Академический Документы
Профессиональный Документы
Культура Документы
Project cost management includes the processes involved in planning, estimating, budgeting, and controlling cost so that the project can be completed within the approved budget.
PM PROCESS
7.1 Cost Estimating 7.2 Cost Budgeting -
Estimating schedule activity costs involves developing an approximation of the costs of the resources needed to complete each schedule activity.
Cost Estimating
Enterprise Environmental Factors Organizational Process Assets Project Scope Statement WBS WBS Dictionary Vendor Bid Analysis Analogous Estimating Determine Resource Cost Rates Activity Cost Estimates Bottom-up Estimating Activity Cost Estimate Supporting Detail Requested Changes Cost Management Plan (Updates)
Parametric Estimating
Project Management Software
INPUTS
OUTPUTS
PM PROCESS
7.1 Cost Estimating 7.2 Cost Budgeting -
OUTPUTS
Cost Baseline
PM PROCESS
7.1 Cost Estimating 7.2 Cost Budgeting 7.3 Cost Control -
Performance Reports
Work Performance Information Approved Change
Measurement Analysis
Forecasting Project Performance Reviews
Requests
Project Management Plan
Project Management
Software Variance Management
INPUTS
OUTPUTS
How
much it has cost to achieve what have been done to date Whether actual accomplishment is ahead or behind
The planned Value (PV): The sum of approved cost estimates for activities scheduled to be performed. The Earned Value (EV): The sum of the approved cost estimates for activities completed. The Actual Cost (AC): Total cost incurred in accomplishing work.
Cost Variance (CV) = EVAC Schedule Variance (SV) = EVPV Earned Value= EV = 100% complete*BAC Cost Performance Index (CPI) = EV/AC Schedule Performance Index (SPI) = EV/PV
CV<0 :?, CV=0 :?, CV>0 :?, CPI<1 :?, CPI=1 :?, CPI>1 :? SV<0 :?, SV=0 :?, SV>0 :?, SPI<1 :?, SPI=1 :?, SPI>1 :?
Alternative 1: EAC = Actual (AC) + (BAC-EV) Alternative 2: EAC = Actual (AC)+ New Estimate for Remaining Budget Alternative 3: EAC = Actual (AC) + (BAC-EV)/CPI
example
Thanks
Direct Cost
Indirect Cost
Overhead Cost