Академический Документы
Профессиональный Документы
Культура Документы
By Ketan Bhingarde Kushinjai Vasalya Navrattan Roshan Kritika Tiwari Tarun Anand
Financing Information
The total project cost is estimated at 2,356 crores. The project shall be financed on the basis of a Viability Gap fund of 650 crores contributed by the Government of India (470 crores being 20% of the project cost) and Government of Maharashtra (180 crores being 7.5% of the project cost). The remainder is to be financed by 70% debt, 30% equity.
Financing Details:
Process Analysis
The study recommended a mass transit corridor from Andheri to Ghatkopar as potentially bankable and economically viable, after examining a number of alternative corridors and alignments. To manage the transaction process, a consortium consisting of Louis Berger as technical consultants, Price Waterhouse Coopers (PWC), Masons and Economic Law Practices was appointed in 2003-04 to assist MMRDA.
Process followed
GoI accorded approval to initiate Pre Qualification process subject to the condition that model documents finalized by GoI / Planning Commission will be followed. ThePre Qualification process started based on RFQ document of GoI. Concession Agreement finalized based on Bid Documents of Hyderabad Metro and drafts of Planning Commission. The documents submitted to Department of Economic Affairs (DEA) on 19th June 2008. Clearance was given by DEA in October 2008 after several meetings. The bid documents were issued to the bidders in October 2008
Siemens, L&T, Gammon, BEML IL&FS and ITD Thailand and Unity Infraprojects
Award of Contract
After the bid process, negotiations commenced with the lowest financial bidder, i.e. Reliance Energy and Connex France. Veolia Transport and Hong Kong MRT The contract for construction of Mumbai Metro is finally award to Reliance Energy and Connex France after the negotiations
Development
The development phase of the project was initiated in parallel to the VGF approval process. Major milestones achieved in the development phase are presented below: The SPV was incorporated in December 2006.
The Engineering and Project Management Consultants, a consortium of Parsons Brinkerhoff (USA) and Systra SA (France) joined the team on February 14, 2007
Signing of the Concession Agreement and Shareholders agreement took place on March 7, 2007
MMOPL and Government of Maharashtra entered the State Support Agreement on April 20, 2007
Construction commenced on February 8, 2008 Financial Closure for the project completed on October 3, 2008
SENSITIVITY
High Medium Medium Low
RISK PERIOD
0 5 Years 0 5 Years 0 5 Years 0 5 Years
RISK BEARER
Government Private Sector Private Sector Private Sector
Construction Risk
Medium
0 5 Years
Private Sector
low
0 5 Years
Government
Medium
0 5 Years
Private Sector
Medium
0 3 5 Years
Private Sector
High
0 30 Years
Private Sector
Performance Risk
High
0 30 Years
Private Sector
Handover Risks
RISK TYPE SENSITIVITY RISK PERIOD RISK BEARER Handover Risk Low 35 Years Private Sector
Low
0 35 Years
Private Sector
0 35 Years
Government
Other Risks
RISK TYPE SENSITIVITY RISK PERIOD RISK BEARER
Interface Risk Medium (with other metro corridors) Force Majeure Low
Throughout
Private Sector
Throughout
Low
Throughout
Private Sector
Current Status
The construction has commenced from February, 2008 and the project achieved financial closure in October 2008. The completion date for the project construction is expected by mid 2011. At present, the construction of the viaduct is underway with 773 piles being dug up. The construction of the Depot, Substation and Stations has also commenced along the route of the project. Work has also commenced on the construction of 2 overhead bridges at Andheri Station and the Western Express Highway.
THANK YOU.