Вы находитесь на странице: 1из 24

NTPC HYDRO LIMITED

( A WHOLLY OWNED SUBSIDIARY OF NTPC Ltd.)

BACKGROUND

To be a partner in the hydro power development program, NTPC Ltd has made a foray into hydro power through its maiden venture KOLDAM HEPP and drawn up an ambitious plan of adding approx. 3500 MW in hydro sector by the end of eleventh plan i,e by 2012. As estimated by Central Electricity Authority / Central Water Commission, 1/3rd of total hydro electric potential is from medium sized hydro electric project. Keeping this in mind and to boost NTPC Ltds capacity addition program in hydro sector, the corporation has set up a wholly owned subsidiary company named NTPC Hydro Limited in December 2002 to provide exclusive thrust for accelerated development of medium scale hydro power projects. The main objective of the company is to develop small to medium size Hydroelectric power project up to 250 MW capacity for generation of electricity.

NHL started its maiden venture through LATA-TAPOVAN HEP, in the state of Uttarakhand.

Since nature of NHLs business is similar to NTPC Ltds business, it is decided to follow DOP and other guidelines/ Circulars of NTPC Ltd Role of NHL:Development of Hydro Electric Power Construction Transmission line Manufacturing Trading and Other business Organization Structure
NHL - BOARD

CEO Sh. R. Khetarpal HR Headed by Sh. S.N. Ramachandran Chief Manager (HR) FINANCE Headed by Sh. S.S. Nagpal DGM (Finance) C&M Headed by Sh. K.R. Mondal DGM (C&M) ENGINEERING Headed by Sh. A.K. Aggarwal DGM (Engineering) P&S Headed by Ms. Rashmi Varma Sr. Manager (P&S)

Hydro Business development Presently NHL is having two prjects- Lata- Tapovan HEP and Ramam St. III HEP

LATA-TAPOVAN HYDRO ELECTRIC (171 MW)

PROJECT

MANA

BADRINATH

LATA TAPOVAN HEP

MALARI

JOSHIMATH

MARKURA

LATA GULABKOTHI PIPALKOTHI TAPOVAN


TAPOVAN VISHNUGAD HEP NTPC HYDRO LTD

NTPC

CHAMOLI

LOCATION PLAN

PROPOSED BARRAGE LOCATION

128 M

LATA-TAPOVAN HEP
LOCATION : 270 KM FROM RISHIKESH AND 27 KM FROM JOSHIMATH (ON JOSHIMATH-MALARI ROAD)

POWER HOUSE

UNDERGROUND, 500 M UPSTREAM OF TAPOVANVISHNUGAD BARRAGE 12 KM FROM TAPOVANVISHNUGAD BARRAGE

BARRAGE

LATA-TAPOVAN HEP TECHNICAL DETAILS

TYPE OF SCHEME : Run of the River RIVER : Dhauli Ganga INSTALLED CAPACITY : 171 (3x57 MW) DIVERSION STRUCTURE : Barrage, 199.5 m, GATES : Radial, 11 M x 13.2 M HEAD : 309 M COST OF ENERGY : Rs 1.35 / Kwh

LATA-TAPOVAN HEP TECHNICAL DETAILS

HEAD RACE TUNNEL ADITS SURGE SHAFT PENSTOCKS POWERHOUSE TURBINE TAIL RACE ANN. GEN. CONST. SCHEDULE

: 4.8 m Dia. , 7315 m Long : Two : 7 m Dia., 140 m High : 3 nos, 2.2 m Dia., 299.5 m long : Underground, 91.4x20x42.5 m : Francis Vertical Shaft, 3 Nos. : 310 m, 4.8 m Dia. : 869 MU (54 % PLF) : 5 years

LATA-TAPOVAN HEP

MOU between NHL and GOUA for execution of Lata Tapovan HEP signed on 18.08.03. Implementation Agreement between NHL and GOUA for execution of Lata Tapovan HEP signed on 21.11.05.

LATA-TAPOVAN HEP

CEA accorded TEC for 171 MW i.e. 3x57 MW capacity of the project on 08.02.06 at an Estimated Present Day Cost (Oct. 2005 Price Level) of Rs. 792.00 crores
Environmental Clearance of MOEF obtained on 21.02.07. Defence Clearance obtained on 22.06.07.

LATA-TAPOVAN HEP

Transfer of Forest Land (70.83 Ha): GOUA vide order dtd.


23.06.07 diverted forest land for project use.

Pvt. Land (3.804 Ha): Possession obtained on 4th and 5th Oct07. Mutation completed on 10.03.08.
One time rehabilitation grant Rs. 1 Lac per nalli to land losers ( including land cost)

LATA-TAPOVAN PROJECT
Geological and Geo-technical investigation was done by WAPCOS

DPR was prepared by TCE Consulting Engineers Ltd


Engineering Consultancy job placed on M/s Consulting Engineering Services (India) Pvt. Ltd. Implementation of project will be done in two EPC packages Civil including HM works package EM works package

NIT for Civil including HM works package has been issued on 12.11.2008

RAMMAM St-III HEP (3 x 40 MW)

PROJECT LAYOUT

RAMMAM St-III HEP


LOCATION : 130 KM FROM SILIGURI/ NEW JALPAIGURI AND 150 KM FROM BAGDOGRA AIRPORT / 80 KM FROM DARJEELING

POWER HOUSE

SURFACE (DEEP SEATED) APPROX. 10KM FROM JORETHANG (SIKKIM) 80KM FROM SILIGURI
AT LODHOMAHAT (DARJEELING)- 130KM FROM SILIGURI

BARRAGE

RAMMAM St-III HEP TECHNICAL DETAILS

TYPE OF SCHEME RIVER INSTALLED CAPACITY DIVERSION STRUCTURE GATES POWER INTAKE

HEAD
COST OF ENERGY

: Run of the River : RAMMAM : 120 (3x40) MW : Barrage, 55 m : Radial, 11 M x 7 M : Tunnel, D-Shape, 2 Nos. 2.85 M Dia : 499 M
: Rs 1.67 / Kwh

RAMMAM St-III HEP TECHNICAL DETAILS


HEAD RACE TUNNEL ADITS SURGE SHAFT PENSTOCKS

: 3.5 m Dia. , 8200 m Long : One : 14.5 m Dia., 52.5 m High : 1 no., 2.7 m Dia., 1526 m long POWERHOUSE : Surface Deep Seated TURBINE : Vertical Pelton, 3 Nos. TAIL RACE CHANNEL : 4x3 M, 740 M ANN. GEN. : 474.36 MU CONST. SCHEDULE : 5 years

RAMMAM St III HEP

Implementation Agreement between NHL and WBSEB for execution of Rammam St- III HEP signed on 28.04.05.

RAMMAM St-III HEP

CEA accorded TEC for 120 MW i.e. 3x40 MW capacity of the project on 12.09.06 at an Estimated Present Day Cost (Feb. 2006 Price Level) of Rs. 633.92 crores
Environmental Clearance of MOEF obtained on 17.08.07 Defence Clearance obtained on 25.02.08

RAMMAM St III HEP


( IN SIKKIM )

Transfer of Forest Land (1.927 Ha) Possession received on 18.10.08


Pvt. Land (5.256 Ha) Compensation distribution completed on 23.09.08 and possession received on 26.09.08 One time settlement on R & R package decided in VDAC meeting held on 22.05.07

RAMMAM St III HEP


( IN DARJEELING WB )

Pvt.+ Govt. Land (64.496 Ha) Possession of land received on 15.09.08 One time settlement on R & R package decided in VDAC meeting held on 18.12.07

RAMMAM St III HEP


Geological, Geo-technical investigation and DPR was prepared by WAPCOS Engineering Consultancy job placed on M/s Karnataka Power Corporation Ltd. Bridges and Approach Roads Package palced on M/s Nar Bahadur Dahal Implementation of project will be done in two EPC packages Civil including HM works package EM works package

NIT for Civil including HM works package is expected to be issued on 19.12.2008

THANK YOU

Вам также может понравиться