As per requirement
Methods
Tools Operation & Maintenance
& Requirements
Technologies
Power Plant Systems & Equipments
• Main Power Generation & Evacuation Systems & Equipments
eg Boiler, Turbine, Generator,Generator Transformer and SWYD
equipments (breakers, isolators) with instruments & control systems
• Routine Maintenance
• Preventive Maintenance
• Scheduled Maintenance
• Break Down Maintenance
• Diagnostic or Periodical Maintenance
Maintenance Management in
TPP
• Routine Maintenance
• Annual Overhaul
• Defect Rectification
• Work Request
• Scheduling & measuring of work
• Quality checks
• Production Calculation
• Different Management Ratio
Scope of Maint. Planning
• Over all Time and resource Planning
• Scheduling of Resources
• Issue and work Control
• Progress Monitoring
• Assessment of Productivity
• Reduce Plant Outages
• Condition Monitoring
Scope of Maint. Planning ….Contd.
• Monitoring Maintenance Cost
• Improve resource Utilisation
• Forecasting Target Dates
• Long Term Planning
• Short Term Planning
• Outage Planning
• Spare Parts Planning
Scope of Maint. Planning ….Contd.
• To develop five years Rolling Plan
• To develop Station Annual Plan
• To Create Standard Data Bank for
reference
• Overhauling Management
Essential Inputs
• Detailed and defined work Activity
• Standard work hour pattern and job duration
• Overall Time of outage
• Types of crafts men and skill required, their
availability and productivity
• Requirement of spares & Consumables, tools &
Plants etc., their source of availability
Essential Inputs…….Contd.
• Mobilisation of resources within given time
• Progress Monitoring of work
• Quality Checks
• Feedback System
• Budget i.e. Finance
• Generation Budget
• Fuel Budget
• Spares Budget
• Manpower Budget
• Revenue Budget
Function of LTP
• Compilation of Station Five year Rolling
Plan
• To Prepare and ensure all necessary
arrangement for the year’s overhaul work
programme
• Produce, Distribute and Monitor major
overhaul and control programme
Function of LTP …..Contd.
• Operate Section of PTW system Before,
during and after major overhaul
• Custody of all licences of equipments
under Indian Boiler Regulation Act, Indian
Electricity Act, Indian Explosive Act and
other safety Rules.
Function of STP
• Development & Monitoring of Station
work control system
• Co-ordinate with maintenance sections and
apprise them about plant reports
• Information about proposed shut down if
any, cooling, drains or constraints that
might delay the availability of permit to
start maintenance work
Function of STP ……Contd.