mach. Cap. 240,000 Labor 6 150,000/300,000=50% At 1 machine for 100,000, it Small takes 1.5 machines for 150,000 Percent capacity used 50.00% Machine requirement 1.50 Labor requirement 3.00 At 2 operators for Family-size 100,000, it takes 3 Percent capacity used 47.92% operators for 150,000 Machine requirement 0.96 Labor requirement 2.88

Question: What are the values for columns 2, 3 and 4 in the table below?

Year: Small (000s) Family (000s) Small Family-size Small Percent capacity used Machine requirement Labor requirement Family-size Percent capacity used Machine requirement Labor requirement

1 150 115 Mach. Cap. Mach. Cap.

2 170 140 300,000 240,000

3 200 170 Labor Labor

4 240 200 6 6

50.00% 56.67% 1.50 1.70 3.00 3.40 47.92% 58.33% 0.96 1.17 2.88 3.50

66.67% 2.00 4.00 70.83% 1.42 4.25

80.00% 2.40 4.80 83.33% 1.67 5.00

Example of a Decision Tree Problem


A glass factory specializing in crystal is experiencing a substantial backlog, and the firm's management is considering three courses of action: A) Arrange for subcontracting B) Construct new facilities C) Do nothing (no change) The correct choice depends largely upon demand, which may be low, medium, or high. By consensus, management estimates the respective demand probabilities as 0.1, 0.5, and 0.4.

Example of a Decision Tree Problem (Continued): The Payoff Table


The management also estimates the profits when choosing from the three alternatives (A, B, and C) under the differing probable levels of demand. These profits, in thousands of dollars are presented in the table below:

A B C

0.1 Low 10 -120 20

0.5 Medium 50 25 40

0.4 High 90 200 60

Example of a Decision Tree Problem (Continued): Step 1. We start by drawing the three decisions

A B C

Example of Decision Tree Problem (Continued): Step 2. Add our possible states of nature, probabilities, and payoffs
High demand (0.4) Medium demand (0.5) Low demand (0.1)

$90k $50k $10k $200k $25k -$120k

A B C

High demand (0.4) Medium demand (0.5)

Low demand (0.1)


High demand (0.4) Medium demand (0.5) Low demand (0.1)

$60k $40k $20k

Example of Decision Tree Problem (Continued): Step 3. Determine the expected value of each decision
High demand (0.4) Medium demand (0.5)

$62k
A

Low demand (0.1)

$90k $50k $10k

EVA=0.4(90)+0.5(50)+0.1(10)=$62k

Example of Decision Tree Problem (Continued): Step 4. Make decision


High demand (0.4) Medium demand (0.5)

$62k
A B

Low demand (0.1) High demand (0.4) Medium demand (0.5) Low demand (0.1)

$90k $50k $10k $200k $25k -$120k $60k $40k $20k

$80.5k

C
High demand (0.4)

$46k

Medium demand (0.5) Low demand (0.1)

Alternative B generates the greatest expected profit, so our choice is B or to construct a new facility

Planning Service Capacity vs. Manufacturing Capacity

Time: Goods can not be stored for later use and capacity must be available to provide a service when it is needed Location: Service goods must be at the customer demand point and capacity must be located near the customer Volatility of Demand: Much greater than in manufacturing

Capacity Utilization & Service Quality

Best operating point is near 70% of capacity

From 70% to 100% of service capacity, what do you think happens to service quality?

Вам также может понравиться