abcd GT24/26 Standard C-Inspection

Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
1 Control modifications in Baden 12,32 dys Wed 26.02.14 Tue 11.03.14
2 Start Control works 0 dys Wed 26.02.14 Wed 26.02.14
3 F_215850 SOFTWARE MODIFICATIONS; F_215850 : 8 hrs Wed 26.02.14 Thu 27.02.14
AUTOMATIC-MANUAL SPEED BOOSTER
4 F_217665 SW MODIFICATIONS: ODC 2006 HMI UPDATES - F_217665 : ODC 2 hrs Thu 27.02.14 Thu 27.02.14
DISPLAY SW VERSION 1.09 AND TOUCH SCREEN VERSION 2006 1.09
8.1 8.1
5 F_218754 CONTROL SW MODIFICATION: DATA TRANSFER F_218754 : 4 hrs Thu 27.02.14 Fri 28.02.14
BETWEEN NODES IN ADVANT CONTROL.
6 F_218540 CONTROL SW MODIFICATION: RELIABILITY ADVANT
F_218540 : 3 hrs Fri 28.02.14 Fri 28.02.14
IMPROVEMENTS- REGARDING PK2/PSEV INCREMENT
PROTECTION. PK2/PSEV
7 F_218267 CONTROL SW MODIFICATION: TO AVOID GCB & F_218267 : 4 hrs Fri 28.02.14 Sat 01.03.14
HV CB TRIPPING DUE TO RUN TIME PROBLEM.

8 F_218162 SW MODIFICATIONS: LOGIC IMPLEMENTATION OF
F_218162 :
8 hrs Sat 01.03.14 Sat 01.03.14
THE HOT / WARM RESTART CONCEPT /
9 F_218113 SW MODIFICATION: RE-WIRING OF FUEL GAS F_218113 : 4 hrs Sat 01.03.14 Mon 03.03.14
TEMPERATURE SIGNAL MBP43CT002 FOR DECOUPLED (
FUEL GAS SYSTEM MBP43CT002)
10 F_218056 SW MODIFICATION: RE-WIRING OF FUEL GAS
F_218056 : 4 hrs Mon 03.03.14 Mon 03.03.14
TEMPERATURE SIGNALS MBP42/43CT002 FOR COUPLED (
FUEL GAS SYSTEM MBP42/43CT002)
11 F_217810 CONTROL SW MODIFICATION: INTRODUCING
F_217810 : 24 hrs Mon 03.03.14 Thu 06.03.14
NONZERO DELAY FOR PLS/PLST PROTECTION.
12 F_217633 SW MODIFICATION ON GAS DETECTION F_217633PLS/PLST
: 6 hrs Thu 06.03.14 Thu 06.03.14
PROTECTION
13 F_217568 CONTROL SW MODIFICATION: UPDATE HRSG F_217568 : 2 hrs Thu 06.03.14 Thu 06.03.14
LEVEL PROTECTION AT GT FLAME OFF
-
14 F_216750 CONTROL SW MODIFICATION: POWER
F_216750 : 2 hrs Thu 06.03.14 Fri 07.03.14
OSCILLATION DETECTION.
15 F_215777 SW MODIFICATION: ODC PLS COUNTING F_215777 : ODC 4 hrs Fri 07.03.14 Fri 07.03.14
PLS
16 F_215185 SW MODIFICATION: ENCLOSURE VENTILATION F_215185 : 15 hrs Fri 07.03.14 Sat 08.03.14
17 F_214520 SOFTWARE MODIFICATION: ALIGN THE LOGIC TO F_214520 : 3 hrs Sat 08.03.14 Mon 10.03.14
ITABAR PROBES. ITABAR
18 F_209281 CONTROL SW MODIFICATION: TAT2 CORRECTION F_209281 : 8 hrs Mon 10.03.14 Tue 11.03.14
FUNCTION
19 Control works completed TAT2
0 dys Tue 11.03.14 Tue 11.03.14
20 Preparation the site for the inspection 10 dys Sat 01.03.14 Tue 11.03.14
21 Gas Turbine 10 dys Sat 01.03.14 Tue 11.03.14
22 Set up work areas 5 dys Sat 01.03.14 Mon 10.03.14
23 Gas turbine check and prepare tools, structures and FSI , 5 dys Sat 01.03.14 Tue 11.03.14
material for the inspection FSI
24 Preparation at Side (Induction / Training of ( , 5,77 dys Wed 05.03.14 Tue 11.03.14
Personnel) according lean concept )
25 Induction of Site specfic EHS (PTW Process, Lotto, RA

10 hrs Wed 05.03.14 Thu 06.03.14
etc.) ( , Lotto, RA .)
26 Technical Induction of GT26 GT26 4 hrs Thu 06.03.14 Fri 07.03.14
27 3D Video Combustor Inspection, ITH Hydraulic Tool , 6 hrs Fri 07.03.14 Fri 07.03.14
Training ITH
28 Workplace Administration & Laydown 3 dys Fri 07.03.14 Mon 10.03.14
29 Prepare technical documentation for CC (Drawings, WI, 20 hrs Fri 07.03.14 Sat 08.03.14
RA, Lifting plans etc) (, WI, RA, , ..)
30 Prepare white board documents (Task Sheets / ( 8 hrs Sat 08.03.14 Sun 09.03.14
Resources/ Material/ Consumable) , , , )
31 Set up of Stands for CC 6 hrs Sun 09.03.14 Sun 09.03.14
32 Marking of floor spaces, walk ways acc. to Laydown plan 5 hrs Sun 09.03.14 Sun 09.03.14

33 Set up shelves for material 3 hrs Sun 09.03.14 Sun 09.03.14
34 Set up white boards 3 hrs Sun 09.03.14 Mon 10.03.14
35 Material Management 2,91 dys Fri 07.03.14 Mon 10.03.14
36 Prepare storage possibilities acc. to requirements 2 hrs Fri 07.03.14 Fri 07.03.14
(Boxes, pallet etc.) (, ..)
37 Prepare CC FSI Material FSI 30 hrs Fri 07.03.14 Mon 10.03.14
38 Pre- assembly of Liner Segments, Front Panels etc. with , 30 hrs Fri 07.03.14 Mon 10.03.14
sealing cord ..
39 Set up Transport possibilities (Crane, Forklift,
(, 2 hrs Mon 10.03.14 Mon 10.03.14
Palletrolley) , )
40 Tools Management 0,32 dys Mon 10.03.14 Mon 10.03.14
41 Prepare CC Toolboxes 2 hrs Mon 10.03.14 Mon 10.03.14
42 Prepare CC special (Customer) tools 4 hrs Mon 10.03.14 Mon 10.03.14
( )
43 Place tool trolleys 1 hr Mon 10.03.14 Mon 10.03.14
44 Parts Cleaning 0,91 dys Mon 10.03.14 Tue 11.03.14
45 Prepare Cleaning area 4 hrs Mon 10.03.14 Tue 11.03.14
46 Install Cleaning equipment 6 hrs Tue 11.03.14 Tue 11.03.14
47 Contractor training 11 hrs Tue 11.03.14 Tue 11.03.14
48 F_214154 REMOVE THE OLD MONORAIL STRUCTURE ON F_214154 4 hrs Mon 10.03.14 Mon 10.03.14
THE AIM MS CONFIGURATION WITH TOP AIR
GENERATOR TYPE AND ASSEMBLE THE NEW MONORAIL
DESIGN (2+1 MONORAIL CONCEPT)
49 F_214250 IMPLEMENTATION OF NEW CHAIN BLOCKS
F_214250

2 hrs Mon 10.03.14 Mon 10.03.14
AND TROLLEYS ON THE NEW MONORAIL DESIGN (2+1 (
MONORAIL CONCEPT) AT THE AIM MS CONFIGURATION. 2+1)

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 1 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
50 F_218218 REWORK OF LIFT OUT BEAM. EXCHANGE OF F_218218 -. 2 hrs Mon 10.03.14 Tue 11.03.14
THE LIFT OUT BEAM NAMEPLATE AND OF THE LIFTING -
FORK NAMEPLATE. EXCHANGE OF TURNBUCKLES. . .

51 GT Generator 0,91 dys Mon 10.03.14 Tue 11.03.14


52 Set up working areas 20 hrs Mon 10.03.14 Tue 11.03.14
53 Check and prepare tools, structures and FSI material for the , 20 hrs Mon 10.03.14 Tue 11.03.14
inspection FSI
54 Steam Turbine 1,36 dys Sun 09.03.14 Tue 11.03.14
55 Set up work areas 30 hrs Sun 09.03.14 Tue 11.03.14
56 Check and prepare tools, structures and FSI material for the , 30 hrs Sun 09.03.14 Tue 11.03.14
inspection FSI
57 F_218559 HP VALVE BLOCK. NEW TOOL REQUIRED FOR F_218559 . 1 hr Sun 09.03.14 Sun 09.03.14
MAINTENACE WORK.
58 F_218562 IP VALVE BLOCK. NEW TOOL REQUIRED FOR
F_218562 .
. 1 hr Sun 09.03.14 Sun 09.03.14
MAINTANANCE WORK.
59 ST Generator
. 1,36 dys Sun 09.03.14 Tue 11.03.14
60 Set up working areas 30 hrs Sun 09.03.14 Tue 11.03.14
61 Check and prepare tools, structures and FSI material for the , 30 hrs Sun 09.03.14 Tue 11.03.14
inspection FSI
62 Supervised shut down 4,05 dys Mon 10.03.14 Fri 14.03.14
63 F_218997 SHUT DOWN READINGS F_218997
1,14 dys Mon 10.03.14 Tue 11.03.14
64 Check operational behavior during load 10 hrs Mon 10.03.14 Tue 11.03.14
65 Check operational behavior during transient 15 hrs Tue 11.03.14 Tue 11.03.14
66 F_218707 SHUT DOWN F_218997 0,91 dys Mon 10.03.14 Tue 11.03.14
67 Preparation and tests during Load 10 hrs Mon 10.03.14 Tue 11.03.14
68 Check operational behaviour in transient operation 10 hrs Tue 11.03.14 Tue 11.03.14
69 F_217843 PLANT ELECTRICAL C-INSP F_217843 0,5 dys Mon 10.03.14 Tue 11.03.14
70 SHUT DOWN READINGS 11 hrs Mon 10.03.14 Tue 11.03.14
71 Steam Turbine 3,93 dys Mon 10.03.14 Fri 14.03.14
72 100% load; readings, observation and tests 100%- , , 5,5 hrs Mon 10.03.14 Mon 10.03.14
73 FSI_219899 Vibration Readings on IP Stop Valve actuator FSI_219899 1 hr Tue 11.03.14 Tue 11.03.14

74 Deload to 50% load; readings and observation 50 %, , 1 hr Mon 10.03.14 Mon 10.03.14
75 Deload to 10% load; readings and observation 10 %, , 2 hrs Mon 10.03.14 Tue 11.03.14
76 Unloading and bypass operation; observation; overspeed test , ; ; 1 hr Tue 11.03.14 Tue 11.03.14

77 Hydraulic control and safety system testing 3 hrs Tue 11.03.14 Tue 11.03.14
78 Test of turning gear 3 hrs Tue 11.03.14 Tue 11.03.14
79 Unit cool down on turning gear 3,5 edys Tue 11.03.14 Fri 14.03.14
80 GT Generator 0,95 dys Mon 10.03.14 Tue 11.03.14
81 Shaft voltage test 5 ehrs Mon 10.03.14 Mon 10.03.14
82 Aquiring operating data 2 ehrs Mon 10.03.14 Tue 11.03.14
83 Breaker open 0 dys Tue 11.03.14 Tue 11.03.14
84 RSO (Rotor interturn short circuit test) RSO ( 5 ehrs Tue 11.03.14 Tue 11.03.14
85 Rotor winding insulation resistance measurement 5 ehrs Tue 11.03.14 Tue 11.03.14
86 Analysis of operation data 6 ehrs Tue 11.03.14 Tue 11.03.14
87 Overhaul Milestones 45 dys Tue 11.03.14 Fri 25.04.14
88 Shut down powertrain 0 dys Tue 11.03.14 Tue 11.03.14
89 Start work on GT 0 dys Tue 11.03.14 Tue 11.03.14
90 Start work on GT Geno 0 dys Tue 11.03.14 Tue 11.03.14
91 Start work on ST 0 dys Fri 14.03.14 Fri 14.03.14
92 Start work on ST Geno 0 dys Fri 14.03.14 Fri 14.03.14
93 ST ready for start up 0 dys Mon 07.04.14 Mon 07.04.14
94 Geno GT ready for motor roll 0 dys Tue 08.04.14 Tue 08.04.14
95 ST Geno ready for start up 0 dys Mon 14.04.14 Mon 14.04.14
96 GT ready for motor roll 0 dys Mon 21.04.14 Mon 21.04.14
97 Start hot commissioning 0 dys Mon 21.04.14 Mon 21.04.14
98 Recommissioning completed 0 dys Fri 25.04.14 Fri 25.04.14
99 Moscow G02647C01 Outage G02647C01 45 dys Tue 11.03.14 Fri 25.04.14
2Shifts/7Days/11Hours , 2 11 7
100 Gas Turbine C-Inspection C 41,97 dys Tue 11.03.14 Mon 21.04.14
101 Milestones 41,7 dys Tue 11.03.14 Mon 21.04.14
102 Shut down GT 0 hrs Tue 11.03.14 Tue 11.03.14
103 Permit to work during forced cooling issued 0 hrs Tue 11.03.14 Tue 11.03.14

104 Forced cooling complete 0 hrs Wed 12.03.14 Wed 12.03.14
105 Permit to work after forced cooling issued 0 hrs Wed 12.03.14 Wed 12.03.14

106 Outercasing removed 0 hrs Sun 16.03.14 Sun 16.03.14
107 Rotor removed 0 hrs Tue 18.03.14 Tue 18.03.14
108 Dismantling complete 0 hrs Wed 19.03.14 Wed 19.03.14
109 Start assembly 0 hrs Mon 07.04.14 Mon 07.04.14
110 Rotor installed 0 hrs Wed 09.04.14 Wed 09.04.14
111 Outercasing placed onto lower casing 0 hrs Sun 13.04.14 Sun 13.04.14
112 Mechanical completion / All permits returned . 0 hrs Mon 21.04.14 Mon 21.04.14
113 Disassembly 8,23 dys Tue 11.03.14 Wed 19.03.14
114 Remove enclosure panels and steel structure 38 hrs Tue 11.03.14 Thu 13.03.14
115 Install scaffolding 16 hrs Tue 11.03.14 Wed 12.03.14
116 Remove turbine insulation and CMAS CMAS 28 hrs Tue 11.03.14 Wed 12.03.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 2 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
117 Prepare for piping removal 28 hrs Tue 11.03.14 Wed 12.03.14
118 Open access doors and plugs 8 hrs Wed 12.03.14 Wed 12.03.14
119 Remove GT penetration (lances, burners, instrumentation) (, , ) 39 hrs Wed 12.03.14 Thu 13.03.14

120 Measure rotor position 5 hrs Wed 12.03.14 Wed 12.03.14


121 F_216712 CHECKING OF VIGV CLEARANCE AND F_216712 1 hr Wed 12.03.14 Wed 12.03.14
REMACHINING OF IGV INNER RING ON AN OPEN VIGV
ENGINE IGV
122 Installation of the temporary jacking oil pump 3 hrs Wed 12.03.14 Wed 12.03.14
123 Disconnect exhaust diffuser from thermal block 14 hrs Wed 12.03.14 Thu 13.03.14
124 Remove covers and open coupling 16 hrs Wed 12.03.14 Thu 13.03.14
125 Remove required piping on turbine 28 hrs Thu 13.03.14 Fri 14.03.14
126 Preparation for airintake & maincasing top removal 28 hrs Fri 14.03.14 Sat 15.03.14

127 F_217018 EGH PREVENTIVE MEASURES: ENSURE F_217018 EGH: 1 hr Fri 14.03.14 Fri 14.03.14
ID-OD SPLIT LINE CLEARENCES
128 Remove airintake & maincasing top
13 hrs Sat 15.03.14 Sun 16.03.14
129 Remove LPT vane carrier top half ( 7 hrs Sun 16.03.14 Sun 16.03.14
130 Open bearing area 10 hrs Sun 16.03.14 Sun 16.03.14
131 Remove combustion chamber top half 25 hrs Sun 16.03.14 Mon 17.03.14
132 F_219090 MEASURE TORQUE OF EV COMBUSTOR F_219090 1,3 hrs Sun 16.03.14 Sun 16.03.14
BOLTS EV
133 F_215983 LOCKING OF SPLIT LINE BOLTS F_215983 M30 1,3 hrs Sun 16.03.14 Sun 16.03.14
M30(NI80TIAL)OF EV-LINER AND FRONT PLATE WITH (NI80TIAL) EV
LOCKING DEVICE AND SECURE THEM BY WELDING.

134 Remove compressor vane carrier 2 top half 2- ( ) 7 hrs Mon 17.03.14 Mon 17.03.14
135 Remove compressor vane carrier 1 top half 1- ( ) 5 hrs Mon 17.03.14 Mon 17.03.14
136 Preparation for removal of rotor 9 hrs Mon 17.03.14 Tue 18.03.14
137 Remove Rotor 8 hrs Tue 18.03.14 Tue 18.03.14
138 Remove HPT carrier ring out of rotorstand 5 hrs Tue 18.03.14 Tue 18.03.14
139 Remove compressor vane carrier 1 bottom half 1- ( ) 4 hrs Tue 18.03.14 Tue 18.03.14
140 Remove compressor vane carrier 2 bottom half 2- ( ) 4 hrs Tue 18.03.14 Tue 18.03.14
141 Remove bearing lower parts 4 hrs Tue 18.03.14 Wed 19.03.14
142 Remove combustion chamber bottom half 5 hrs Tue 18.03.14 Wed 19.03.14
143 Remove LPT Vane Carrier Bottom Part ( ) 4 hrs Wed 19.03.14 Wed 19.03.14
144 Remove bearing #1 pedestal 1 8 hrs Wed 19.03.14 Wed 19.03.14
145 Inspection 40,11 dys Wed 12.03.14 Mon 21.04.14
146 Milestones 18,32 dys Sat 22.03.14 Wed 09.04.14
147 TVC top ready for assembly 0 dys Sat 22.03.14 Sat 22.03.14

148 CVC1 top half ready to install 0 dys Sat 22.03.14 Sat 22.03.14
149 CVC1 lower half ready to install 0 dys Sat 22.03.14 Sat 22.03.14
150 TVC lower half ready for assembly 0 hrs Mon 24.03.14 Mon 24.03.14

151 CVC2 top half ready to install 0 dys Tue 25.03.14 Tue 25.03.14
152 Maincasing Top ready for assembly 0 dys Thu 27.03.14 Thu 27.03.14
153 CC lower half ready to install 0 dys Thu 27.03.14 Thu 27.03.14
154 Maincasing bottom ready for assembly 0 hrs Fri 28.03.14 Fri 28.03.14
155 CVC2 lower half ready to install 0 dys Sat 29.03.14 Sat 29.03.14
156 CC upper half ready to install 0 dys Sun 30.03.14 Sun 30.03.14
157 Rotor ready to install 0 hrs Wed 09.04.14 Wed 09.04.14
158 TVC ( 8,27 dys Sun 16.03.14 Mon 24.03.14
159 Disassembly of TH 1,27 dys Sun 16.03.14 Mon 17.03.14
160 Remove turbine vanes row 1 1- 5 hrs Sun 16.03.14 Sun 16.03.14
161 Remove SHS A SHS A 5 hrs Sun 16.03.14 Sun 16.03.14
162 Remove turbine vanes row 2 2- 5 hrs Sun 16.03.14 Mon 17.03.14
163 Remove SHS B SHS B 4 hrs Mon 17.03.14 Mon 17.03.14
164 Remove turbine vanes row 3 3- 5 hrs Mon 17.03.14 Mon 17.03.14
165 Remove SHS C SHS C 4 hrs Mon 17.03.14 Mon 17.03.14
166 Disassembly of BH 1,27 dys Wed 19.03.14 Thu 20.03.14
167 Remove turbine vanes row 1 1- 5 hrs Wed 19.03.14 Wed 19.03.14
168 Remove SHS A SHS A 5 hrs Wed 19.03.14 Wed 19.03.14
169 Remove turbine vanes row 2 2- 5 hrs Wed 19.03.14 Thu 20.03.14
170 Remove SHS B SHS B 4 hrs Thu 20.03.14 Thu 20.03.14
171 Remove turbine vanes row 3 3- 5 hrs Thu 20.03.14 Thu 20.03.14
172 Remove SHS C SHS C 4 hrs Thu 20.03.14 Thu 20.03.14
173 Inspection / Cleaning of TVC TH / 6,14 dys Sun 16.03.14 Sat 22.03.14
174 Inspection of TVC top parts 3 hrs Sun 16.03.14 Sun 16.03.14
175 Repair of fixation pin holes (FSI_xxxxxx) equipment 13 hrs Sun 16.03.14 Mon 17.03.14
needed? (FSI_xxxxxx)?
176 Cleaning and work according inspection 18 hrs Mon 17.03.14 Mon 17.03.14
177 Inspection of LP turbine vanes and HS top HS 17 hrs Fri 21.03.14 Sat 22.03.14
178 Clean TVC TH 52 hrs Mon 17.03.14 Thu 20.03.14
179 Inspection / Cleaning of TVC BH / 3,77 dys Wed 19.03.14 Sun 23.03.14
180 Inspection of TVC bottom parts 3 hrs Wed 19.03.14 Wed 19.03.14
181 Repair of fixation pin holes (FSI_xxxxxx) equipment 13 hrs Wed 19.03.14 Thu 20.03.14
needed? (FSI_xxxxxx)?
182 Cleaning and work according inspection 18 hrs Thu 20.03.14 Thu 20.03.14
183 Clean TVC BH 52 hrs Thu 20.03.14 Sun 23.03.14
184 Inspection of LP turbine vanes and HS bottom HS 17 hrs Fri 21.03.14 Sat 22.03.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 3 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
185 F_215828 EXCHANGE OF ECCENTRIC BUSHES F_215828 ( 8 hrs Fri 21.03.14 Sat 22.03.14
(TVC) )
186 F_218820 GT26 TVC AND ROTOR ALIGNMENT. F_218820 GT26 14 hrs Sat 22.03.14 Sat 22.03.14

187 Assembly of BH 1,45 dys Sun 23.03.14 Mon 24.03.14


188 F_209185 REPLACE ENTIRE ROW OF SHS C F_209185 SHS C (HTCT151136 4 hrs Sun 23.03.14 Sun 23.03.14
(HTCT151136 R6) R6)
189 F_217947 IMPLEMANTATION OF LPT VANE 3 F_217947 3- 5 hrs Sun 23.03.14 Sun 23.03.14
ROW (HTCT156986R0001) (HTCT156986R0001)
190 F_206536 IMPLEMENTATION OF LPT SHS-B ROW F_206536 SHS B 4 hrs Sun 23.03.14 Sun 23.03.14
(HTCT155214R0001) (HTCT155214R0001)
191 F_207030 IMPLEMENTATION OF LPT VANE 2 F_207030 2- 6 hrs Sun 23.03.14 Mon 24.03.14
ROW (HTCT151121R0005) (HTCT151121R0005)
192 F_213145 IMPLEMANTATION OF LPT SHS A ROW F_213145 SHS A 8 hrs Mon 24.03.14 Mon 24.03.14
(HTCT156281R0001) (HTCT156281R0001)
193 F_216397 IMPLEMANTATION OF LPT VANE 1 F_216397 1- 5 hrs Mon 24.03.14 Mon 24.03.14
ROW (HTCT156257R0001) (HTCT156257R0001)
194 Assembly of TH 1,5 dys Thu 20.03.14 Sat 22.03.14
195 F_209185 REPLACE ENTIRE ROW OF SHS C F_209185 SHS C (HTCT151136 4 hrs Thu 20.03.14 Thu 20.03.14
(HTCT151136 R6) R6)
196 F_217947 IMPLEMANTATION OF LPT VANE 3 F_217947 3- 5 hrs Thu 20.03.14 Fri 21.03.14
ROW (HTCT156986R0001) (HTCT156986R0001)
197 F_206536 IMPLEMENTATION OF LPT SHS-B ROW F_206536 SHS B 4 hrs Fri 21.03.14 Fri 21.03.14
(HTCT155214R0001) (HTCT155214R0001)
198 F_207030 IMPLEMENTATION OF LPT VANE 2 F_207030 2- 7 hrs Fri 21.03.14 Fri 21.03.14
ROW (HTCT151121R0005) (HTCT151121R0005)
199 F_213145 IMPLEMANTATION OF LPT SHS A ROW F_213145 SHS A 8 hrs Fri 21.03.14 Sat 22.03.14
(HTCT156281R0001) (HTCT156281R0001)
200 F_216397 IMPLEMANTATION OF LPT VANE 1 F_216397 1- 5 hrs Sat 22.03.14 Sat 22.03.14
ROW (HTCT156257R0001) (HTCT156257R0001)
201 Turbine Housing / Exhaust housing , 12,18 dys Sun 16.03.14 Fri 28.03.14
202 Top half 9,59 dys Sun 16.03.14 Tue 25.03.14
203 Inspection of main casing top half 10 hrs Sun 16.03.14 Sun 16.03.14
204 F_218083 EXHAUST HOUSING - ASSEMBLY OF F_218083 28 hrs Wed 19.03.14 Thu 20.03.14
PINS THROUGH CENTERING HALF RING.
205 F_211408 REPLACING OF DAMAGED .
F_211408 28 hrs Sun 16.03.14 Mon 17.03.14
INTERMEDIATE INSULATION SEGMENTS AND
CONNECTION PARTS ON EXHAUST GAS
HOUSING ACCORDING TO THE FINDINGS. .
206 Weld repair of CMAS color and cracks top CMAS ( 28 hrs Sun 16.03.14 Mon 17.03.14
207 Weld repair of EGH according findings EGH 114 hrs Sun 16.03.14 Fri 21.03.14

208 Lapping of EV burner sealing faces on top 28 hrs Thu 20.03.14 Fri 21.03.14
209 Cleaning of grooves, splitline, etc.. , . 114 hrs Thu 20.03.14 Tue 25.03.14
210 Bottom half 9,05 dys Wed 19.03.14 Fri 28.03.14
211 Inspection of main casing bottom half 10 hrs Wed 19.03.14 Thu 20.03.14
212 Inspection of GT support, foundation, pipe supports
, , 8 hrs Thu 20.03.14 Thu 20.03.14

213 F_218083 EXHAUST HOUSING - ASSEMBLY OF F_218083 28 hrs Thu 20.03.14 Fri 21.03.14
PINS THROUGH CENTERING HALF RING.
214 F_218337 EXCHANGE OF THE SHIMSETS AT THE .
F_218337 5 hrs Thu 20.03.14 Thu 20.03.14
AXIAL KEYWAY, TURBINE END. ( )
215 F_211408 REPLACING OF DAMAGED F_211408 28 hrs Thu 20.03.14 Fri 21.03.14
INTERMEDIATE INSULATION SEGMENTS AND
CONNECTION PARTS ON EXHAUST GAS
HOUSING ACCORDING TO THE FINDINGS. .
216 Weld repair of CMAS color and cracks bottom CMAS ( 28 hrs Thu 20.03.14 Fri 21.03.14
217 Weld repair of EGH according findings EGH 114 hrs Thu 20.03.14 Tue 25.03.14

218 F_219151 IMPROVEMENTS PACKAGE LINER F_219151 65 hrs Tue 25.03.14 Fri 28.03.14
STABILIZATION
219 F_208841 INSPECTION OF GROUNDING F_208841 TB, 13 hrs Wed 19.03.14 Wed 19.03.14
CONNECTIONS ON TB, AIM AND EXH.
DIFFUSERS
220 Lapping of EV burner sealing faces on bottom 28 hrs Fri 21.03.14 Sun 23.03.14
221 Cleaning and work according inspection 114 hrs Fri 21.03.14 Thu 27.03.14
222 Combustion Chamber 12,61 dys Mon 17.03.14 Sun 30.03.14
223 Disassembly of TH 5,57 dys Mon 17.03.14 Sun 23.03.14
224 Remove SEV outer liner segments SEV 5 hrs Mon 17.03.14 Mon 17.03.14
225 Turning of CC 3 hrs Mon 17.03.14 Mon 17.03.14
226 Remove EV outer liner segments EV 6 hrs Mon 17.03.14 Tue 18.03.14
227 Remove SEV burner SEV 1,5 hrs Tue 18.03.14 Tue 18.03.14
228 Remove HPT OGV OGV 1,5 hrs Tue 18.03.14 Tue 18.03.14
229 Remove HPT vanes 3 hrs Tue 18.03.14 Tue 18.03.14
230 Remove front segments 3 hrs Tue 18.03.14 Tue 18.03.14
231 Remove front plate 3 hrs Tue 18.03.14 Tue 18.03.14
232 Remove EV inner liner segments EV 5 hrs Tue 18.03.14 Tue 18.03.14
233 Remove SEV inner liner segments SEV 8 hrs Tue 18.03.14 Wed 19.03.14
234 Turning of CC 3 hrs Sat 22.03.14 Sun 23.03.14
235 Disassembly of BH 1,7 dys Wed 19.03.14 Thu 20.03.14
236 Remove Instrumentation 1,5 hrs Wed 19.03.14 Wed 19.03.14
237 Remove SEV outer liner SEV 2 hrs Wed 19.03.14 Wed 19.03.14
238 Remove EV inner liner EV 3 hrs Wed 19.03.14 Wed 19.03.14
239 Remove SEV outer liner segments SEV 5 hrs Wed 19.03.14 Wed 19.03.14
240 Remove SEV rotor cover SEV 1 hr Wed 19.03.14 Wed 19.03.14
241 Remove SEV inner carrier ribs and pipes SEV 6 hrs Wed 19.03.14 Wed 19.03.14
242 Remove front plate 1 hr Wed 19.03.14 Wed 19.03.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 4 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
243 Remove front segments 1,5 hrs Wed 19.03.14 Wed 19.03.14
244 Remove EV inner liner segments EV 2 hrs Wed 19.03.14 Wed 19.03.14
245 Remove SEV inner liner SEV 4 hrs Wed 19.03.14 Thu 20.03.14
246 Remove SEV inner liner segments SEV 8 hrs Thu 20.03.14 Thu 20.03.14
247 Turning of EV outerliner and SEV outercarrier EV SEV 2 hrs Thu 20.03.14 Thu 20.03.14
248 Remove EV outer liner segments EV 7 hrs Thu 20.03.14 Thu 20.03.14
249 Remove SEV burner SEV 3 hrs Thu 20.03.14 Thu 20.03.14
250 Remove HPT OGV OGV 1 hr Thu 20.03.14 Thu 20.03.14
251 Remove HPT vanes 3 hrs Thu 20.03.14 Thu 20.03.14
252 Inspection / Cleaning of CC TH / 9,89 dys Mon 17.03.14 Thu 27.03.14
253 Inspection of SEV outer liner segments top SEV 4 hrs Mon 17.03.14 Tue 18.03.14
254 Inspection of EV outer liner segments top EV 4 hrs Tue 18.03.14 Tue 18.03.14
255 Inspection of SEV burners Top SEV 4 hrs Tue 18.03.14 Tue 18.03.14

256 Inspection of HPT OGV top OGV 4 hrs Tue 18.03.14 Tue 18.03.14
257 Inspection of HPT vanes top 4 hrs Tue 18.03.14 Tue 18.03.14
258 Inspection of EV carrier top EV 5 hrs Wed 19.03.14 Wed 19.03.14
259 Inspection of EV front segments top EV 4 hrs Tue 18.03.14 Tue 18.03.14
260 Inspection of EV inner liner segments top EV 4 hrs Wed 19.03.14 Wed 19.03.14
261 Inspection of SEV carrier top SEV 4 hrs Wed 19.03.14 Wed 19.03.14
262 Inspection of SEV inner liner segments top SEV 4 hrs Wed 19.03.14 Wed 19.03.14
263 Clean SEV inner liner SEV 4 hrs Wed 19.03.14 Wed 19.03.14
264 Clean SEV rotor cover SEV 4 hrs Wed 19.03.14 Wed 19.03.14
265 Clean SEV outer liner SEV 5 hrs Fri 21.03.14 Sat 22.03.14
266 Clean EV outer liner EV 6,5 hrs Sat 22.03.14 Sat 22.03.14
267 Clean front plate 4 hrs Sat 22.03.14 Sat 22.03.14
268 Clean SEV outer carrier SEV 8 hrs Sat 22.03.14 Sat 22.03.14
269 Clean EV inner liner EV 5 hrs Sat 22.03.14 Sat 22.03.14
270 Clean SEV inner carrier SEV 6 hrs Sat 22.03.14 Sun 23.03.14
271 F_215218 EXCHANGE SEV OUTER CARRIER F_215218 3 hrs Sat 22.03.14 Sat 22.03.14
SEAL RING INCLUDING PRESSING SPRINGS AND SEV,
THRUST BOLTS
272 F_215983 LOCKING OF SPLIT LINE BOLTS F_215983 M30 4 hrs Thu 27.03.14 Thu 27.03.14
M30(NI80TIAL)OF EV-LINER AND FRONT PLATE (NI80TIAL) EV
WITH LOCKING DEVICE AND SECURE THEM BY
WELDING.
273 F_219090 MEASURE TORQUE OF EV F_219090 4 hrs Tue 18.03.14 Tue 18.03.14
COMBUSTOR BOLTS EV
274 F_218723 REPLACE EV FRONT PLATE BRUSH F_218723 4 hrs Tue 18.03.14 Tue 18.03.14
SEAL BRISTLES EV
275 F_218775 REWORK OF EV FRONT SEGMENT F_218775 CPL 16 hrs Tue 18.03.14 Wed 19.03.14
COATING CPL. EV
276 F_217277 HPT VANE THRUST RING RETENTION F_217277 9 hrs Tue 18.03.14 Tue 18.03.14

277 Inspection / Cleaning of CC BH / 3,61 dys Tue 18.03.14 Sat 22.03.14
278 Inspection of SEV inner liner segments bottom SEV 4 hrs Tue 18.03.14 Tue 18.03.14
279 Inspection of SEV carrier bottom SEV 4 hrs Wed 19.03.14 Wed 19.03.14
280 Inspection of SEV outer liner segments bottom SEV 4 hrs Wed 19.03.14 Thu 20.03.14
281 Clean SEV outer liner SEV 7 hrs Wed 19.03.14 Wed 19.03.14
282 Clean SEV rotor cover SEV 4 hrs Wed 19.03.14 Thu 20.03.14
283 Clean front plate 3 hrs Thu 20.03.14 Thu 20.03.14
284 Inspection of EV front segments bottom EV 4 hrs Thu 20.03.14 Thu 20.03.14
285 Inspection of EV inner liner segments bottom EV 4 hrs Wed 19.03.14 Thu 20.03.14
286 Clean EV inner liner EV 5 hrs Thu 20.03.14 Thu 20.03.14
287 Inspection of EV carrier bottom EV 5 hrs Thu 20.03.14 Fri 21.03.14
288 Inspection of EV outer liner segments bottom EV 4 hrs Thu 20.03.14 Fri 21.03.14
289 Clean SEV inner carrier SEV 6,5 hrs Thu 20.03.14 Thu 20.03.14
290 Inspection of SEV burners Bottom SEV 4 hrs Fri 21.03.14 Fri 21.03.14

291 Inspection of HPT OGV bottom OGV 4 hrs Fri 21.03.14 Fri 21.03.14

292 Inspection of HPT vanes bottom 4 hrs Fri 21.03.14 Fri 21.03.14
293 Clean SEV inner liner SEV 5 hrs Thu 20.03.14 Fri 21.03.14
294 Clean EV outer liner EV 10 hrs Fri 21.03.14 Fri 21.03.14
295 Clean SEV outer carrier SEV 8 hrs Fri 21.03.14 Fri 21.03.14
296 F_215218 EXCHANGE SEV OUTER CARRIER F_215218 3 hrs Fri 21.03.14 Sat 22.03.14
SEAL RING INCLUDING PRESSING SPRINGS AND SEV,
THRUST BOLTS
297 F_219090 MEASURE TORQUE OF EV F_219090 4 hrs Wed 19.03.14 Wed 19.03.14
COMBUSTOR BOLTS EV
298 F_218775 REWORK OF EV FRONT SEGMENT F_218775 CPL 15 hrs Wed 19.03.14 Thu 20.03.14
COATING CPL. EV
299 F_219566 EV OUTER LINER CARRIER BYPASS F_219566 14 hrs Fri 21.03.14 Sat 22.03.14
SLOT CLOSING.
300 F_217277 HPT VANE THRUST RING RETENTION EV
F_217277 9 hrs Thu 20.03.14 Fri 21.03.14

301 Assembly of BH 6,43 dys Thu 20.03.14 Thu 27.03.14
302 Install SEV inner liner segments SEV 0,59 dys Thu 20.03.14 Fri 21.03.14
303 F_212828 EXCHANGE OF EXISTING SEV F_212828 SEV 8 hrs Thu 20.03.14 Fri 21.03.14
INNER SEGMENT ROW WITH NEW SEV INNER HTCT122628R0001
SEGMENT ROW HTCT122628R0001
304 F_212404 REPLACE COVER RING MACHINED F_212404 3 hrs Fri 21.03.14 Fri 21.03.14
WITH SAME DESIGN (HTCT105262R0005) (HTCT105262R0005)

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 5 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
305 Lock welding of SEV inner liner segments SEV 4 hrs Fri 21.03.14 Fri 21.03.14
306 Install SEV outer liner segments SEV 0,68 dys Thu 20.03.14 Fri 21.03.14
307 F_212836 EXCHANGE OF EXISTING SEV F_212836 SEV 12 hrs Thu 20.03.14 Fri 21.03.14
OUTER SEGMENT ROW WITH NEW SEV HTCT122629R0001
OUTER SEGMENT ROW HTCT122629R0001

308 Lock welding of SEV outer liner segments SEV 4 hrs Fri 21.03.14 Fri 21.03.14
309 Install SEV inner liner SEV 4 hrs Fri 21.03.14 Fri 21.03.14
310 Turning of EV outerliner and SEV outercarrier EV SEV 1,5 hrs Fri 21.03.14 Fri 21.03.14
311 Install EV inner liner segments EV 0,82 dys Fri 21.03.14 Sat 22.03.14
312 F_212829 EXCHANGE OF EXISTING EV INNER F_212829 EV 14 hrs Fri 21.03.14 Sat 22.03.14
SEGMENT ROW WITH NEW EV INNER HTCT122702R0001
SEGMENT ROW HTCT122702R0001
313 Lock welding of EV inner liner segments EV 5 hrs Sat 22.03.14 Sat 22.03.14
314 F_213587 INTRODUCTION OF NEW EV FRONT F_213587 5 hrs Sat 22.03.14 Sat 22.03.14
SEGMENTS HTCT122631R0001 WITH MODIFIED EV HTCT122631R0001
FIXATION
315 F_218788 REPLACEMENT OF THE EV FRONT F_218788 5 hrs Sat 22.03.14 Sat 22.03.14
SEGMENT HOOK HOLDERS WITH NEW DESIGN EV
(NEW HOOK HOLDER STS18/8;B=40.5MM, (STS18/8;B=40,5, NI80TIAL
NI80TIAL BOLTING M12TX70 WITH NI80TIAL M12TX70 NI80TIAL)
EXPANSION SLEEVE)AND IMPLEMENTATION OF .
NEW BOLT LOCKING DEVICE.

316 Install front plate 0,36 dys Sat 22.03.14 Sun 23.03.14
317 Install front plate 4 hrs Sat 22.03.14 Sun 23.03.14
318 Lock welding of front segments 4 hrs Sun 23.03.14 Sun 23.03.14
319 F_219092 IMPLEMENTATION OF NEW BOLT F_219092 3 hrs Sun 23.03.14 Sun 23.03.14
LOCKING DEVICE ON FRONT PLATE INNER
RADIAL BOLTING. .
320 !!F_219177 EV INNER CARRIER/EV OUTER !!F_219177 0 dys Sun 23.03.14 Sun 23.03.14
CARRIER SHIMMING EV
321 Install EV outer liner segments
EV
EV 0,77 dys Sat 22.03.14 Sun 23.03.14
322 F_212830 EXCHANGE OF EXISTING EV OUTER F_212830 EV 14 hrs Sat 22.03.14 Sun 23.03.14
SEGMENT ROW WITH NEW EV OUTER HTCT122707R0001
SEGMENT ROW HTCT122707R0001

323 Lock welding of EV outer liner segments EV 4 hrs Sun 23.03.14 Sun 23.03.14
324 Turning of EV outerliner and SEV outercarrier EV SEV 1,5 hrs Sun 23.03.14 Sun 23.03.14
325 F_219077 LOCKING OF RADIAL BOLTS M24 F_219077 M24 26 hrs Sun 23.03.14 Mon 24.03.14
BETWEEN EV OUTER CARRIER AND EV FRONT EV
PLATE EV
326 Chamfer HPT and OGV splitline vanes for assembly 1 hr Sun 23.03.14 Sun 23.03.14
OGV
327 F_216396 IMPLEMENTATION OF HPT VANE ROW F_216396 4 hrs Sun 23.03.14 Sun 23.03.14
(HTCT156571R0001) (HTCT156571R0001)
328 F_220333 REPLACEMENT OF ROTOR COOLING F_220333 4 hrs Sun 23.03.14 Sun 23.03.14
AIR FEED BUSHES IN A HPT VANE ROW

329 Install HPT OGV OGV 7 hrs Sun 23.03.14 Mon 24.03.14
330 F_212355 INSTALLATION OF SEV BURNER ROW F_212355 SEV 14 hrs Mon 24.03.14 Mon 24.03.14
HTCT121909R0001 HTCT121909R0001
331 Lift CC into assembly stand 4 hrs Mon 24.03.14 Tue 25.03.14
332 Install SEV outer liner SEV 4 hrs Tue 25.03.14 Tue 25.03.14
333 Install instrumentation, delta P tubes , 10 hrs Tue 25.03.14 Tue 25.03.14
334 F_215676 EXCHANGE OF THERMOCOUPLE F_215676 3 hrs Tue 25.03.14 Tue 25.03.14
FIXATION CLIPS AT THE COMBUSTOR AND 2,
CVC2, APPLICATION OF NEW ASSEMBLY
PROCEDURE FOR THE PRESSURE TUBES. .
335 Install SEV inner carrier SEV 0,5 dys Tue 25.03.14 Tue 25.03.14
336 Install SEV inner carrier, ribs and pipes SEV 11 hrs Tue 25.03.14 Tue 25.03.14
337 Lock welding 4 hrs Tue 25.03.14 Tue 25.03.14
338 Install EV inner liner EV 6 hrs Tue 25.03.14 Wed 26.03.14
339 Install instrumentation, thermocouples , 26 hrs Wed 26.03.14 Thu 27.03.14
340 Install SEV rotor cover SEV 1,5 hrs Wed 26.03.14 Wed 26.03.14
341 Assembly of TH 5,14 dys Mon 24.03.14 Sun 30.03.14
342 Install EV outer liner segments EV 0,95 dys Mon 24.03.14 Tue 25.03.14
343 F_212830 EXCHANGE OF EXISTING EV OUTER F_212830 EV 14 hrs Mon 24.03.14 Tue 25.03.14
SEGMENT ROW WITH NEW EV OUTER HTCT122707R0001
SEGMENT ROW HTCT122707R0001

344 Lock welding of EV outer liner segments EV 4 hrs Tue 25.03.14 Tue 25.03.14
345 F_218138 REWORK EDGE CHAMFER ON EV F_218138 4 hrs Tue 25.03.14 Tue 25.03.14
OUTER LINER UPPER HALF EV
346 Install EV inner liner segments EV 0,91 dys Tue 25.03.14 Wed 26.03.14
347 F_212829 EXCHANGE OF EXISTING EV INNER F_212829 EV 16 hrs Tue 25.03.14 Wed 26.03.14
SEGMENT ROW WITH NEW EV INNER HTCT122702R0001
SEGMENT ROW HTCT122702R0001
348 Lock welding of EV inner liner segments EV 5 hrs Wed 26.03.14 Wed 26.03.14
349 F_213587 INTRODUCTION OF NEW EV FRONT F_213587 5 hrs Wed 26.03.14 Wed 26.03.14
SEGMENTS HTCT122631R0001 WITH MODIFIED EV HTCT122631R0001
FIXATION
350 F_218788 REPLACEMENT OF THE EV FRONT F_218788 5 hrs Wed 26.03.14 Wed 26.03.14
SEGMENT HOOK HOLDERS WITH NEW DESIGN EV
(NEW HOOK HOLDER STS18/8;B=40.5MM, (STS18/8; B = 40,5, NI80TIAL
NI80TIAL BOLTING M12TX70 WITH NI80TIAL M12TX70 NI80TIAL)
EXPANSION SLEEVE)AND IMPLEMENTATION OF .
NEW BOLT LOCKING DEVICE.

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 6 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
351 Install front plate 0,55 dys Wed 26.03.14 Thu 27.03.14
352 Install front plate 5 hrs Wed 26.03.14 Thu 27.03.14
353 F_219092 IMPLEMENTATION OF NEW BOLT F_219092 3 hrs Thu 27.03.14 Thu 27.03.14
LOCKING DEVICE ON FRONT PLATE INNER
RADIAL BOLTING. .
354 Lock welding of front segments 4 hrs Thu 27.03.14 Thu 27.03.14
355 !!F_219177 EV INNER CARRIER/EV OUTER !!F_219177 0 dys Thu 27.03.14 Thu 27.03.14
CARRIER SHIMMING EV
356 Install SEV inner liner segments

EV SEV 0,82 dys Thu 27.03.14 Fri 28.03.14
357 F_212828 EXCHANGE OF EXISTING SEV F_212828 SEV 13 hrs Thu 27.03.14 Thu 27.03.14
INNER SEGMENT ROW WITH NEW SEV INNER HTCT122628R0001
SEGMENT ROW HTCT122628R0001
358 F_212404 REPLACE COVER RING MACHINED F_212404 3 hrs Thu 27.03.14 Fri 28.03.14
WITH SAME DESIGN (HTCT105262R0005) (HTCT105262R0005)

359 Lock welding of SEV inner liner segments SEV 4 hrs Fri 28.03.14 Fri 28.03.14
360 Turning of CC 3 hrs Fri 28.03.14 Fri 28.03.14
361 F_219077 LOCKING OF RADIAL BOLTS M24 F_219077 M24 26 hrs Fri 28.03.14 Sat 29.03.14
BETWEEN EV OUTER CARRIER AND EV FRONT EV
PLATE EV
362 Chamfer HPT and OGV splitline vanes for assembly 1,5 hrs Fri 28.03.14 Fri 28.03.14
OGV
363 F_216396 IMPLEMENTATION OF HPT VANE ROW F_216396 7 hrs Fri 28.03.14 Fri 28.03.14
(HTCT156571R0001) (HTCT156571R0001)
364 F_220333 REPLACEMENT OF ROTOR COOLING F_220333 7 hrs Fri 28.03.14 Fri 28.03.14
AIR FEED BUSHES IN A HPT VANE ROW

365 Install HPT OGV OGV 7 hrs Fri 28.03.14 Fri 28.03.14
366 F_212355 INSTALLATION OF SEV BURNER ROW F_212355 SEV 14 hrs Fri 28.03.14 Sat 29.03.14
HTCT121909R0001 HTCT121909R0001
367 Install SEV outer liner segments SEV 0,45 dys Sat 29.03.14 Sun 30.03.14
368 F_212836 EXCHANGE OF EXISTING SEV F_212836 SEV 8 hrs Sat 29.03.14 Sat 29.03.14
OUTER SEGMENT ROW WITH NEW SEV HTCT122629R0001
OUTER SEGMENT ROW HTCT122629R0001

369 Lock welding of SEV outer liner segments SEV 3 hrs Sat 29.03.14 Sun 30.03.14
370 Compressor stator 13,23 dys Sun 16.03.14 Sat 29.03.14
371 CVC2 2 11,86 dys Mon 17.03.14 Sat 29.03.14
372 F_216673 IMPLEMENTATION OF MBH40 F_216673 5,59 dys Thu 20.03.14 Tue 25.03.14
COOLING AIR DISTRIBUTION PIPES 2
CHIP SOLUTION - PIPES ARE MBH40
DELIVERED WITH LOOSE PISTONS.

373 Send CVC 2 top to Workshop 2 14 hrs Thu 20.03.14 Thu 20.03.14
374 Machine CVC2 2 30 hrs Thu 20.03.14 Sat 22.03.14
375 Send back to site 15 hrs Sat 22.03.14 Sat 22.03.14
376 Install CVC2 Bottom half 2 5 hrs Sun 23.03.14 Sun 23.03.14
377 Install CVC2 Top half 2 8 hrs Sun 23.03.14 Sun 23.03.14
378 F_217157 REPLACEMENT OF THE MBH40 F_217157 30 hrs Sun 23.03.14 Tue 25.03.14
COOLING AIR DISTRIBUTION PIPES - MBH40
DELIVERED WITH LOOSE PISTONS AND AN
ADDITIONAL PIECE OF PIPE!
379 Remove CVC2 top out of casing 2 8 hrs Tue 25.03.14 Tue 25.03.14
380 Remove CVC2 bottom out of casing 2 5 hrs Tue 25.03.14 Tue 25.03.14
381 Inspection / Cleaning of CVC2 TH /
9,32 dys Mon 17.03.14 Wed 26.03.14
382 Inspection of CVC2 TH 2 4 hrs Mon 17.03.14 Mon 17.03.14
383 Inspection of compressor vanes row 17 - 22 top (1722) 3 hrs Mon 17.03.14 Mon 17.03.14

384 Cleaning procedure CVC2 2 29 hrs Mon 17.03.14 Wed 19.03.14


385 NDT test of compressor vanes 17-21 top (1721) 20 hrs Wed 19.03.14 Thu 20.03.14
386 Work according inspection 29 hrs Tue 25.03.14 Wed 26.03.14
387 Inspection / Cleaning of CVC2 BH /
10,23 dys Wed 19.03.14 Sat 29.03.14
388 Inspection of CVC2 BH 2 4 hrs Wed 19.03.14 Wed 19.03.14
389 Inspection of compressor vanes row 17 - 22 (1722) 3 hrs Wed 19.03.14 Wed 19.03.14
bottom
390 Cleaning procedure CVC2 2 29 hrs Wed 19.03.14 Thu 20.03.14
391 NDT test of compressor vanes 17-21 bottom
20 hrs Thu 20.03.14 Fri 21.03.14
(1721)
392 Work according inspection 29 hrs Sun 23.03.14 Mon 24.03.14
393 F_214565 ELONGATED GROOVE IN THE SPLIT F_214565 52 hrs Tue 25.03.14 Thu 27.03.14
PLANE OF CVC2. 2.
394 F_214639 REPLACEMENT OF EXISTING CHIP F_214639 8 hrs Sat 22.03.14 Sun 23.03.14
BUSHES BY ST530-TS BUSHES ST530-TS
395 F_215676 EXCHANGE OF THERMOCOUPLE F_215676 3 hrs Thu 27.03.14 Fri 28.03.14
FIXATION CLIPS AT THE COMBUSTOR AND 2,
CVC2, APPLICATION OF NEW ASSEMBLY
PROCEDURE FOR THE PRESSURE TUBES. .

396 Replace thermocouples 29 hrs Thu 27.03.14 Sat 29.03.14


397 F_215692 EXCHANGE OF LEADOUT-STUD F_215692 4 hrs Sat 29.03.14 Sat 29.03.14
TUBE FOR CVC2 INSTRUMENTATION 2
398 CVC1 1 4,64 dys Tue 18.03.14 Sat 22.03.14
399 Inspection / Cleaning of CVC1 TH /
4,05 dys Tue 18.03.14 Sat 22.03.14
400 Inspection of CVC1 TH 1 3 hrs Tue 18.03.14 Tue 18.03.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 7 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
401 Inspection of compressor vanes row 12 - 16 top (1216) 1,5 hrs Tue 18.03.14 Tue 18.03.14

402 Cleaning and work according inspection 31 hrs Tue 18.03.14 Thu 20.03.14
403 F_214348 REWORK OF COMPRESSOR VANE F_214348 16 21 hrs Tue 18.03.14 Wed 19.03.14
16
404 F_218331 DEBURRING OF COMPRESSOR F_218331 26 hrs Thu 20.03.14 Fri 21.03.14
BLADES AND VANES AND REWORK OF ,
COMPRESSOR GROOVES AND WEDGE LIKE
INLET PHASE ON COMPRESSOR CASING AND
CVC1 1
405 NDT test of compressor vanes 12-16 top (1216) 20 hrs Fri 21.03.14 Sat 22.03.14
406 Inspection / Cleaning of CVC1 BH / 3,64 dys Wed 19.03.14 Sat 22.03.14
407 Inspection of CVC1 BH 1 3 hrs Wed 19.03.14 Wed 19.03.14
408 Inspection of compressor vanes row 12 - 16 (1216) 1,5 hrs Wed 19.03.14 Wed 19.03.14
bottom
409 Cleaning and work according inspection 31 hrs Wed 19.03.14 Thu 20.03.14
410 F_214348 REWORK OF COMPRESSOR VANE F_214348 16 21 hrs Wed 19.03.14 Thu 20.03.14
16
411 F_218331 DEBURRING OF COMPRESSOR F_218331 26 hrs Thu 20.03.14 Fri 21.03.14
BLADES AND VANES AND REWORK OF ,
COMPRESSOR GROOVES AND WEDGE LIKE
INLET PHASE ON COMPRESSOR CASING AND
CVC1 1
412 NDT test of compressor vanes 12-16 bottom 20 hrs Fri 21.03.14 Sat 22.03.14
(1216)
413 Compressor casing 13 dys Sun 16.03.14 Sat 29.03.14
414 Inspection / Cleaning of compressor / 10 dys Wed 19.03.14 Sat 29.03.14
casing BH
415 Inspection of compressor vanes row 1 - 11 bottom (111) 3 hrs Wed 19.03.14 Wed 19.03.14

416 F_216712 CHECKING OF VIGV CLEARANCE F_216712 14 hrs Wed 19.03.14 Thu 20.03.14
AND REMACHINING OF IGV INNER RING ON VIGV
AN OPEN ENGINE IGV
417 F_218345 REMOVAL OF SMEARED MATERIAL F_218345 53 hrs Wed 19.03.14 Fri 21.03.14
ON THE COMPRESSOR CASING AND ON THE .
ROTOR.
418 F_218331 DEBURRING OF COMPRESSOR F_218331 78 hrs Fri 21.03.14 Tue 25.03.14
BLADES AND VANES AND REWORK OF ,
COMPRESSOR GROOVES AND WEDGE LIKE
INLET PHASE ON COMPRESSOR CASING AND CVC1
CVC1
419 Cleaning and work according inspection 43 hrs Tue 25.03.14 Thu 27.03.14
420 NDT test of compressor VIGV, VGV1&2 and vane VIGV, VGV 33 hrs Thu 27.03.14 Fri 28.03.14
3-11 bottom 1 2 (311)
421 F_218880 INSPECTION OF INLET GUIDE VANE F_218880 10 hrs Fri 28.03.14 Sat 29.03.14
AND VANE ADJUSTMENT MECHANISM

422 Inspection / Cleaning of compressor / 12,36 dys Sun 16.03.14 Fri 28.03.14
casing TH
423 Inspection of compressor vanes row 1 - 11 top (111) 3 hrs Sun 16.03.14 Sun 16.03.14

424 F_218345 REMOVAL OF SMEARED MATERIAL F_218345 91 hrs Sun 16.03.14 Thu 20.03.14
ON THE COMPRESSOR CASING AND ON THE .
ROTOR.
425 F_218331 DEBURRING OF COMPRESSOR F_218331 78 hrs Thu 20.03.14 Mon 24.03.14
BLADES AND VANES AND REWORK OF ,
COMPRESSOR GROOVES AND WEDGE LIKE
INLET PHASE ON COMPRESSOR CASING AND CVC1
CVC1
426 Cleaning and work according inspection 43 hrs Mon 24.03.14 Wed 26.03.14
427 NDT test of compressor VIGV, VGV1&2 and vane VIGV, VGV 33 hrs Wed 26.03.14 Thu 27.03.14
3-11 top 1 2 (311)
428 F_216712 CHECKING OF VIGV CLEARANCE F_216712 14 hrs Thu 27.03.14 Fri 28.03.14
AND REMACHINING OF IGV INNER RING ON VIGV
AN OPEN ENGINE IGV
429 F_218880 INSPECTION OF INLET GUIDE VANE F_218880 10 hrs Fri 28.03.14 Fri 28.03.14
AND VANE ADJUSTMENT MECHANISM

430 Rotor 21,64 dys Tue 18.03.14 Wed 09.04.14
431 Disassembly of LP & HP turbine blading 4,23 dys Tue 18.03.14 Sun 23.03.14

432 Remove turbine blades row 1 and RHS A 1- RHS A 14 hrs Tue 18.03.14 Wed 19.03.14
433 Remove turbine blades row 2 and RHS B 2- RHS B 8 hrs Wed 19.03.14 Wed 19.03.14
434 Remove turbine blades row 3 3- 14 hrs Wed 19.03.14 Thu 20.03.14
435 Remove turbine blades row 4 and RHS C 4- RHS C 11 hrs Thu 20.03.14 Thu 20.03.14
436 Remove HPT blades 8 hrs Thu 20.03.14 Fri 21.03.14
437 Remove turbine HPT SHS HPT SHS 14 hrs Sat 22.03.14 Sun 23.03.14
438 Inspection / Cleaning of rotor / 21,64 dys Tue 18.03.14 Wed 09.04.14
439 Cleaning of rotor 111 hrs Tue 18.03.14 Sun 23.03.14
440 F_218331 DEBURRING OF COMPRESSOR F_218331 182 hrs Fri 21.03.14 Sat 29.03.14
BLADES AND VANES AND REWORK OF ,
COMPRESSOR GROOVES AND WEDGE LIKE
INLET PHASE ON COMPRESSOR CASING AND
CVC1 1
441 NDT test of compressor blades 143 hrs Sat 29.03.14 Sat 05.04.14
442 F_218345 REMOVAL OF SMEARED MATERIAL ON F_218345 91 hrs Sat 05.04.14 Wed 09.04.14
THE COMPRESSOR CASING AND ON THE .
ROTOR.
443 Retap balancing holes 14 hrs Tue 18.03.14 Wed 19.03.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 8 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
444 F_218343 REWORK OF SMEARED BALANCING F_218343 31 hrs Wed 19.03.14 Thu 20.03.14
HOLES
445 Inspection of rotor 20 hrs Tue 18.03.14 Thu 20.03.14
446 Inspection of compressor blades row 1 - 22 (122) 16 hrs Thu 20.03.14 Fri 21.03.14
447 Inspection of compressor heat shield segments row (1722) 3 hrs Fri 21.03.14 Fri 21.03.14
17-22
448 Inspection of HPT heat shield segments 5 hrs Fri 21.03.14 Sat 22.03.14
449 Clean LP & HP turbine fir tree grooves 34 hrs Fri 21.03.14 Sat 22.03.14
450 F_217701 DIMENSIONAL CHECK OF HP-ROTOR- F_217701 8 hrs Sat 22.03.14 Sun 23.03.14
DIAMETERS.
451 Inspection of LP turbine blades 29 hrs Fri 21.03.14 Sun 23.03.14
452 Inspection of HP turbine blades 9 hrs Fri 21.03.14 Fri 21.03.14
453 Inspection of LP turbine rotor heat shield segments 7 hrs Sun 23.03.14 Sun 23.03.14

454 Cleaning of HPT ring 10 hrs Sun 23.03.14 Sun 23.03.14
455 F_218909 REWORK OF HPT RING 6 O CLOCK F_218909 10 hrs Sun 23.03.14 Sun 23.03.14
FIXING LUG 6
456 Reassembly of LP & HP turbine blades 2,64 dys
Sat 05.04.14 Mon 07.04.14
457 F_217056 EXCHANGE OF EXISTING HPT HEAT F_217056 29 hrs Sat 05.04.14 Sun 06.04.14
SHIELD ROW. (HTCT151333R0006) (HTCT151333R0006)
458 Install RHS C RHS C 14 hrs Sat 05.04.14 Sat 05.04.14
459 Install turbine blades row 4 4- 14 hrs Sat 05.04.14 Sat 05.04.14
460 F_215625 IMPLEMENTATION OF LPT BLADE 3 F_215625 3- 14 hrs Sat 05.04.14 Sun 06.04.14
ROW (HTCT152892R0006) (HTCT152892R0006)
461 F_216398 IMPLEMENTATION OF LPT BLADE 2 F_216398 2- 10 hrs Sun 06.04.14 Sun 06.04.14
ROW (HTCT156200R0002) (HTCT156200R0002)
462 Install RHS B RHS B 10 hrs Sun 06.04.14 Sun 06.04.14
463 F_214751 IMPLEMENTATION OF LPT BLADE 1 F_214751 1- 10 hrs Sun 06.04.14 Mon 07.04.14
ROW (HTCT156717R0001) (HTCT156717R0001)
464 Install RHS A RHS A 10 hrs Sun 06.04.14 Mon 07.04.14
465 F_217802 IMPLEMENTATION OF HPT BLADE F_217802 10 hrs Mon 07.04.14 Mon 07.04.14
ROW (HTCT156963R0001) (HTCT156963R0001)
466 Dummy rows 0,41 dys Fri 21.03.14 Fri 21.03.14
467 F_214399 SHORTENED WELDING SEAM FOR F_214399 9 hrs Fri 21.03.14 Fri 21.03.14
DUMMY ROW LOCKING PIECE
468 Additional modules 40,11 dys Wed 12.03.14 Mon 21.04.14
469 HP & LP OTC 40,11 dys Wed 12.03.14 Mon 21.04.14
470 Install scaffolding 14 hrs Wed 12.03.14 Wed 12.03.14
471 Open inspection holes 5 hrs Wed 12.03.14 Wed 12.03.14
472 Open OTC preservation holes 1 dy Wed 12.03.14 Thu 13.03.14
473 Inspection of the OTCs 5 hrs Thu 13.03.14 Thu 13.03.14

474 Close inspection holes 10 hrs Thu 13.03.14 Thu 13.03.14


475 Connect dryers 1,5 dys Thu 13.03.14 Sat 15.03.14
476 Normalize system 1,5 dys Sat 19.04.14 Sun 20.04.14
477 Remove scaffolding 10 hrs Sun 20.04.14 Mon 21.04.14
478 Compressor Air Intake / Manifold / , 11,05 dys Wed 12.03.14 Sun 23.03.14
Filterhouse
479 Inspection of air intake system 5 hrs Wed 12.03.14 Wed 12.03.14
480 Cleaning of air intake housing 31 hrs Wed 19.03.14 Thu 20.03.14
481 F_216332 INSTALLATION OF PRESSURE F_216332 86 hrs Wed 19.03.14 Sun 23.03.14
MEASUREMENT SENSING LINES
482 F_208841 INSPECTION OF GROUNDING F_208841 TB, 6,5 hrs Wed 19.03.14 Wed 19.03.14
CONNECTIONS ON TB, AIM AND EXH.
DIFFUSERS
483 MBH cooling air system MBH 33,47 dys Wed 12.03.14 Mon 14.04.14
484 Inspection of MBH50, MBH55, MBH60 fan MBH50, MBH55, MBH60 4 hrs Wed 12.03.14 Wed 12.03.14
485 Inspection of BOV 8 hrs Wed 19.03.14 Wed 19.03.14
486 F_213031 GASKET REPLACEMENT MBH40 F_213031 MBH40 BR023, 024, 025, 3 ehrs Mon 14.04.14 Mon 14.04.14
BR023,024,025,027 027
487 Diffuser 1 and 2 1 2 16,73 dys Wed 12.03.14 Sat 29.03.14
488 Inspection of exhaust diffuser 1 and 2 1 2 8 hrs Wed 12.03.14 Thu 13.03.14
489 Weld repair according inspection 9 edys Wed 19.03.14 Fri 28.03.14
490 Cleaning of diffusor 1 and 2 1 2 13 hrs Fri 28.03.14 Fri 28.03.14
491 F_208767 REPLACEMENT OF TAT2 PROBES AND F_208767 TAT2 57 hrs Wed 19.03.14 Fri 21.03.14
CENTERING SLEEVS
492 F_217596 INSTALLATION OF LUBE OIL F_217596 57 hrs Fri 21.03.14 Mon 24.03.14
PRESSURE MEASUREMENT SENSING LINE
493 F_218802 MERCEDES STAR STRUT - DISRUPTED F_218802 MERCEDES 104 hrs Mon 24.03.14 Sat 29.03.14
INSTRUMENT CABLING
494 EV / SEV FDS (burners, lances, EV / SEV FDS (, , ) 37,88 dys Fri 14.03.14 Mon 21.04.14
instrumentation)
495 Inspection of flame eye tube 3 hrs Fri 14.03.14 Fri 14.03.14
496 Inspection of igniter 1,5 hrs Fri 14.03.14 Fri 14.03.14
497 Cleaning and prepare for reassembly 1,5 dys Wed 19.03.14 Thu 20.03.14
498 Inspection of EV burners EV 13 hrs Wed 19.03.14 Thu 20.03.14
499 Inspection of EV lances EV 10 hrs Wed 19.03.14 Thu 20.03.14
500 Inspection of SEV lances SEV 13 hrs Wed 19.03.14 Thu 20.03.14
501 Weld repair of EV burners EV 7 hrs Thu 20.03.14 Thu 20.03.14
502 Lapping of EV burners EV 29 hrs Thu 20.03.14 Sat 22.03.14
503 F_215465 EXCHANGE OF SEV LANCE TAT1 F_215465 SEV TAT1 52 hrs Thu 20.03.14 Sat 22.03.14
THERMOCOUPLE AND THERMOCOUPLE
PROTECTIVE SLEEVE

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 9 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
504 F_218660 REPLACEMENT OF STANDARD FAMILY F_218660 , 3 hrs Sun 20.04.14 Sun 20.04.14
PULSATION PROBE (HTCT105580R0261) WHICH SEV,
PROTRUDE INTO SEV-COMBUSTOR WITH (HTCT105580R0261) (HTCT120997R0261).
(HTCT120997R0261).

505 F_218659 REPLACEMENT OF STANDARD FAMILY F_218659 , 3 hrs Sun 20.04.14 Mon 21.04.14
PULSATION PROBE (HTCT105580R0262)WHICH SEV
PROTRUDE INTO EV-COMBUSTOR. ASSEMBLE (HTCT105580R0262).
SPARE IMPROVED FAMILY PULSATION PROBE (HTCT120997R0262)
(HTCT120997R0262)

506 F_220214 INSPECTION AND REWORK OF F_220214 18 hrs Wed 19.03.14 Thu 20.03.14
CONTROL AIR CLAMPS AT EV/SEV FDS EV/SEV FDS
507 F_215191 DISASSEMBLY OF THE STAGE 1 F_215191 1- 62 hrs Thu 20.03.14 Sun 23.03.14
SECTION HARDWARE FROM EV FDS EV FDS
508 Bearing pedestal, journal & thrust bearing . 6,77 dys Wed 19.03.14 Wed 26.03.14

509 Inspection of bearings 9 hrs Wed 19.03.14 Wed 19.03.14


510 Cleaning bearing parts 43 hrs Wed 19.03.14 Sun 23.03.14
511 NDT check of thrust and journal bearings 14 hrs Sun 23.03.14 Mon 24.03.14
512 Measurements on journal bearings 14 hrs Mon 24.03.14 Tue 25.03.14
513 F_214243 REPLACEMENT OF THE TWO LOCKING F_214243 3 hrs Sun 23.03.14 Sun 23.03.14
BOLTS ON THE BEARING HOUSING TS TS

514 F_219325 TC CABLING OPTIMIZATION BEARING F_219325 TC 10 hrs Tue 25.03.14 Wed 26.03.14
AREAS
515 Insulation and CMAS CMAS 8,59 dys Wed 19.03.14 Thu 27.03.14
516 Inspection of insulation and CMAS CMAS 7 hrs Wed 19.03.14 Wed 19.03.14
517 Repair insulation and CMAS according inspection CMAS 182 hrs Wed 19.03.14 Thu 27.03.14

518 F_215632 ARNOLD INSULATION: EXCHANGE OF F_215632 ARNOLD: CMAS 26 hrs Wed 19.03.14 Thu 20.03.14
CMAS CLIPS
519 GT- Fuel system / Permanent strainers : , 8 dys Wed 19.03.14 Thu 27.03.14

520 Remove permanent strainers 10 hrs Wed 19.03.14 Wed 19.03.14
521 Inspect permanent strainers 1,5 hrs Wed 19.03.14 Wed 19.03.14
522 Cleaning of permanent strainers 1,5 hrs Wed 19.03.14 Wed 19.03.14
523 Inspection of fuel gas filter and strainer 3 hrs Thu 20.03.14 Thu 20.03.14
524 Install permanent strainers 14 hrs Thu 20.03.14 Fri 21.03.14
525 F_217507 RE-WIRING OF FUEL GAS F_217507 10 hrs Wed 19.03.14 Wed 19.03.14
TEMPERATURE SIGNALS MBP41/42/43CT002 IN ( MBP41/42/43CT002)
CV-BLOCK JUNCTION BOX MBX01GD010 CV MBX01GD010
526 F_218444 REPAIR OF MBP05CF FUEL GAS F_218444 52 hrs Wed 19.03.14 Sat 22.03.14
FLOWMETER PAINT MBP05CF
527 F_208440 EXCHANGE OF GAS VALVE SEALS, F_208440 , 8 edys Wed 19.03.14 Thu 27.03.14
INSPECTION OF GAS VALVES AND LEAKAGE
TEST
528 Oil system 2,23 dys Wed 19.03.14 Fri 21.03.14
529 F_214959 ROTOR BARRING TURNING GEAR F_214959 14 hrs Wed 19.03.14 Thu 20.03.14
OVERHAUL.
530 F_220009 REMOVE PROTECTION PLATE F_220009 4 hrs Thu 20.03.14 Thu 20.03.14
531 F_218963 RETARDED 2003 HYDRAULIC TRIP F_218963 10 hrs Thu 20.03.14 Thu 20.03.14
2003
532 F_219973 REPLACE SM-RI FLOWMETER OIL F_219973 SM-RI 5 hrs Thu 20.03.14 Thu 20.03.14
PUMP
533 F_219341 INSTALLATION OF PLUG AT LUBE OIL F_219341 3 hrs Thu 20.03.14 Fri 21.03.14
FILTER DRAIN VALVE OUTLET
534 F_214577 REPLACEMENT OF PLASTIC HOSES F_214577 13 hrs Fri 21.03.14 Fri 21.03.14
WITH METAL HOSES ON OIL VAPOR FANS

535 F_216700 CC AND TVC SHIFTING DEVICE - F_216700 CC 2,59 dys Wed 19.03.14 Fri 21.03.14
INCREASE CLEARANCE BETWEEN OUTER
CASING AND SHIFTING DEVICE BY 0.2MM.
2.
536 Send shifting devices to workshop 14 hrs Wed 19.03.14 Thu 20.03.14
537 Machine shifting devices 29 hrs Thu 20.03.14 Fri 21.03.14
538 Send shifting devices back to site 14 hrs Fri 21.03.14 Fri 21.03.14
539 Assembly 14,43 dys Mon 07.04.14 Mon 21.04.14
540 Start assembly 0 hrs Mon 07.04.14 Mon 07.04.14
541 Install bearing #1 pedestal 1 6,5 hrs Mon 07.04.14 Mon 07.04.14
542 Install LPT vane carrier bottom half ( ) 8 hrs Mon 07.04.14 Mon 07.04.14
543 Install combustion chamber bottom half 8 hrs Mon 07.04.14 Tue 08.04.14
544 Install compressor vane carrier 2 bottom half 2- ( ) 8 hrs Tue 08.04.14 Tue 08.04.14
545 Install thermocouples and pressure lines 5 hrs Tue 08.04.14 Tue 08.04.14
546 Install compressor vane carrier 1 bottom half 1- ( ) 5 hrs Tue 08.04.14 Wed 09.04.14
547 Prepare for install the rotor 10 hrs Wed 09.04.14 Wed 09.04.14
548 Install HPT carrier ring 8 hrs Wed 09.04.14 Wed 09.04.14
549 Install rotor 8 hrs Wed 09.04.14 Wed 09.04.14
550 Close bearing area 13 hrs Wed 09.04.14 Thu 10.04.14
551 Measurements after reinstallation of rotor 10 hrs Wed 09.04.14 Thu 10.04.14
552 Install compressor vane carrier 1 top half 1- ( ) 8 hrs Thu 10.04.14 Thu 10.04.14
553 Install SEV CC SEV 29 hrs Thu 10.04.14 Fri 11.04.14
554 Install compressor vane carrier 2 top half 2- ( ) 14 hrs Thu 10.04.14 Fri 11.04.14
555 Install EV CC EV 29 hrs Fri 11.04.14 Sat 12.04.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 10 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
556 F_215983 LOCKING OF SPLIT LINE BOLTS F_215983 M30 4 hrs Sat 12.04.14 Sat 12.04.14
M30(NI80TIAL)OF EV-LINER AND FRONT PLATE WITH (NI80TIAL) EV
LOCKING DEVICE AND SECURE THEM BY WELDING.

557 Install LPT vane carrier top half ( 6,5 hrs Sat 12.04.14 Sun 13.04.14
558 Prepare installation of top half housings 8 hrs Sun 13.04.14 Sun 13.04.14
559 F_219703 IMPLEMENTATION OF A SEALING PASTE ON F_219703 18 hrs Sat 12.04.14 Sun 13.04.14
THE SPLIT LINE FLANGE OF COMPRESSOR,TURBINE ,
AND EXHAUST CASING. .
560 Install instrumentation bearing 4 hrs Sun 13.04.14 Sun 13.04.14
561 Install top half housings 8 hrs Sun 13.04.14 Sun 13.04.14
562 F_217018 EGH PREVENTIVE MEASURES: ENSURE F_217018 EGH: 1 hr Sun 13.04.14 Sun 13.04.14
ID-OD SPLIT LINE CLEARENCES
563 Install air intake housing
3,9 hrs Sun 13.04.14 Sun 13.04.14
564 Normalize GT housings 14 hrs Sun 13.04.14 Mon 14.04.14
565 Couple exhaust diffuser to thermal block 28,6 hrs Mon 14.04.14 Tue 15.04.14
566 Install cooling air piping & strainers 52 hrs Mon 14.04.14 Wed 16.04.14
567 Install all penetrations 44 hrs Mon 14.04.14 Wed 16.04.14
568 F_212812 REPLACEMENT OF THE EXISTING SEV F_212812 SEV 29 hrs Mon 14.04.14 Tue 15.04.14
LANCES WITH SEV LANCES HTCT121569R0001. SEV HTCT121569R0001.
569 Install EV Burner F_219410 INSTALLATION OF THE EV F_219410 29 hrs Mon 14.04.14 Tue 15.04.14
EV17IE BURNER HTCT124323R0501 EV17IE HTCT124323R0501
570 Leakage test pressure sensing lines 5 hrs Mon 14.04.14 Mon 14.04.14
571 Install Turbine insulation and CMAS CMAS 96 hrs Mon 14.04.14 Fri 18.04.14
572 Install EV lances EV 14 hrs Tue 15.04.14 Wed 16.04.14
573 Install EV- and SEV FDS and all related tubing FDS EV SEV, 98 hrs Wed 16.04.14 Mon 21.04.14
574 Install access panel and normalize air intake manifold 10 hrs Wed 16.04.14 Thu 17.04.14

575 F_213892 SECURE OF BOLTS AT THE AIM SPLIT LINE F_213892 AIM 52 hrs Wed 16.04.14 Fri 18.04.14
FLANGES AND DOOR
576 Measure radial rotor position on 7 planes and realign 7 26 hrs Wed 16.04.14 Fri 18.04.14

577 Install enclosure panels and steel structure 57 hrs Wed 16.04.14 Sat 19.04.14
578 Measurements on coupling and realigning of rotor alignment 39 hrs Fri 18.04.14 Sat 19.04.14

579 Close & thigthen coupling , 13 hrs Sat 19.04.14 Sun 20.04.14
580 Install coupling cover 8 hrs Sun 20.04.14 Sun 20.04.14
581 Removal of the temporary jacking oil pump 3 hrs Sun 20.04.14 Sun 20.04.14
582 Install instrumentation 3 hrs Sun 20.04.14 Sun 20.04.14
583 Remove scaffolding 13 hrs Mon 21.04.14 Mon 21.04.14
584 Test of ignition torch 5 hrs Mon 21.04.14 Mon 21.04.14
585 Final works 14 hrs Mon 21.04.14 Mon 21.04.14
586 GT mechanically complete 0 dys Mon 21.04.14 Mon 21.04.14
587 Cold Commissioning 20,75 dys Tue 01.04.14 Mon 21.04.14
588 Part recommissioning (Alstom) (Alstom) 4,5 dys Tue 01.04.14 Sat 05.04.14
589 Part recommissioning start 0 dys Tue 01.04.14 Tue 01.04.14
590 Temperature Transmitters calibration / checks 4,5 edys Tue 01.04.14 Sat 05.04.14
591 Pressure Transmitters / Switches calibration / checks 3,5 edys Wed 02.04.14 Sat 05.04.14

592 Drives (Air driven / Motor operated) ( , ) 1,5 edys Fri 04.04.14 Sat 05.04.14
593 Part Recommissioning finished 0 dys Sat 05.04.14 Sat 05.04.14
594 Control Modifications 2,68 dys Tue 01.04.14 Fri 04.04.14
595 Start Control works 0 hrs Tue 01.04.14 Tue 01.04.14
596 Implement prepared controll modification FSIs 30 hrs Tue 01.04.14 Fri 04.04.14
597 Control works completed 0 hrs Fri 04.04.14 Fri 04.04.14
598 Commissioning FSI's FSI 2,73 dys Sat 05.04.14 Tue 08.04.14
599 Start Commissioning FSI's FSI 0 hrs Sat 05.04.14 Sat 05.04.14
600 F_218115 PROFIBUS CABLE SHIELDING F_218115 2 hrs Sat 05.04.14 Sat 05.04.14
CONNECTIONS OF ABB PRESSURE TRANSMITTERS ABB ITABAR
FOR ITABAR APPLICATIONS
601 F_213323 EXCHANGE OF ANGLE TRANSMITTERS F_213323 V(I)GV 33 hrs Sat 05.04.14 Mon 07.04.14
ON THE V(I)GV AND APPROPRIATE SIGNAL
REPEATERS
602 F_215678 ADJUSTMENT OF THE V(I)GV F_215678 V(I)GV 24 hrs Mon 07.04.14 Tue 08.04.14
TRANSMITTERS TO THE EXTENDED RANGES
603 Commissioning FSI's comleted FSI 0 dys Tue 08.04.14 Tue 08.04.14
604 Other Systems recommissioning (Project 2,5 dys Tue 08.04.14 Thu 10.04.14
specific tasks performed by ALSTOM) ( ,
ALSTOM)
605 Start 0 dys Tue 08.04.14 Tue 08.04.14
606 Power Aumentation System Function 7 hrs Tue 08.04.14 Tue 08.04.14
607 Anti Icing System Function 2 hrs Tue 08.04.14 Wed 09.04.14
608 Compressor Wash System Function 3 hrs Wed 09.04.14 Wed 09.04.14
609 Filter House Flaps Function 11 hrs Wed 09.04.14 Thu 10.04.14
610 Fuel Oil / Nox Water Supply System Function , 6 hrs Thu 10.04.14 Thu 10.04.14
611 Control Air System Function 3 hrs Thu 10.04.14 Thu 10.04.14
612 Finished 0 dys Thu 10.04.14 Thu 10.04.14
613 Systems commissioning 6,8 dys Thu 10.04.14 Thu 17.04.14
614 Auxilliary systems 80 hrs Thu 10.04.14 Mon 14.04.14
615 Thermal block systems 100 hrs Sun 13.04.14 Thu 17.04.14
616 Commissioning instrumentation 4,09 dys Mon 14.04.14 Fri 18.04.14
617 Commissioning instrumentation 90 hrs Mon 14.04.14 Fri 18.04.14
618 Protection test 0,27 dys Fri 18.04.14 Sat 19.04.14
Task Rolled Up Task Split Inactive Milestone Duration-only Start-only
Issued: M.Floric Page 11 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
619 Protection tests 6 hrs Fri 18.04.14 Sat 19.04.14
620 Ancillary Systems (Client) () 0 dys Mon 21.04.14 Mon 21.04.14
621 Fire fighting / gas detection system ready 0 dys Mon 21.04.14 Mon 21.04.14
622 Preparation for startup 0,27 dys Mon 21.04.14 Mon 21.04.14
623 Final checks and preparation for motoroll 6 hrs Mon 21.04.14 Mon 21.04.14
624 All permits canceled 0 dys Mon 21.04.14 Mon 21.04.14
625 GT Generator WY23Z B-Inspection B WY23Z 29,18 dys Tue 11.03.14 Wed 09.04.14
(1Shift/6Days/10Hours) (1 10 6 )
626 Outage milestones 29,18 dys Tue 11.03.14 Wed 09.04.14
627 Work permit issued 0 dys Tue 11.03.14 Tue 11.03.14
628 GT cooled down 0 dys Wed 12.03.14 Wed 12.03.14
629 Gen. ready for turning gear / rotor barring 0 hrs Tue 08.04.14 Tue 08.04.14
630 Ready for motorroll / start up 0 hrs Tue 08.04.14 Tue 08.04.14
631 End of Inspection 0 dys Wed 09.04.14 Wed 09.04.14
632 F_209543 Generator offline B-inspecton F_209543 B 29,18 dys Tue 11.03.14 Wed 09.04.14
633 Disassemby 6,14 dys Tue 11.03.14 Mon 17.03.14
634 Dismantle acoustical enclosure 13 hrs Tue 11.03.14 Wed 12.03.14
635 Disconnect instrumentation 5 hrs Wed 12.03.14 Thu 13.03.14
636 Remove shaft seal & outer endshield 12 hrs Thu 13.03.14 Fri 14.03.14
637 Remove inner shield & diffuser 13 hrs Fri 14.03.14 Sat 15.03.14
638 Disconnect flexible links 5 hrs Fri 14.03.14 Fri 14.03.14
639 Remove shaft seal & bearing cover 8 hrs Sat 15.03.14 Sat 15.03.14
640 Remove bearing shells 10 hrs Sat 15.03.14 Mon 17.03.14
641 Inspection 13,95 dys Mon 17.03.14 Mon 31.03.14
642 F_210110 Generator diagnostic F_210110 11 dys Mon 17.03.14 Fri 28.03.14
643 Visual inspection 2,68 dys Mon 17.03.14 Thu 20.03.14
644 Stator 18 hrs Mon 17.03.14 Wed 19.03.14
645 Rotor 5 hrs Wed 19.03.14 Thu 20.03.14
646 DIRIS measurements DIRIS 4,41 dys Thu 20.03.14 Mon 24.03.14
647 Install robotic equipment 5 hrs Thu 20.03.14 Thu 20.03.14
648 Stator slot wedge assessment and visual 13 hrs Thu 20.03.14 Fri 21.03.14
inspection of stator bore area
649 Check of shaft insulation quality 3 hrs Fri 21.03.14 Sat 22.03.14
650 Low flux iron core test 13 hrs Sat 22.03.14 Mon 24.03.14
651 Removal of robotic equipment 5 hrs Mon 24.03.14 Mon 24.03.14
652 Electrical tests 1,27 dys Tue 25.03.14 Wed 26.03.14
653 Install test equipment 3 hrs Tue 25.03.14 Tue 25.03.14
654 DC charging and leakage current measurement 5 hrs Tue 25.03.14 Tue 25.03.14

655 DC high voltage test (. ) 5 hrs Tue 25.03.14 Wed 26.03.14


656 Removal of test equipment 3 hrs Wed 26.03.14 Wed 26.03.14
657 Analysis of measuring data and reporting 1 dy Wed 26.03.14 Fri 28.03.14
658 Retighten the foundation bolts 8 hrs Wed 26.03.14 Thu 27.03.14
659 Inspection of bearing 13 hrs Mon 17.03.14 Wed 19.03.14
660 Inspect stator & casing 10 hrs Wed 26.03.14 Thu 27.03.14
661 Inspect rotor 5 hrs Thu 27.03.14 Fri 28.03.14
662 Inspect air coolers 10 hrs Wed 19.03.14 Thu 20.03.14
663 Brush gear / exciter , 5 hrs Thu 20.03.14 Thu 20.03.14
664 Shaft grounding 5 hrs Thu 20.03.14 Fri 21.03.14
665 Clean all components 16 hrs Mon 17.03.14 Wed 19.03.14
666 Minor repair works 16 hrs Wed 19.03.14 Thu 20.03.14
667 Retightening of the stator end windings 31 hrs Wed 26.03.14 Sat 29.03.14
668 Clean stator end windings 10 hrs Sat 29.03.14 Mon 31.03.14
669 Assembly 12,36 dys Fri 28.03.14 Wed 09.04.14
670 Install flexible links 7 hrs Fri 28.03.14 Fri 28.03.14
671 Install inner shields & diffuser 16 hrs Mon 31.03.14 Wed 02.04.14
672 Install outer endshield & shaft seal 16 hrs Wed 02.04.14 Thu 03.04.14
673 Install bearing shells & connect 13 hrs Thu 03.04.14 Sat 05.04.14
674 Install bearing cover & shaft seal 16 hrs Sat 05.04.14 Mon 07.04.14
675 Connect instrumentation 5 hrs Mon 07.04.14 Tue 08.04.14
676 Install acoustical enclosure 16 hrs Tue 08.04.14 Wed 09.04.14
677 Final task 10 hrs Tue 08.04.14 Wed 09.04.14
678 ST B-Inspection (Multi shaft / acc. B 29,41 dys Tue 11.03.14 Wed 09.04.14
Recommendation HTCZ658611) ( , . . HTCZ658611)
(1Shift/6Days/10Hours) (1 10 6 )
679 Outage milestones 28,09 dys Tue 11.03.14 Tue 08.04.14
680 Projekt start / unit shut down , 0 dys Tue 11.03.14 Tue 11.03.14
681 Steamturbine start of work 0 dys Fri 14.03.14 Fri 14.03.14
682 Mechanical work complete 0 dys Mon 07.04.14 Mon 07.04.14
683 Steamturbine ready for turning gear/ rotor barring 0 dys Mon 07.04.14 Mon 07.04.14

684 Steamturbine ready for start-up 0 dys Tue 08.04.14 Tue 08.04.14
685 Steamturbine inspection 29,14 dys Tue 11.03.14 Wed 09.04.14
686 Scaffolding / instrumentation / insulation , , 29,14 dys Tue 11.03.14 Wed 09.04.14

687 Install scaffolding 20 hrs Tue 11.03.14 Wed 12.03.14


688 Remove instrumentation 20 hrs Tue 11.03.14 Wed 12.03.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 12 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
689 Remove insulation 13 hrs Tue 11.03.14 Wed 12.03.14
690 Install insulation 26 hrs Sat 05.04.14 Wed 09.04.14
691 Install instrumentation 20 hrs Thu 03.04.14 Sat 05.04.14
692 Remove scafolding 13 hrs Sat 05.04.14 Mon 07.04.14
693 Steamturbine inspection mecanical work 24,05 dys Fri 14.03.14 Mon 07.04.14
694 Cross over piping IP / LP (if necessary) 24,05 dys Fri 14.03.14 Mon 07.04.14
( )
695 Disassemble cross over pipe 9 hrs Fri 14.03.14 Sat 15.03.14
696 Scaffolding 4 hrs Sat 15.03.14 Sat 15.03.14
697 Inspection and cleaning of all parts 10 hrs Sat 15.03.14 Mon 17.03.14
698 Scaffolding 4 hrs Sat 05.04.14 Sat 05.04.14
699 Assembly cross over pipe 9 hrs Sat 05.04.14 Mon 07.04.14
700 HP turbine 6,18 dys Fri 14.03.14 Thu 20.03.14
701 Open the boroscope openings 4 hrs Fri 14.03.14 Fri 14.03.14
702 Boroscope check HP blades 13 hrs Tue 18.03.14 Thu 20.03.14
703 General checks 4 hrs Thu 20.03.14 Thu 20.03.14
704 Close the boroscope openings 4 hrs Thu 20.03.14 Thu 20.03.14
705 IP turbine 7,18 dys Sat 15.03.14 Sat 22.03.14
706 Open boroscope openings 7 hrs Sat 15.03.14 Sat 15.03.14
707 Boroscope check IP 10 hrs Thu 20.03.14 Fri 21.03.14
708 General checks 4 hrs Fri 21.03.14 Fri 21.03.14
709 Close the boroscope openings 8 hrs Fri 21.03.14 Sat 22.03.14
710 LP turbine 16,09 dys Sat 15.03.14 Mon 31.03.14
711 Arrange for boroscope check 7 hrs Sat 15.03.14 Mon 17.03.14
712 Boroscope check LP blades 16 hrs Fri 21.03.14 Sat 22.03.14
713 Check visual LP blades, last row (rotating blade) ( 5 hrs Sat 22.03.14 Mon 24.03.14
714 General checks 4 hrs Mon 24.03.14 Mon 24.03.14
715 Close the boroscope openings 10 hrs Mon 24.03.14 Tue 25.03.14
716 Inspection of Vacuum breaking valve 26 hrs Tue 25.03.14 Fri 28.03.14
717 Inspection of Water injection valve 26 hrs Fri 28.03.14 Mon 31.03.14
718 Front bearing pedestal 14,18 dys Fri 14.03.14 Fri 28.03.14
719 Open bearing pedestal 7 hrs Fri 14.03.14 Sat 15.03.14
720 Remove Lube oil pump 4 hrs Sat 15.03.14 Sat 15.03.14
721 Remove bearings 8 hrs Mon 24.03.14 Tue 25.03.14
722 Inspection 8 hrs Tue 25.03.14 Tue 25.03.14
723 F_215038 Replave Radial Key F_215038 13 hrs Tue 25.03.14 Wed 26.03.14
724 F_219255 Lube oil Inlet piping, check Straub Couplings F_219255 , 7 hrs Tue 25.03.14 Tue 25.03.14
Straub
725 Cleaning and minor repair 8 hrs Tue 25.03.14 Wed 26.03.14
726 Install bearings 8 hrs Wed 26.03.14 Thu 27.03.14
727 Instal Lube oil pump 7 hrs Thu 27.03.14 Fri 28.03.14
728 Assembly, close bearing pedestal , 8 hrs Fri 28.03.14 Fri 28.03.14
729 Axial bearing pedestal (HP / IP) (, ) 17,18 dys Sat 15.03.14 Tue 01.04.14
730 Open bearing pedestal 10 hrs Sat 15.03.14 Mon 17.03.14
731 Remove bearing 8 hrs Thu 27.03.14 Fri 28.03.14
732 Inspection 8 hrs Fri 28.03.14 Sat 29.03.14
733 F_215038 Replave Radial Key F_215038 13 hrs Fri 28.03.14 Sat 29.03.14
734 F_219255 Lube oil Inlet piping, check Straub Couplings F_219255 , 7 hrs Fri 28.03.14 Fri 28.03.14
Straub
735 Cleaning and minor repair 8 hrs Sat 29.03.14 Sat 29.03.14
736 Assembly bearing 8 hrs Sat 29.03.14 Mon 31.03.14
737 Assembly / close pedestal , 10 hrs Mon 31.03.14 Tue 01.04.14
738 Bearing pedestal (IP / LP) (, ) 16,23 dys Mon 17.03.14 Wed 02.04.14
739 Open bearing pedestal 7 hrs Mon 17.03.14 Mon 17.03.14
740 Remove bearing 3 hrs Sat 29.03.14 Mon 31.03.14
741 Inspection 7 hrs Mon 31.03.14 Mon 31.03.14
742 F_219255 Lube oil Inlet piping, check Straub Couplings F_219255 , 7 hrs Mon 31.03.14 Mon 31.03.14
Straub
743 Cleaning and minor repair 7 hrs Mon 31.03.14 Tue 01.04.14
744 Assembly bearing 5 hrs Tue 01.04.14 Wed 02.04.14
745 Assembly, close bearing pedestal , 7 hrs Wed 02.04.14 Wed 02.04.14
746 Bearing pedestal ( LP/rear) (, ) 4,82 dys Wed 02.04.14 Mon 07.04.14
747 Open bearing pedestal 7 hrs Wed 02.04.14 Thu 03.04.14
748 Remove bearing 3 hrs Thu 03.04.14 Thu 03.04.14
749 Inspection 7 hrs Thu 03.04.14 Fri 04.04.14
750 F_219255 Lube oil Inlet piping, check Straub Couplings F_219255 , 7 hrs Thu 03.04.14 Fri 04.04.14
Straub
751 Cleaning and minor repair 7 hrs Fri 04.04.14 Sat 05.04.14
752 Assembly bearing 5 hrs Sat 05.04.14 Sat 05.04.14
753 Assembly, close bearing pedestal , 7 hrs Sat 05.04.14 Mon 07.04.14
754 Coupling run out test (HP-IP) (, ) 0,14 dys Tue 18.03.14 Tue 18.03.14
755 SSS - cluch run - out test SSS 3 hrs Tue 18.03.14 Tue 18.03.14
756 Coupling run - out test (IP - LP) (, ) 0,14 dys Tue 18.03.14 Tue 18.03.14
757 Run - out test 3 hrs Tue 18.03.14 Tue 18.03.14
758 Coupling run - out test ( LP - Gen.) ( ) 0,14 dys Tue 18.03.14 Tue 18.03.14
759 Run - out test 3 hrs Tue 18.03.14 Tue 18.03.14
760 Turbine control and stop valve 22,05 dys Fri 14.03.14 Sat 05.04.14
761 HP control valve 12,91 dys Fri 14.03.14 Thu 27.03.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 13 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
762 Remove actuator 4 hrs Fri 14.03.14 Fri 14.03.14
763 Disassembly control valve 8 hrs Sat 15.03.14 Sat 15.03.14
764 Inspection 4 hrs Mon 17.03.14 Tue 18.03.14
765 Cleaning and minor repair 21 hrs Tue 18.03.14 Thu 20.03.14
766 FSI_219896 HP-CV Bushing DN160 FSI_219896 DN160 HP-CV 78 hrs Sat 15.03.14 Tue 25.03.14
767 Assembly control valve 8 hrs Tue 25.03.14 Wed 26.03.14
768 FSI_216701 HP Valve Block: Secure Screw FSI_216701 : 7 hrs Wed 26.03.14 Thu 27.03.14
Connection
769 Assembly actuator to valve 3 hrs Thu 27.03.14 Thu 27.03.14
770 HP stop valve 13,09 dys Sat 15.03.14 Fri 28.03.14
771 Remove actuator 4 hrs Sat 15.03.14 Mon 17.03.14
772 Disassembly stop valve 7 hrs Mon 17.03.14 Mon 17.03.14
773 Inspection 5 hrs Thu 20.03.14 Thu 20.03.14
774 Cleaning and minor repair 21 hrs Thu 20.03.14 Sat 22.03.14
775 Assembly stop valve 5 hrs Thu 27.03.14 Thu 27.03.14
776 FSI_216701 HP Valve Block: Secure Screw FSI_216701 : 7 hrs Thu 27.03.14 Fri 28.03.14
Connection
777 Assembly actuator to valve 4 hrs Fri 28.03.14 Fri 28.03.14
778 IP control / stop valve left side (MKRA) / 17,95 dys Fri 14.03.14 Tue 01.04.14
, (MKRA)
779 Remove actuator control & stop side 7 hrs Fri 14.03.14 Sat 15.03.14

780 Disassembly control valve side 10 hrs Sat 15.03.14 Mon 17.03.14
781 Disassembly stop valve side 13 hrs Mon 17.03.14 Tue 18.03.14
782 Disassembly stop valve head from valve body 20 hrs Tue 18.03.14 Thu 20.03.14
(inspect pilot stroke) ( )
783 Inspection, cleaning and minor repair , 52 hrs Thu 20.03.14 Wed 26.03.14
784 Reassembly stop valve head to valve body 13 hrs Wed 26.03.14 Fri 28.03.14
785 FSI_216707 Valve Block: Secure Screw connection FSI_216701 : 1 hr Fri 28.03.14 Fri 28.03.14

786 Assembly stop valve side 13 hrs Fri 28.03.14 Sat 29.03.14
787 Assembly control valve side 13 hrs Sat 29.03.14 Mon 31.03.14
788 Assembly the actuators to valves 7 hrs Mon 31.03.14 Tue 01.04.14
789 IP control / stop valve right side (MKRA) / 18,05 dys Tue 18.03.14 Sat 05.04.14
, (MKRA)
790 Remove actuator control & stop side 7 hrs Tue 18.03.14 Wed 19.03.14

791 Disassembly control valve side 10 hrs Wed 19.03.14 Thu 20.03.14
792 Disassembly stop valve side 13 hrs Thu 20.03.14 Fri 21.03.14
793 Disassembly stop valve head from valve body 20 hrs Fri 21.03.14 Mon 24.03.14
(inspect pilot stroke) ( )
794 Inspection, cleaning and minor repair , 52 hrs Tue 25.03.14 Mon 31.03.14
795 Reassembly stop valve head to valve body 13 hrs Mon 31.03.14 Wed 02.04.14
796 Assembly stop valve side 13 hrs Wed 02.04.14 Thu 03.04.14
797 FSI_218528 Replace Clamping ring and belonging FSI_218528 1 hr Thu 03.04.14 Thu 03.04.14
bolts
798 FSI_216707 Valve Block: Secure Screw connection FSI_216701 : 1 hr Thu 03.04.14 Thu 03.04.14

799 Assembly control valve side 13 hrs Thu 03.04.14 Fri 04.04.14
800 Assembly the actuators to valves 7 hrs Sat 05.04.14 Sat 05.04.14
801 Butterfly valves 6,36 dys Sat 29.03.14 Fri 04.04.14
802 LP-butterfly control / stop - valves & 6,36 dys Sat 29.03.14 Fri 04.04.14
actuator (ADAMS)
803 Support the piping (ADAMS)
5 hrs Sat 29.03.14 Sat 29.03.14
804 Remove assembly (actuator with valve) ( ) 7 hrs Sat 29.03.14 Mon 31.03.14
805 Remove the actuator from the assembly 4 hrs Mon 31.03.14 Mon 31.03.14
806 Valve disc inspection 3 hrs Mon 31.03.14 Mon 31.03.14
807 Disassemble the valves 4 hrs Mon 31.03.14 Tue 01.04.14
808 Cleaning and minor repair 5 hrs Tue 01.04.14 Tue 01.04.14
809 Assemble the valves 4 hrs Tue 01.04.14 Wed 02.04.14
810 Fit the actuator in to the assembly 5 hrs Wed 02.04.14 Wed 02.04.14
811 Install assembly (actuator with valve) ( ) 5 hrs Wed 02.04.14 Thu 03.04.14
812 Normalize piping 4 hrs Thu 03.04.14 Thu 03.04.14
813 LP- steam strainer 1,09 dys Thu 03.04.14 Fri 04.04.14
814 Remove steam strainer 3 hrs Thu 03.04.14 Thu 03.04.14
815 Inspection 1 hr Thu 03.04.14 Thu 03.04.14
816 Cleaning and minor repair 5 hrs Fri 04.04.14 Fri 04.04.14
817 Assemble the steam strainer 3 hrs Fri 04.04.14 Fri 04.04.14
818 NRV (Check valves) in extraction pipes NRV ( )
12,18 dys Wed 19.03.14 Mon 31.03.14
819 Inspection of the check valves 104 hrs Wed 19.03.14 Mon 31.03.14
820 Auxiliary works 23,96 dys Fri 14.03.14 Mon 07.04.14
821 Turbine piping system complete 8,82 dys
Sat 29.03.14 Mon 07.04.14
822 Visual check for tightness or damages 7 hrs Sat 29.03.14 Mon 31.03.14
823 Check pipe condition & pipe supports 7 hrs Mon 31.03.14 Tue 01.04.14
824 Drain valves and dirt traps 39 hrs Tue 01.04.14 Sat 05.04.14
825 Cleaning and minor repair 13 hrs Sat 05.04.14 Mon 07.04.14
826 Foundation bolts 1,14 dys Thu 20.03.14 Fri 21.03.14
827 Check anchor bolts 13 hrs Thu 20.03.14 Fri 21.03.14
828 Gland steam system 5,82 dys
Fri 14.03.14 Thu 20.03.14
829 Water injection 13 hrs Fri 14.03.14 Sat 15.03.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 14 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
830 Gland steam condenser 26 hrs Sat 15.03.14 Wed 19.03.14
831 Drains 7 hrs Wed 19.03.14 Thu 20.03.14
832 ST Generator extended B-insp B (2 35,45 dys Tue 11.03.14 Tue 15.04.14
(2Shift/7Days/11Hours) 11 7 )
833 Outage milestones 35,45 dys Tue 11.03.14 Tue 15.04.14
834 Shut down / cool down of ST 0 dys Tue 11.03.14 Tue 11.03.14
835 Work permit issued 0 dys Fri 14.03.14 Fri 14.03.14
836 Start of Generator work 0 dys Fri 14.03.14 Fri 14.03.14
837 Release for coupling alignment 0 dys Fri 28.03.14 Fri 28.03.14
838 Generator ready for Motoroll 0 dys Mon 14.04.14 Mon 14.04.14
839 End of Inspection 0 dys Tue 15.04.14 Tue 15.04.14
840 F_210880 Generator Extended B-Inspection F_210880 B 31,91 dys Fri 14.03.14 Tue 15.04.14

841 Disassembly 6,82 dys Fri 14.03.14 Fri 21.03.14


842 Instrumentation disconnect & dismantle 5 hrs Fri 14.03.14 Fri 14.03.14
843 Enclosure disconnect cables & remove e-components 8 hrs Fri 14.03.14 Sat 15.03.14

844 Enclosure (mechanical) dismantle 10 hrs Sat 15.03.14 Sat 15.03.14


845 Remove shaft seal & disconnect brush gear 8 hrs Sat 15.03.14 Sat 15.03.14
846 Dismantle brush gear 8 hrs Sat 15.03.14 Sun 16.03.14
847 Remove shaft seal & bearing cover 12 hrs Sun 16.03.14 Sun 16.03.14
848 Remove shaft seal & outer end shield 14 hrs Sun 16.03.14 Mon 17.03.14
849 Remove inner shield and diffuser 14 hrs Mon 17.03.14 Tue 18.03.14
850 Dismantle fan blades 8 hrs Tue 18.03.14 Tue 18.03.14
851 Split coupling towards ST 13 hrs Tue 18.03.14 Wed 19.03.14
852 Check coupling alignment 4 hrs Wed 19.03.14 Wed 19.03.14
853 Remove bearings & pedestal 16 hrs Wed 19.03.14 Thu 20.03.14
854 Install sub-structure rotor 16 hrs Wed 19.03.14 Thu 20.03.14
855 Install scaffold arround the sbustructure 26 hrs Wed 19.03.14 Thu 20.03.14
856 Remove generator rotor 16 hrs Thu 20.03.14 Fri 21.03.14
857 Disconnect flexible links 5 hrs Sat 15.03.14 Sat 15.03.14
858 Remove coolers 13 hrs Sat 15.03.14 Sun 16.03.14
859 Inspection 5,45 dys Fri 21.03.14 Wed 26.03.14
860 Inspect generator 5,45 dys Fri 21.03.14 Wed 26.03.14
861 Clean stator winding 10 hrs Fri 21.03.14 Fri 21.03.14
862 F_219374 Diagnosis-Inspection F_219374 (WIDIPRO) 4,55 dys Sat 22.03.14 Wed 26.03.14
(WIDIPRO)
863 Visual checks 16 hrs Sat 22.03.14 Sun 23.03.14
864 Widipro tests WIDIPRO 16 hrs Sun 23.03.14 Mon 24.03.14
865 Electrical tests 16 hrs Mon 24.03.14 Tue 25.03.14
866 Reporting 1 edy Tue 25.03.14 Wed 26.03.14
867 Bearings 10 hrs Fri 21.03.14 Fri 21.03.14
868 Shaft grounding 5 hrs Sun 23.03.14 Sun 23.03.14
869 Inspection & pressure test air coolers 39 hrs Fri 21.03.14 Sun 23.03.14
870 Clean all components 26 hrs Sun 23.03.14 Mon 24.03.14
871 Minor repairs 26 hrs Mon 24.03.14 Wed 26.03.14
872 Enclosure clean, inspect & repair e-components , 5 hrs Sun 23.03.14 Sun 23.03.14
873 Enclosure (mechanical) minor repair 5 hrs Sun 23.03.14 Sun 23.03.14
874 GT / gen coupling and interm. shaft clean & inspect 8 hrs Sun 23.03.14 Mon 24.03.14
,
875 Lube oil pump inspection, cleaning and minor repair , 18 hrs Mon 24.03.14 Tue 25.03.14

876 Instrumentation check / calibrate 26 hrs Tue 25.03.14 Wed 26.03.14
877 Stator 2,36 dys Mon 24.03.14 Wed 26.03.14
878 Inspect stator and casing 10 hrs Mon 24.03.14 Mon 24.03.14
879 Minor repair works on stator winiding 21 hrs Mon 24.03.14 Tue 25.03.14
880 Cleaning works 21 hrs Tue 25.03.14 Wed 26.03.14
881 Piping system complete 0,41 dys Mon 24.03.14 Tue 25.03.14
882 Visual check for tightness and damage 3 hrs Mon 24.03.14 Tue 25.03.14
883 Check strainers and filters 3 hrs Tue 25.03.14 Tue 25.03.14
884 Cleaning and minor repair 3 hrs Tue 25.03.14 Tue 25.03.14
885 Generator cooling system 0,95 dys Tue 25.03.14 Wed 26.03.14
886 Visual check & leakage test 13 hrs Tue 25.03.14 Tue 25.03.14
887 Minor repair & cleaning 5 hrs Tue 25.03.14 Wed 26.03.14
888 Functional check . 3 hrs Wed 26.03.14 Wed 26.03.14
889 Brush gear 1,64 dys Mon 24.03.14 Wed 26.03.14
890 Inspect brush gear 5 hrs Mon 24.03.14 Tue 25.03.14
891 Cleaning & minor repair 10 hrs Wed 26.03.14 Wed 26.03.14
892 Assembly 19,91 dys Wed 26.03.14 Tue 15.04.14
893 Install rotor 16 hrs Wed 26.03.14 Thu 27.03.14
894 Install bearings & pedesal 18 hrs Thu 27.03.14 Fri 28.03.14
895 Check alignment 4 hrs Mon 07.04.14 Mon 07.04.14
896 Stator alignment (if nescessary) ( ) 2,95 dys Mon 07.04.14 Thu 10.04.14
897 Loose anchor bolts 13 hrs Mon 07.04.14 Tue 08.04.14
898 Align generator 21 hrs Tue 08.04.14 Wed 09.04.14
899 Tighten anchor bolts 13 hrs Wed 09.04.14 Wed 09.04.14
900 Adjust guige keys 5 hrs Wed 09.04.14 Thu 10.04.14
901 Lock anchor bolts 13 hrs Thu 10.04.14 Thu 10.04.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 15 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
902 Close coupling towards ST 13 hrs Wed 09.04.14 Thu 10.04.14
903 Install fan blades 8 hrs Thu 10.04.14 Thu 10.04.14
904 Install shields & diffuser 16 hrs Thu 10.04.14 Fri 11.04.14
905 Install outer end shield and shaft seals 16 hrs Fri 11.04.14 Sat 12.04.14
906 Install bearing cover and shaft seal 16 hrs Sun 13.04.14 Sun 13.04.14
907 Reinstall brush gear and align 10 hrs Sat 12.04.14 Sat 12.04.14
908 Install shaft seal & connect brush gear 10 hrs Sat 12.04.14 Sun 13.04.14
909 Install coolers 20 hrs Thu 27.03.14 Fri 28.03.14
910 Dismantle sub-structure rotor 13 hrs Fri 28.03.14 Fri 28.03.14
911 Remove scaffold 13 hrs Fri 28.03.14 Fri 28.03.14
912 Connect flexible links 5 hrs Thu 27.03.14 Thu 27.03.14
913 Instrumentation install & connect 10 hrs Sun 13.04.14 Mon 14.04.14
914 Enclosure (mechanical) install 16 hrs Mon 14.04.14 Tue 15.04.14
915 Enclosure install e-components & connect cables 10 hrs Tue 15.04.14 Tue 15.04.14
916 Plant Scope (1Shift/6Days/10Hours) (1 10 6 45 dys Tue 11.03.14 Fri 25.04.14
917 Milestones 45 dys Tue 11.03.14 Fri 25.04.14
918 Plant Shut Down 0 dys Tue 11.03.14 Tue 11.03.14
919 GT Standstill 0 dys Wed 12.03.14 Wed 12.03.14
920 Ready for High Voltage Outage on GT 0 dys Wed 12.03.14 Wed 12.03.14

921 ST Standstill 0 dys Fri 14.03.14 Fri 14.03.14
922 Ready for High Voltage Outage on ST 0 dys Wed 19.03.14 Wed 19.03.14

923 Rotor in 0 dys Wed 09.04.14 Wed 09.04.14
924 Start Hotcommissioning 0 dys Mon 21.04.14 Mon 21.04.14
925 Finish Hotcommissioning 0 dys Fri 25.04.14 Fri 25.04.14
926 I&C C-INSP (1 shift / 6 days / 11 hours) C (1 11 6 ) 4,91 dys Thu 27.03.14 Tue 01.04.14
927 F_219915 GT CONTROL F_219915 26 hrs Thu 27.03.14 Mon 31.03.14
928 F_219918 HUMAN MACHINE INTERFACE F_219918 - 12 hrs Mon 31.03.14 Tue 01.04.14
929 F_217843 PLANT ELECTRICAL C-INSP (1 shift / F_217843 C (1 35,41 dys Wed 12.03.14 Wed 16.04.14
6 days / 11 hours) 11 6 )
930 High voltage outage 16,09 dys Wed 12.03.14 Fri 28.03.14
931 GENERATOR CIRCUIT BREAKER 20 hrs Wed 12.03.14 Thu 13.03.14
932 STEP-UP TRANSFORMER 29 hrs Fri 14.03.14 Mon 17.03.14
933 STATION SERVICE TRANSFORMER 29 hrs Mon 17.03.14 Thu 20.03.14
934 BUSDUCT & NEUTRAL CUBICAL 2,05 dys Thu 20.03.14 Sat 22.03.14
935 GENERATOR+TRANSF BUS DUCT 21 hrs Thu 20.03.14 Sat 22.03.14
936 GENERATOR NEUTRAL POINT 5 hrs Fri 21.03.14 Sat 22.03.14
937 STATIC STARTING DEVICE 43 hrs Sat 22.03.14 Fri 28.03.14
938 Electrical checks and cold commissioning 19,32 dys Fri 28.03.14 Wed 16.04.14

939 AUXILIARY TRANSFORMER 13 hrs Fri 28.03.14 Sat 29.03.14
940 EXCITATION & VOLTAGE CONTROL 26 hrs Sat 29.03.14 Wed 02.04.14
941 EXCITATION TRANSFORMER 13 hrs Wed 02.04.14 Thu 03.04.14
942 DIESEL GENERATOR 13 hrs Thu 03.04.14 Fri 04.04.14
943 SYNCHRONISING, MEASURING, METERING , 20 hrs Fri 04.04.14 Mon 07.04.14
944 BTL, DC, UPS BTL, DC, 6 dys Mon 07.04.14 Sun 13.04.14
945 System checks 20 hrs Mon 07.04.14 Wed 09.04.14
946 Battery discharge test (2 banks) optional ( 4 edys Wed 09.04.14 Sun 13.04.14
947 GENERATOR & TRANSFORMER PROTECTION 29 hrs Mon 14.04.14 Wed 16.04.14
948 WSC C-INSP (1 shift / 6 days / 11 hours) C WSC (1 11 6 ) 39,91 dys Fri 14.03.14 Wed 23.04.14
949 Scaffolding works 39,91 dys Fri 14.03.14 Wed 23.04.14
950 Install Scaffoldings 5,09 dys Fri 14.03.14 Wed 19.03.14
951 ST 2,86 dys Fri 14.03.14 Mon 17.03.14
952 F_218869 C WATER COOLED CONDENSER F_218869 C 7 hrs Fri 14.03.14 Sat 15.03.14

953 F_218927 EJECTOR C F_218927 C 3 hrs Sat 15.03.14 Sat 15.03.14


954 F_218888 FEEDWATER TANK F_218888 4 hrs Sat 15.03.14 Sat 15.03.14
955 F_218275 ATMOSPHERIC DRAIN VESSEL F_218275
3 hrs Mon 17.03.14 Mon 17.03.14
956 OEM Scope Valves 2,23 dys Mon 17.03.14 Wed 19.03.14
957 F_217745 BYPASS HP BLOCK F_217745 7 hrs Mon 17.03.14 Mon 17.03.14
958 F_217745 BYPASS IP BLOCK F_217745 7 hrs Tue 18.03.14 Tue 18.03.14
959 F_217745 BYPASS LP BLOCK F_217745 7 hrs Tue 18.03.14 Wed 19.03.14
960 F_218928 WSC VALVES F_218928 WSC 4 hrs Wed 19.03.14 Wed 19.03.14
961 Remove Scaffoldings 34,91 dys Wed 19.03.14 Wed 23.04.14
962 ST 5 dys Wed 19.03.14 Mon 24.03.14
963 F_218869 C WATER COOLED CONDENSER F_218869 C 7 hrs Wed 19.03.14 Thu 20.03.14

964 F_218927 EJECTOR C F_218927 C 3 hrs Sat 22.03.14 Sat 22.03.14


965 F_218888 FEEDWATER TANK F_218888 4 hrs Sat 22.03.14 Sat 22.03.14
966 F_218275 ATMOSPHERIC DRAIN VESSEL F_218275
3 hrs Mon 24.03.14 Mon 24.03.14
967 OEM Scope Valves 24,95 dys Sat 29.03.14 Wed 23.04.14
968 F_217745 BYPASS HP BLOCK F_217745 7 hrs Sat 29.03.14 Mon 31.03.14
969 F_217745 BYPASS IP BLOCK F_217745 7 hrs Thu 10.04.14 Thu 10.04.14
970 F_217745 BYPASS LP BLOCK F_217745 7 hrs Tue 22.04.14 Tue 22.04.14
971 F_218928 WSC VALVES F_218928 WSC 4 hrs Wed 23.04.14 Wed 23.04.14
972 Insulation works 38,18 dys Sat 15.03.14 Tue 22.04.14
973 Remove Insulation 4,09 dys Sat 15.03.14 Wed 19.03.14
Task Rolled Up Task Split Inactive Milestone Duration-only Start-only
Issued: M.Floric Page 16 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
974 ST 1,86 dys Sat 15.03.14 Mon 17.03.14
975 F_218927 EJECTOR C F_218927 C 3 hrs Sat 15.03.14 Sat 15.03.14
976 F_218888 FEEDWATER TANK F_218888 3 hrs Mon 17.03.14 Mon 17.03.14
977 OEM Scope Valves 2,23 dys Mon 17.03.14 Wed 19.03.14
978 F_217745 BYPASS HP BLOCK F_217745 7 hrs Mon 17.03.14 Mon 17.03.14
979 F_217745 BYPASS IP BLOCK F_217745 7 hrs Tue 18.03.14 Tue 18.03.14
980 F_217745 BYPASS LP BLOCK F_217745 7 hrs Tue 18.03.14 Wed 19.03.14
981 F_218928 WSC VALVES F_218928 WSC 4 hrs Wed 19.03.14 Wed 19.03.14
982 Install Insulation 32,09 dys Fri 21.03.14 Tue 22.04.14
983 ST 0,73 dys Fri 21.03.14 Sat 22.03.14
984 F_218927 EJECTOR C F_218927 C 3 hrs Fri 21.03.14 Sat 22.03.14
985 F_218888 FEEDWATER TANK F_218888 1 hr Sat 22.03.14 Sat 22.03.14
986 OEM Scope Valves 25,09 dys Fri 28.03.14 Tue 22.04.14
987 F_217745 BYPASS HP BLOCK F_217745 7 hrs Fri 28.03.14 Sat 29.03.14
988 F_217745 BYPASS IP BLOCK F_217745 7 hrs Wed 09.04.14 Thu 10.04.14
989 F_217745 BYPASS LP BLOCK F_217745 7 hrs Mon 21.04.14 Tue 22.04.14
990 F_218928 WSC VALVES F_218928 WSC 4 hrs Tue 22.04.14 Tue 22.04.14
991 WSC Inspection WSC 38,14 dys Sat 15.03.14 Tue 22.04.14
992 Alstom Scope Alstom 9 dys Sat 15.03.14 Mon 24.03.14
993 ST 9 dys Sat 15.03.14 Mon 24.03.14
994 F_218869 C WATER COOLED CONDENSER F_218869 C 33 hrs Sat 15.03.14 Wed 19.03.14

995 F_218927 EJECTOR C F_218927 C 22 hrs Wed 19.03.14 Fri 21.03.14


996 F_218888 FEEDWATER TANK F_218888 3 hrs Fri 21.03.14 Sat 22.03.14
997 F_218275 ATMOSPHERIC DRAIN VESSEL F_218275
12 hrs Sat 22.03.14 Mon 24.03.14
998 OEM Scope Valves 35,27 dys Tue 18.03.14 Tue 22.04.14
999 F_217745 BYPASS HP BLOCK F_217745
10,36 dys Tue 18.03.14 Fri 28.03.14
1000 HP BYPASS WATER INJECTION CONTROL 20 hrs Tue 18.03.14 Wed 19.03.14
VALVE
1001 HP BYPASS CONTROL VALVE 39 hrs Thu 20.03.14 Mon 24.03.14
1002 HP BYPASS STOP VALVE 39 hrs Mon 24.03.14 Fri 28.03.14
1003 F_217745 BYPASS IP BLOCK F_217745
11,91 dys Fri 28.03.14 Wed 09.04.14
1004 IP BYPASS WATER INJECTION CONTROL 20 hrs Fri 28.03.14 Mon 31.03.14
VALVE
1005 IP BYPASS CONTROL VALVE 39 hrs Mon 31.03.14 Fri 04.04.14
1006 IP BYPASS STOP VALVE 39 hrs Fri 04.04.14 Wed 09.04.14
1007 F_217745 BYPASS LP BLOCK F_217745 11,91 dys Wed 09.04.14 Mon 21.04.14
1008 LP BYPASS WATER INJECTION CONTROL 20 hrs Wed 09.04.14 Fri 11.04.14
VALVE
1009 LP BYPASS CONTROL VALVE 39 hrs Fri 11.04.14 Wed 16.04.14
1010 LP BYPASS STOP VALVE 39 hrs Wed 16.04.14 Mon 21.04.14
1011 F_218928 WSC VALVES F_218928 WSC 12 hrs Mon 21.04.14 Tue 22.04.14
1012 HRSG C-INSP (1 shift / 6 days / 10 hours) C - (1 10 16,91 dys Fri 14.03.14 Mon 31.03.14
1013 Scaffolding works 9,91 dys Mon 17.03.14 Thu 27.03.14
1014 Install Scaffoldings 1,14 dys Mon 17.03.14 Tue 18.03.14
1015 F_218573 HEAT EXCHANGER IN GAS PATH & F_218573 10 hrs Mon 17.03.14 Tue 18.03.14
DRUMS
1016 F_218653 HRSG VALVE F_218653 - 3 hrs Tue 18.03.14 Tue 18.03.14
1017 Remove Scaffoldings 4,95 dys Sat 22.03.14 Thu 27.03.14
1018 F_218573 HEAT EXCHANGER IN GAS PATH & F_218573 10 hrs Sat 22.03.14 Mon 24.03.14
DRUMS
1019 F_218653 HRSG VALVE F_218653 - 3 hrs Wed 26.03.14 Thu 27.03.14
1020 Insulation works 12,91 dys Tue 18.03.14 Mon 31.03.14
1021 Remove Insulation 0,77 dys Tue 18.03.14 Wed 19.03.14
1022 F_218653 HRSG VALVE F_218653 - 3 hrs Tue 18.03.14 Tue 18.03.14
1023 F_218690 HRSG BLOWDOWN SYSTEM F_218690 - 2 hrs Tue 18.03.14 Wed 19.03.14
1024 Install Insulation 4,95 dys Wed 26.03.14 Mon 31.03.14
1025 F_218653 HRSG VALVE F_218653 - 3 hrs Wed 26.03.14 Wed 26.03.14
1026 F_218690 HRSG BLOWDOWN SYSTEM F_218690 - 2 hrs Mon 31.03.14 Mon 31.03.14
1027 HRSG Inspection - 16,82 dys Fri 14.03.14 Mon 31.03.14
1028 F_218647 HRSG DUCTING, PIPING & STRUCTURES F_218647 - 26 hrs Fri 14.03.14 Tue 18.03.14
1029 F_218573 HEAT EXCHANGER IN GAS PATH & F_218573 39 hrs Tue 18.03.14 Sat 22.03.14
DRUMS
1030 F_218653 HRSG VALVE F_218653 - 33 hrs Sat 22.03.14 Wed 26.03.14
1031 F_218706 HRSG DESUPERHEATER F_218653 - 20 hrs Wed 26.03.14 Fri 28.03.14
1032 F_218690 HRSG BLOWDOWN SYSTEM F_218690 - 17 hrs Fri 28.03.14 Mon 31.03.14
1033 Commissioning ST/ST GENO/WSC , 8,2 dys Tue 15.04.14 Wed 23.04.14
1034 Generator cold commissioning 1,93 dys
Fri 18.04.14 Sun 20.04.14
1035 Cold commisioning 13 hrs Fri 18.04.14 Sun 20.04.14
1036 ST cold commissioning 5,11 dys Tue 15.04.14 Sun 20.04.14
1037 Turbine drains and LPT hood spray - 7 hrs Tue 15.04.14 Wed 16.04.14
1038 Gland steam system 3 hrs Wed 16.04.14 Wed 16.04.14
1039 Lube oil supply system 1 hr Wed 16.04.14 Wed 16.04.14
1040 ST control and protection equipment 3 hrs Wed 16.04.14 Wed 16.04.14
1041 Jacking oil and turning gear system 4 hrs Wed 16.04.14 Thu 17.04.14
1042 Valve function test and calibration 16 hrs Thu 17.04.14 Fri 18.04.14
1043 Test of trip circuit 13 hrs Fri 18.04.14 Sun 20.04.14
1044 F_218708 START UP F_218708 4,18 dys Sat 19.04.14 Wed 23.04.14
1045 Prepare for start up (incl Walkdown) ( ) 26 hrs Sat 19.04.14 Mon 21.04.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 17 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress
abcd GT24/26 Standard C-Inspection
Draft 3
Tentative Schedule 1AHX 615 174 Rev. A
Calendar: GT 2 shift / 11 hours / 7 days
GT Generator 1 shift/10 hours/ 6 days
IFSi list rev - 2 oct 2013 v 4 Steamturbine 1 shift/10 hours/ 6 days
ST Generator 2 shift / 11 hours / 7 days

ID Projects Projects_rus Duration Planed Start Planed Finish Planned 24 Feb '14 03 Mar '14 10 Mar '14 17 Mar '14 24 Mar '14 31 Mar '14 07 Apr '14 14 Apr '14 21 Apr '14 28 A
23 25 27 01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
1046 Start up of HRSG - 26 hrs Mon 21.04.14 Wed 23.04.14
1047 F_218998 WSC START UP F_218708 WSC 2,09 dys Sun 20.04.14 Tue 22.04.14
1048 System check and walk down 13 hrs Sun 20.04.14 Mon 21.04.14
1049 Start up of WSC WSC 13 hrs Mon 21.04.14 Tue 22.04.14
1050 ST hot commissioning 0,82 dys Mon 21.04.14 Tue 22.04.14
1051 Bypass operation 3 hrs Mon 21.04.14 Mon 21.04.14
1052 Start and run up of ST and min lod 5 ehrs Mon 21.04.14 Mon 21.04.14
1053 Partial stroke test 1 ehr Mon 21.04.14 Mon 21.04.14
1054 Readings, observation and tests , 5 ehrs Mon 21.04.14 Tue 22.04.14
1055 Test at 100% load; readings, observation and tests 100%- , , 5 ehrs Tue 22.04.14 Tue 22.04.14

1056 Hot commissioning according load profile 3,35 dys
Mon 21.04.14 Fri 25.04.14
1057 Milstones 3,07 dys Mon 21.04.14 Fri 25.04.14
1058 First Ignition 0 dys Mon 21.04.14 Mon 21.04.14
1059 Fuel Gas recommissioned 0 dys Thu 24.04.14 Thu 24.04.14
1060 Handover to client 0 dys Fri 25.04.14 Fri 25.04.14
1061 Motor roll 1,27 dys Mon 21.04.14 Tue 22.04.14
1062 Motoroll, Flame off test, Idle run, overspeed test,TAT1 , 30 ehrs Mon 21.04.14 Tue 22.04.14
verification, EV Fulload, SEV on , ,
1063 Fuel Gas recommissioning GT , TAT1,
1,64 dys Tue 22.04.14 Thu 24.04.14
1064 Partload mapping, Baselaod adj, standard readings , , 40 ehrs Tue 22.04.14 Thu 24.04.14

1065 Final settings implementation and handover 0,44 dys Thu 24.04.14 Fri 25.04.14

1066 Operation concept implementation 4 ehrs Thu 24.04.14 Thu 24.04.14


1067 Start up 6 ehrs Thu 24.04.14 Fri 25.04.14
1068 Handover to client 0 dys Fri 25.04.14 Fri 25.04.14
1069 Close out tasks 7 dys Mon 21.04.14 Mon 28.04.14
1070 Inspection and reporting (missing, damaged) on all tools and 7 edys Mon 21.04.14 Mon 28.04.14
devices (, ...)
1071 Inspection and reporting of SIM material SIM 7 edys Mon 21.04.14 Mon 28.04.14
1072 Inspection and reporting on all material used 7 edys Mon 21.04.14 Mon 28.04.14
1073 Prepare reports and documentation 7 edys Mon 21.04.14 Mon 28.04.14
1074 Packing and returning of material 7 edys Mon 21.04.14 Mon 28.04.14
1075 Task to show critical path , 90 ehrs Fri 25.04.14 Mon 28.04.14

Task Rolled Up Task Split Inactive Milestone Duration-only Start-only


Issued: M.Floric Page 18 of 33
Reviewed: Milestone Slack Inactive Task Inactive Summary Manual Summary Rollup Finish-only
Approved:
Summary Critical Inactive Task Manual Task Manual Summary Progress